SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 6235

IN THE HIGH COURT OF DELHI AT NEW DELHI


Date of decision: 09.04.2026


O.M.P. (COMM) 181/2024 & I.A. 9043/2024 (Ex.)


KRISHNA UDYOG .....Petitioner


Through: Mr. Kamlesh Ojha, Advocate.


versus


UNION OF INDIA .....Respondent


Through: Ms. Radhika Bishwajit Dubey, CGSC along with Ms. Gurleen Kaur Waraich, Mr. Kritarth Upadhyay, Mr. Vivek Sharma and Mr. Amulya Dev Mishra, Advocates.


CORAM:


HON'BLE MR. JUSTICE HARISH VAIDYANATHAN SHANKAR


JUDGMENT (ORAL)

Challenges to arbitral tribunal constitution are barred where parties have expressly waived statutory disqualifications in writing. Additionally, liquidated damages representing pre-estimated compensation in a contract are enforceable as agreed damages without requiring proof of actual loss, provided the contract's essence relative to timely performance is maintained.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 12(5), 34(3) - Limitation - Period of limitation for setting aside an award is three months, extendable by thirty days - Petition filed within the aggregate period of three months and thirty days is maintainable even without a formal condonation application where delay is marginal and falls within the statutorily permissible bracket. (Paras 6-9)

(B) Arbitration and Conciliation Act, 1996 - Section 12(5) - Unilateral appointment - Waiver of disqualification - Proviso to Section 12(5) permits waiver of statutory ineligibility through express agreement in writing after disputes arise - A party that has consciously and unequivocally agreed to a waiver and actively participated in the nomination process cannot subsequently challenge the constitution of the arbitral tribunal on grounds of lack of independence or neutrality. (Paras 23-27)

(C) Contract Act, 1872 - Sections 55, 73, 74 - Liquidated damages - Proof of actual loss - Where a contract contains a stipulation for pre-estimated damages as compensation for breach, proof of actual loss is not a prerequisite for recovery - Extension of delivery period subject to specific recovery conditions confirms that time remains the essence of the contract, and does not negate the enforceability of the liquidated damages clause unless specifically waived. (Paras 30-31)

Facts of the case:
The petitioner challenged an arbitral award, raising three primary contentions: first, that the petition was within the limitation period; second, that the arbitral tribunal was unilaterally constituted in violation of statutory neutrality requirements; and third, that the imposition of liquidated damages without proof of actual loss was contrary to the law of contract.

Findings of Court:
The court observed that the petition filed within the grace period permitted under the legislative framework is maintainable. It held that the petitioner had provided an explicit written waiver regarding the statutory disqualification of arbitrators and had actively participated in the appointment process, thereby barring a subsequent challenge. Regarding the liquidated damages, the court affirmed that the contractual terms clearly provided for pre-estimated compensation in the event of specified breaches, and the tribunal's findings on the essence of time and the validity of damages were well-reasoned and based on the agreed contractual framework.

Issues: The main issues were the maintainability of the petition regarding the statutory limitation period, the legality of the tribunal's constitution following an alleged unilateral appointment, and the enforceability of liquidated damages in the absence of quantified actual loss.

Ratio Decidendi: A written waiver under Section 12(5) of the Act is legally binding and precludes challenges to the composition of a tribunal. Furthermore, liquidated damages specified in a contract to be payable upon breach operate as pre-estimated compensation and are recoverable without secondary proof of actual loss, provided the contract terms are unambiguous and time-related obligations remain enforceable.

Result: Petition dismissed.

HARISH VAIDYANATHAN SHANKAR, J.

1. The present Petition has been instituted under Section 34 of the Arbitration and Conciliation Act, 1996, (A&C Act), assailing the Award dated 14.11.2023, (Impugned Award). By way of the Impugned Award, a three-member Arbitral Tribunal dismissed the claims preferred by the Petitioner herein.

I. On preliminary objection concerning the delay

2. At the outset, the learned Central Government Standing Counsel appearing on behalf of the Respondent raises a preliminary objection to the maintainability of the present Petition on the ground that it is barred by limitation.

3. This Court proposes to consider and decide the said preliminary objection at the first instance.

4. At this juncture, this Court finds it apposite to reproduce the bare provision of Section 34 of the A&C Act, as the same is necessary for the proper adjudication of the present case:

“34. Application for setting aside arbitral award. -

*****

(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:

Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.

….”

5. A plain reading of Section 34(3) of the A&C Act makes it abundantly clear that the period prescribed therein is mandatory and inflexible. An application for setting aside an arbitral award must be filed within three months from the date of receipt of the award, extendable by a further period of thirty days, but not thereafter. The law in this regard has been succinctly reiterated by the Hon’ble Supreme Court in Chintels India Ltd. v. Bhayana Builders Pvt. Ltd. , (2021 SCC Online SC 80), which reads as follows:

“10. Sections 34(2) and (2-A) then sets out the grounds on which an arbitral award may be set aside. Section 34(3), which again is material for decision of the question raised in this appeal, reads as follows:

“34. (3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under Section 33, from the date on which that request had been disposed of by the Arbitral Tribunal:

Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.”

11. A reading of Section 34(1) would make it clear that an application made to set aside an award has to be in accordance with both sub-sections (2) and (3). This would mean that such application would not only have to be within the limitation period prescribed by sub-section (3), but would then have to set out grounds under sub-sections (2) and/or (2-A) for setting aside such award. What follows from this is that the application itself must be within time, and if not within a period of three months, must be accompanied with an application for condonation of delay, provided it is within a further period of 30 days, this Court having made it clear that Section 5 of the Limitation Act, 1963 does not apply and that any delay beyond 120 days cannot be condoned — see State of H.P. v. Himachal Techno Engineers at para 5.”

(emphasis added)

6. Section 34(3) of the A&C Act prescribes a strict and peremptory period of limitation for filing a petition for setting aside an arbitral award. The provision mandates that such a petition must be filed within a period of three months from the date on which the party making the application received the arbitral award. The proviso thereto, howe

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top