IN THE HIGH COURT OF DELHI AT NEW DELHI
GOVT.OF NCT OF DELHI & ANR. – Appellant
Versus
GAURAV ENTERPRISES – Respondent
O.M.P. (COMM)-221/2017



$~J * IN THE HIGH COURT OF DELHI AT NEW DELHI Judgment reserved on:01.11.2025 Judgment pronounced on: 22 .01.2026 + O.M.P. (COMM) 221/2017 & I.A. 26479/2025 GOVT.OF NCT OF DELHI & ANR. ………Petitioners Through: Mr. Tushar Sannu, Ms. Ankita Bhadoriya and Mr. Vishal Ji, Advs.

versus GAURAV ENTERPRISES ………Respondent Through: Mr. Sudhir Nandrajog Sr. Adv. with Mr. Tarkeshwar Nath, Mr. Harshit Singh, Advs.

CORAM:

HON'BLE MR. JUSTICE JASMEET SINGH

J U D G M E N T

1. This is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“1996 Act”) seeking to set aside the Arbitral Award dated 20.12.2016 (“impugned Award”), wherein the claims of the respondent were allowed and was awarded a sum of Rs.6,87,09,157/- towards pending bills and Rs. 32,82,807/- as refund of security along with interest @ 9% p.a from the date of invocation of the arbitration clause upto the date of the award and future interest @

12% p.a. from the date of the award till its realization.

2. The petitioners before this Court were the respondents in the arbitration proceedings and the respondent herein was the claimant.

FACTUAL BACKGROUND

3. The petitioner No. 1 i.e., Dr. Baba Saheb Ambedkar Hospital, a government aided hospital, situated at Rohini, provides super specialty facilities including Neurosurgery, Nephrology, Pulmonology and Urology. The petitioner No. 2 i.e., Health & Family Welfare Department, is a Department of Government of NCT of Delhi and is committed to providing healthcare facilities to the people of Delhi.

4. The respondent i.e., M/s. Gaurav Enterprises, is engaged in the business of providing security services.

5. The petitioner No. 1 invited e-tenders for providing security services with trained manpower at Dr. Baba Saheb Ambedkar Hospital for a period of two years on contract basis. The respondent participated in the same and was awarded the contract to provide 130 security guards and 3 security supervisors for a period of 2 years starting from

29.04.2011 @ Rs. 338.12/- per day per security guard.

6. Subsequently, an Offer Letter dated 27.04.2011 (“Offer Letter”) was issued by petitioner No. 1 to the respondent. Later, on 28.04.2011, a notice was issued by petitioner No. 1 to the respondent directing the respondent to take over the charge of security services and to submit a list of manpower deployed with their addresses and medical fitness and police verification within 7 days. Consequently, an Agreement dated 28.04.2011 (“Agreement”) was executed between the petitioner No. 1 and the respondent for a period of two years from 29.04.2011 to

28.04.2013.

7. The said Agreement contains an arbitration being Clause No. 58 of the Terms and Conditions of the Contract (“TCC”), which reads as under:-

“58.⁠ ⁠Dispute Resolution (a) Any dispute and or difference arising out of or relating to this contract will be resolved through joint discussion of the authorities' representatives of the concerned parties. However, if the disputes are not resolved by joint discussions, then the matter will be referred for adjudication to a sole Arbitrator appointed by the Principal Secretary/Secretary (of the Administrative Department), Government of NCT of Delhi (b) The award of the sole Arbitrator shall be final and binding on all the parties. The arbitration proceeding's shall be governed by Indian Arbitration and Conciliation Act

1996 as amended from time to time.

(c) The cost of Arbitration shall be borne by the respective parties in equal proportions. During the pendency of the arbitration proceeding and currency of contract, neither party shall be entitled to suspend the work/service to which the dispute relates on account of the arbitration and payment to the contractor shall continue to be made in terms of the contract.

Arbitration proceedings will be held at Delhi/New Delhi only.”

8. The respondent took over the charge of security services with effect from 29.04.2011 and deployed its manpower. However, the Agreement period was extended till 24.12.2014 (termin