SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 135

IN THE HIGH COURT OF DELHI AT NEW DELHI
Amit Bansal, J
VEDANTA LIMITED – Appellant
Versus
SHENZHEN SHANDONG NUCLEAR POWER CONSTRUCTION COMPANY LIMITED – Respondent
OMP (ENF.) (COMM.) 225/2018 | EX.APPL.(OS) 553/2019 | I.A. 6421/2019 | EX.APPL.(OS) 2944/2022



Advocates:
For the Appellants/Petitioners:Mr. Dhruv Mehta, Senior Advocate, Ms. Ranjana Roy Gawai, Ms. Vasudha Sen, Mr. Vineet Wadhwa, Mr. Keith Vargese, Mr. Shreyas Mittal
For the Respondents:Mr. Gourab Banerji, Senior Advocate, Mr. Anshuman Pande, Mr. Abhishek Bhushan Singh

Payment recognized under decree requires unconditional compliance; bank guarantees do not suffice, and interest continues until funds are available to the decree holder.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Enforcement of Arbitral Award - Enforcement petition filed to recover amounts in compliance with arbitral tribunal's award dated 9th November 2017 - Appeal by judgment debtor challenging payment order was dismissed - Deposit made by judgment debtor was deemed insufficient for claim satisfaction - Interest liability applicable until decree holder could access funds. (Paras 1, 6, 31, 47)

(B) Payment under Decree - Order XXI Rule 1 of CPC - Payment recognized only if unconditional; bank guarantees do not count as payments - Interest continues to accrue until conditions for withdrawal are met. (Paras 7, 18, 28)

Facts of the case:
The petitioner sought enforcement of an arbitral award, with multiple proceedings regarding amounts owed dating back to 2012, leading to disputes over interest calculations and claim eligibility based on deposits made and guarantees provided. The judgment debtor contested the timing and conditions under which payment was deemed to have occurred. (Paras 2.1 - 2.20)

Findings of Court:
The court held that interest ceases only when the decree holder has unimpeded access to payments owing from the judgment debtor, which was not the case until 8th August 2019. (Paras 51, 52)

Issues: Whether the decree holder is entitled to recover interest on awarded amounts till conditions for withdrawal are met and if deposit constituted full payment under the law. (Paras 6, 18)

Ratio Decidendi: The ruling established that until a decree holder can freely access deposited amounts, interest accrues. The court clarified that bank guarantees do not equate to actual payments owed under the decree. (Paras 7, 51)

Result: Enforcement petition disposed; directions issued for revised calculation of amounts due. (Paras 53, 54)

Table of Content
1. enforcement petition for arbitral award (Para 1 , 2)
2. arguments by the decree holder's counsel (Para 3)
3. arguments by the judgment debtor's counsel (Para 4)
4. court's findings and analysis on interest (Para 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51)
5. final directions and disposition of petition (Para 53 , 54 , 55)

JUDGEMENT

AMIT BANSAL, J.

1. The present enforcement petition has been filed seeking enforcement of the Arbitral Award dated 9th November 2017 (hereinafter the “Arbitral Award”).

2. Brief factual background of the case is set out below:

2.1 On 18th April 2012, notice was issued on behalf of the claimant/ decree holder invoking the arbitration clause. The statement of claim was filed on behalf of the decree holder (claimant in the arbitration) on 17th October 2012.

2.2 On 12th December 2012, the Division Bench of Bombay High Court passed an order in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the Act’), arising out of a petition under Section 9 of the Act, directing the judgment debtor to furnish a security in the sum of Rs.187 crores to the decree holder. An SLP was filed against the said order, which was dismissed in July, 2013.

2.3 On 14th August 2013, a bank guarantee was furnished on behalf of the judgment debtor to the decree holder for a sum of Rs.187 crores, which continued during the pendency of the arbitration proceedings.

2.4 The Arbitral Award was passed by the Arbitral Tribunal on 9th November 2017.

2.5 On 12th February 2018, a Single Judge of this Court dismissed the petition under Section 34 of the Act filed on behalf of the judgment debtor.

2.6 The said decision was carried in appeal before the Division Bench by the judgment debtor under Section 37 of the Act. On 5th March 2018, the Division Bench directed the judgment debtor to deposit the entire amount as per the Arbitral Award, including interest calculated at 9% per annum, with the Registry of this Court. It was further directed that upon the deposit being made, the bank guarantee given by the judgment debtor to the decree holder would be returned.

2.7 On 23rd March 2018, at the request of the counsel appearing on behalf of the judgment debtor, the Division Bench permitted the judgment debtor to deposit a sum of Rs.152.22 crores in court during the course of the day, which was done by the judgment debtor.

2.8 The Division Bench dismissed the appeal filed by the judgment debtor on 30th August 2018.

2.9 On 14th September 2018, the present execution petition was filed by the decree holder seeking enforcement of the Arbitral Award.

2.10 On 24th September 2018, this Court directed the Registry to release Rs.60 crores to the decree holder with a caveat that decree holder will retain the said money in its Indian Bank Account till the SLP filed by the judgment debtor against the order of the Division Bench is listed.

2.11 On 11th October 2018, the Supreme Court disposed of the Special Leave Petition by modifying the interest rate on the Euro component of the Award from 9% per annum to London Interbank Offered Rate (LIBOR) plus 3%.

2.12 On 8th August 2019, the executing court directed the Registry to release a sum of Rs.34,69,20,245/- to the decree holder.

2.13 On 6th January 2020, the executing court passed an order that the amount deposited by the judgment debtor in this Court has to be adjusted towards the interest first and thereafter towards the principal amount. The Court also held that the Euro component of the Award would be converted into Indian Rupees as per the exchange rate prevalent on the date of filing of the claim petition i.e. 17th October 2012.

2.14 An appeal was filed by the decree holder against the judgment passed by the executing court on 6th January 2020, which was dismissed by the Division Bench on

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top