IN THE HIGH COURT OF DELHI AT NEW DELHI
RAMASETHU INFRASTRUCTURE – Appellant
Versus
INDIAN RAILWAY WALFARE ORGANISATION – Respondent
* IN THE HIGH COURT OF DELHI AT NEW DELHI Date of decision: 24rd MARCH, 2026 IN THE MATTER OF:
+ O.M.P. (COMM) 348/2020 RAMASETHU INFRASTRUCTURE .....Petitioner Through: Mr. Gireesh Kumar and Ms. Sneha Mathew, Advocates, versus INDIAN RAILWAY WALFARE ORGANISATION .....Respondent Through: Mr. Sulaiman Mohd Khan, Ms. Taiba Khan, Mr. Gopeshwer Singh Chandel, Mr. Abdul Bari Khan, Ms. Aditi Chaudhary and Mr. Chandra Bose, Advocates. CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
1. The Petitioner seeks to challenge the Award dated 23.12.2014 passed by the Arbitral Tribunal while adjudicating the disputes between the parties under a contract for construction of 140 dwelling units comprising of 20 units of Type A (Type I) (only ground floor), 68 units Type-B (Type II) (only ground floor), 30 units Type C (Type III) (G-FF) and 22 units Type – D (Type IV) (G-FF) Terrace, stair room in Ambattum village near T.I. Cycle factory, Chennai – 600053, including all Civil, internal electrical, plumbing, sewerage, roads, pavements, drains, U/G water tank, sub-station, Boundary wall and gate etc. (hereinafter referred to as “tender work”) at quoted rates or total cost of Rs.16,72,35,219/- on the
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.