IN THE HIGH COURT OF DELHI AT NEW DELHI
M/S DEVINDER DAHIYA INFRASTRUCTURE PVT. LTD VS. PUBILC WORKS DEPARTMENT
$~6 * IN THE HIGH COURT OF DELHI AT NEW DELHI + ARB.P. 1772/2025 M/S DEVINDER DAHIYA INFRASTRUCTURE PVT. LTD .....Petitioner Through: Mr. Sumit Kalra, Ms. Yashika Malhotra and Mr. Hari Arora, Advocates versus PUBLIC WORKS DEPARTMENT .....Respondent Through: Mr. Anubhav Gupta, Advocate.
CORAM:
HON'BLE MR. JUSTICE AMIT BANSAL
O R D E R
% 10.12.2025
1. This petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter ‘Act’), seeking appointment of a Sole Arbitrator for the adjudication of the disputes between the parties arising out of Agreement No. 23/EE/Edu.Maint.Div.(South)/PWD/2018-19 (hereinafter ‘Agreement’).
2. The petitioner was awarded a contract for ‘construction of additional classrooms at SBV Yogi Arvind, GGSSS Tigri, GGSSS No 2 Sector-5 Ambedkar Nagar, Ishani G-Block Saket, SKV MB Road Pushp Vihar, New Delhi’.
3. Since there were disputes between the parties on account of non- payment of the outstanding dues by the respondent, the petitioner sent several notices to the respondent including the notice dated 7th April 2025, invoking the aforesaid arbitration clause under Section 21 of the Act.
However, the respondent has failed to respond
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.