SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 238

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, Om Prakash Shukla, JJ
M/S. M.V. OMNI PROJECTS (INDIA) LTD. – Appellant
Versus
UNION OF INDIA THROUGH EXECUTIVE ENGINEER CPWD – Respondent
FAO(OS) (COMM) 110/2024



Advocates:
For the Appellants/Petitioners: Mr. Raj Shekhar Rao, Sr. Adv., Mr. Subodh Kr. Pathak, Mr. Amit Sinha, Mr. Abhishek Sandillya, Mr. Pawan Kumar Sharma, Mr. Wamic Wasim
For the Respondents: Mr. Ankur Mahindro, Mr. Ruchir Mishra, Mr. Rohan Taneja, Mr. Ankush Satija, Mr. Aditya Kapur, Mr. Mohit Dagar, Mr. Raghav Kalra, Mr. Animesh Dubey, Ms. Creesha Shashtri, Ms. Jhanak Setia, Ms. Radhika Agrawal

An arbitrator's appointment violating Section 12(5) of the Arbitration Act without an express written waiver is invalid, rendering any adjudicated award void.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 12(5) - Challenge to arbitral award - The High Court set aside the arbitral award on grounds of the arbitrator's ineligibility as per Section 12(5) due to non-compliance with appointment protocols. The court affirmed the Single Judge's decision confirming the appointment was void ab initio as the parties did not execute an express written agreement waiving this ineligibility. (Paras 5, 16, 28)

(B) Legal Principle - The appointment of an arbitrator is invalid if it contravenes Section 12(5), which prohibits the appointment of individuals having specified relationships with parties unless there is an express written waiver post-dispute. (Paras 77, 90)

(C) The recent Supreme Court ruling clarified that mere consent or procedural participation does not constitute a valid waiver under Section 12(5). (Paras 90, 123)

Facts of the case:
The appellant sought to appeal a judgment overturning an arbitral award due to the arbitrator's appointment violating Section 12(5), which was considered by the High Court. The award was issued following disputes arising from a contract dated 12 January 2016. (Paras 2, 3, 26)

Findings of Court:
The earlier appointment made without explicit waiver was deemed invalid, affirming the lower court's holding that the award could not stand due to legal noncompliance with the Arbitration Act provisions. (Paras 28, 30)

Issues: The principal question was whether the arbitrator's appointment was valid under provisions of Section 12(5) and if any waiver existed. (Paras 16, 28)

Ratio Decidendi: The court ruled that an express written waiver of Section 12(5) is mandatory; failure to comply rendered the arbitrator's appointment void, negating the resultant arbitral award. (Paras 28, 30)

Result: Appeal dismissed.

Table of Content
1. court's jurisdiction in arbitration appeals (Para 1 , 2 , 3 , 4 , 5 , 6)
2. contractual provisions for arbitration (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14)
3. impact of section 12(5) on arbitrators (Para 15 , 16 , 17)
4. requirements for waiver under section 12(5) (Para 18 , 19 , 20 , 21 , 22 , 23)
5. final decision on arbitration legality (Para 24 , 25 , 26 , 27 , 28)

JUDGMENT

% 14.01.2026 C. HARI SHANKAR, J.The lis

1. We are required, in this appeal, to consider the extent to which this case would be covered by the recent judgment of the Supreme Court in Bhadra International (India) (P) Ltd v. Airports Authority of India1

2. Disputes, which emanated out of an agreement dated 12 January 2016, between the appellant and the respondent, were referred to arbitration and culminated in an arbitral award dated 30 May 2023, which was adverse to the respondent. The respondent challenged the said award before this Court under Section 34 of the Arbitration and Conciliation Act, 1996 , “the 1996 Act”, hereinafter by way of OMP (Comm) 355/2023. By judgment dated 8 May 2024, a learned Single Judge of this Court has allowed OMP (Comm) 355/20233 and has set aside the arbitral award.

3. Aggrieved thereby, the present appellant, as the respondent in the OMP, has instituted the present appeal.

4. We have heard Mr. Raj Shekhar Rao, learned Senior Counsel for the appellant and Mr. Ankur Mahindro, learned Counsel for the respondent, at length.

5. The learned Single Judge has, by the impugned judgment, set aside the arbitral award, solely on the ground that the appointment of the arbitrator was in violation of Section 12 (5)4 of the 1996 Act. In so holding, the learned Single Judge has followed the judgments of the 1 2026 SCC OnLine SC 7, referred to, hereinafter, as “Bhadra”. 3 Union of India v M/s. M.V. Omni Projects (India) Ltd. 4 (5) Notwithstanding any prior agreement to the contrary, any person whose relationship, with the parties or counsel or the subject-matter of the dispute, falls under any of the categories specified in the Seventh Schedule shall be ineligible to be appointed as an arbitrator: Provided that parties may, subsequent to disputes having arisen between them, waive the applicability of this sub-section by an express agreement in writing. Supreme Court in Bharat Broadband Network Ltd. v. United Telecoms Ltd. /b>, (2019) 5 SCC 755 and Perkins Eastman Architects DPC v. HSCC (India) Ltd, (2020) 20 SCC 760

6. The Supreme Court has, very recently, clarified the legal position in its judgment in Bhadra. Essentially, the arguments before us revolved around the impact of the said decision on the facts of the present case.

Facts

7. Clause 25 of the General Conditions of Contract governing the agreement between the appellant and the respondent provided for reference of disputes to arbitration, and read as under:

“CLAUSE 25 Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:

(i) ………….

(ii) Except where the decision has become final, binding and conclusive in terms of Sub Para (i) above, disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Chief Engineer, CPWD, in charge of the work or if there be no Chief Engineer, the Additional Director General of the concerned region of CPWD or if there be no Additional Director General,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top