IN THE HIGH COURT OF DELHI AT NEW DELHI
M/S DEVINDER DAHIYA INFRASTRUCTURE PVT. LTD. VS. PUBLIC WORKS DEPARTMENT


$~4 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 1765/2025 M/S DEVINDER DAHIYA INFRASTRUCTURE PVT. LTD .....Petitioner Through: Mr. Sumit Kalra, Ms. Yashika Malhotra and Mr. Hari Arora, Advocates.

versus PUBLIC WORKS DEPARTMENT .....Respondent Through: Mr. Anubhav Gupta, Advocate CORAM:

HON'BLE MR. JUSTICE AMIT BANSAL

O R D E R

% 10.12.2025

1. This petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter ‘Act’), seeking appointment of a Sole Arbitrator for the adjudication of the disputes between the parties arising out of Agreement No. 18/EE/EMD(S & SE)/PWD/18-19 (hereinafter ‘Agreement’).

2. The petitioner was awarded a contract for ‘construction of additional classrooms in existing premises at S.K.V (Gargi) Green Park Extension, SV Sardarjung Enclave, SKV Hauzrani, New Delhi’.

3. Since there were disputes between the parties on account of non- payment of the outstanding dues by the respondent, the petitioner sent several notices to the respondent including the notice dated 22nd April 2025, invoking the aforesaid arbitration clause under Section 21 of the Act.

However, the respondent has failed to respond to the said notices.

4. Hence,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top