SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 6286

IN THE HIGH COURT OF DELHI AT NEW DELHI
MD. KARIMUNNISA – Appellant
Versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA THROUGH ITS CHAIRMAN & ANR. – Respondent
W.P.(C)-4817/2026



Judicial review in contractual matters is limited to examining the decision-making process for arbitrariness or mala fides; a contractor cannot challenge a valid termination clause after accepting it and enjoying benefits under the contract.

Headnote:(A) Constitution of India, 1950 - Article 226 - Scope of judicial review in contractual matters - Termination of contract - Specific Relief Act, 1963 - Specific performance not granted for contracts requiring continuous supervision. (Paras 20-23, 38)

(B) Judicial review in contractual and tender matters is confined to examining the decision-making process and not the merits of the decision itself. Interference is warranted only where the decision is arbitrary, mala fide, irrational, or in violation of statutory or constitutional mandates. (Paras 20-23, citing Tata Cellular v. Union of India, (1994) 6 SCC 651; Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517; N.G. Projects Ltd. v. Vinod Kumar Jain, (2022) 6 SCC 127)

(C) A contractor who enters into a commercial contract with open eyes and accepts mutually agreed termination clauses cannot later challenge those clauses as arbitrary, especially after enjoying the benefits of the contract for a substantial period. The doctrine of unfair contractual terms (Central Inland Water Transport Corpn. Ltd. v. Brojo Nath Ganguly) does not apply to commercial contracts between business entities in a competitive market. (Paras 29-31, 37)

(D) The mere fact that a fresh tender process was initiated contemporaneously with the termination decision does not establish mala fides or pre-determination. Administrative preparedness to avoid disruption in toll collection constitutes prudent governance. (Para 42) (E) Delay by the public authority in invoking contractual safeguards, such as the windfall gain clause, may cause loss to the public exchequer but does not render the termination invalid. However, authorities are expected to implement robust monitoring mechanisms for timely action. (Paras 48-51)

Facts of the case:
The Petitioner, a toll collection agency, entered into a contract with the national highway authority for collection of user fee at a fee plaza for one year from June 2025 to June 2026. The contract contained Clause 35(2) allowing termination on seven days’ notice without assigning reasons, and Clause 35(6) permitting termination in case of “windfall gain” where moving average of collections exceeded 40% of the remittance. In April 2026, the authority issued a show cause notice cum termination notice invoking both clauses, alleging that collections had substantially exceeded the threshold. A fresh tender for a new agency was also issued. The Petitioner challenged the termination and the fresh tender by way of a writ petition under Article 226.

Findings of Court:
The Court held that the termination was valid. The decision-making process was fair - notice, opportunity of hearing, and reasoned order were given. The invocation of Clause 35(6) was not arbitrary; the fee plaza was treated as a new plaza and collections exceeded the 40% benchmark. Even if Clause 35(6) were not strictly applicable, Clause 35(2) independently allowed termination on notice. The contractor had no vested right to continue till the end of the tenure. The challenge to the termination clause at a belated stage was estopped. The relief of specific performance was not available as damages were an adequate remedy. The Court, however, noted the authority’s delay in invoking the clause and directed expeditious conclusion of disciplinary proceedings against officials responsible for the delay, and implementation of automated monitoring systems.

Issues: (i) Whether the authority was justified in terminating the contract under Clauses 35(2) and 35(6). (ii) Whether interference in writ jurisdiction with a contractual decision taken in public interest was warranted.

Ratio Decidendi: The court ruled that judicial review in contractual matters is limited to examining the process, not the commercial wisdom of the authority. The termination was procedurally fair, within the express contractual terms, and not arbitrary or mala fide. A contractor who accepts such terms cannot subsequently challenge them. The remedy for breach, if any, lies in damages, not in specific performance.

Result: Writ Petition dismissed. All pending applications closed. Directions issued regarding disciplinary proceedings and monitoring mechanisms. (Paras 52, 51)

Legal Category Hierarchy

  • constitutional law
    • fundamental rights
      • right to equality (article 14) (Para 16, 34, 35)
  • administrative law
    • natural justice
      • right to hearing in contractual termination (Para 40, 41, 42)
    • public authority duties
      • monitoring and timely action (Para 48, 49, 50)
  • contract law
    • termination of contract
      • termination clauses
      • estoppel and acquiescence (Para 36, 37, 38)
      • specific performance (Para 38)
  • practice and procedure
    • writ jurisdiction

Table of Contents

1. Writ petition under Article 226 challenging termination of a toll collection contract by a public authority. (Para 1 , 4 , 5 , 6 , 7 , 8 , 9 , 10 )

2. Petitioner contended termination was arbitrary and contrary to contract; respondents contended contract permitted termination and decision was in public interest. (Para 2 , 11 , 16 , 17 , 18 )

3. Writ petition dismissed as devoid of merit. (Para 51 , 52 )

4. What is the scope of judicial review in contractual matters under Article 226?

Judicial review is confined to examining the decision-making process for arbitrariness, mala fides, or irrationality; the court does not substitute its own view. (Para 20 , 21 , 22 , 23 , 24 , 34 , 43 , 44 , 45 , 46 , 47 )

5. Can a termination clause in a commercial contract be challenged as arbitrary after being voluntarily accepted?

No. A clause forming part of a mutually accepted contract cannot be struck down as arbitrary, especially when both parties have safeguards. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 35 , 39 )

6. Does the issuance of a show cause notice and grant of hearing satisfy natural justice requirements in contractual termination?

Yes. Natural justice does not require a judicial decree; it is sufficient if the order shows application of mind to the reply and hearing. (Para 40 , 41 , 42 )

7. Can a contractor challenge a termination clause after enjoying benefits of the contract for a substantial period?

No. The contractor is estopped from challenging the validity of a clause after availing benefits under the contract for most of its tenure. (Para 36 , 37 , 38 )

8. What is the duty of a public authority in monitoring contractual safeguards like windfall gain clauses?

Public authorities must act promptly to avoid loss to public exchequer; delay in invoking such clauses undermines their purpose and may lead to accountability. (Para 48 , 49 , 50 )

JUDGMENT

ANIL KSHETARPAL, J. :

1. Through the present Writ Petition under Article 226 of the Constitution of India, the Petitioner assails the order dated 08.04.2026 [hereinafter referred to as the „Impugned Order‟], along with the show cause notice dated 02.04.2026 [hereinafter referred to as the „Impugned Show Cause Notice‟], whereby the Contract dated 26.05.2025 [hereinafter referred to as „Contract‟] executed between the Petitioner and the NHAI for collection of user fee at Pawangaon Fee Plaza has been terminated prior to expiry of the contractual period. The Petitioner has also challenged the fresh tender dated 02.04.2026 issued for engagement of a new user fee collecting agency for three months for the said Fee Plaza.

2. The Petitioner contends that the termination of the Contract is arbitrary, premeditated and contrary to the contractual stipulations, particularly Clause 35(6) of the Contract [hereinafter referred to as „Clause 35(6)‟], inasmuch as no circumstances warranting invocation of the said clause existed. It is further urged that the impugned action has been taken despite the contract remaining valid till 17.06.2026 and without any breach attributable to the Petitioner.

3. In the aforesaid backdrop, the principal issues that arise for consideration before this Court are:

i. Whether the Respondent Authority was justified in terminating the Contract in exercise of its enabling powers under Clauses 35(2) [hereinafter referred to as „Clause 35(2)‟] and 35(6); and

ii. Whether any interference is warranted in exercise of writ jurisdiction with a contractual decision taken in the interest of public exchequer by a public authority in matters relating to the termination of a tender contract.

FACTUAL MATRIX:

4. In order to appreciate the controversy involved in the present case, the relevant facts, in brief, are required to be noticed.

5. The Petitioner had earlier operated as a User Fee Collection Agency at the Pawangaon Fee Plaza situated at Km. 57+935 on NH-353J in the State of Maharashtra for a period of two months during April and May 2025. The Respondent No.1, namely the National Highways Authority of India [hereinafter referred to as „NHAI‟], invited bids through e-tender for engagement of a User Fee Collection Agency at the said Pawangaon Fee Plaza, for a period of one year.

6. Pursuant to the competitive bidding process, in which multiple bidders participated, the Petitioner was declared the successful bidder with a daily remittance of Rs.2,62,430/- (Rs.2,58,737/- as per the stand of the Respondents) for a period of one year and a Letter of Award dated 13.05.2025 came to be issued in its favour. It is stated that the Petitioner‟s quoted remittance was substantially higher than the reserve price as well as the bid submitted by the second highest bidder.

7. Thereafter, the Contract was executed between the parties for collection of user fee at the said Fee Plaza for the period commencing from 17.06.2025 (08:00 hours) till 17.06.2026 (08:00 hours). The Petitioner furnished performance security and commenced toll collection operations in terms of the Contract.

8. The Contract, inter alia, contained Clause 35 governing termination of the contract. While Clause 35(2) enabled termination upon issuance of seven days‟ notice without assigning reasons, Clause 35(6) provided for termination in case of “windfall gain” at new fee plazas where the moving average of ETC and cash collections for the preceding fifteen days exceeded forty percent of the existing remittance being paid by the toll agency.

9. On 02.04.2026, the Respondents issued a show cause notice cum seven days‟ termination notice invoking Clauses 35(2) and 35(6) of the Contract, stating their intention to terminate the contract. The notice alleged the occurrence of windfall gain and simultaneously afforded an opportunity of personal hearing to the Petitioner. On the same date, the Respondents also issued a fresh tender for engagement of a new user fee-collecting agency for t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top