IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Decision: 23rd April, 2026
Uploaded on: 24th April, 2026
W.P.(C) 2686/2018
ANAND KHANNA .....Petitioner
Through: Mr. S. K. Rout, Mr. Aman Mehrotra, Ms. Prabasini Pradhan & Ms. Alka Singh, Advs. (M: 9818522926)
versus
UNION OF INDIA .....Respondent
Through: Mr. Sanjay Kumar Pathak, Standing Counsel with Mrs. K. K. Kiran Pathak, Mr. Sunil Kumar Jha, Mr. Mohd. Sueb Akhtar & Mrs. Joohu Kumari, Advocates for LAC. (M: 9793585441)
CORAM:
JUSTICE PRATHIBA M. SINGH
JUSTICE MADHU JAIN
Prathiba M. Singh, J. (Oral)
1. This hearing has been done through hybrid mode.
2. The Petitioner, who is the bhumidar/owner of the land measuring 19 biswas (950 Sq. Yds.) out of Khasra No.30/1/1 situated in urbanized Village – Nagli Sakrawati, Delhi (hereinafter, ‘the subject land’), has filed the present petition challenging the impugned order dated 8th January, 2018 (hereinafter, ‘the impugned order’) passed by the LAC/ADM (South West), Kapashera, New Delhi.
3. Vide the impugned order, a reference petition under Section 18 of the Land Acquisition Act, 1894 (hereinafter the ‘Act’) filed by the Petitioner had been rejected as being barred by time.
4. The background of the case is that a notification u/s 4 of the Act dated 7th April, 2006 was issued for the acquisition of the subject land. Thereafter, a notification u/s 6 of the Act was issued on 4th April, 2007, declaring the acquisition of the land of the Petitioner for public purpose.
5. Vide award no. 13/2008- 09/SW dated 30th March, 2009, the land of the Petitioner was acquired and compensation was assessed by the LAC. The said compensation was also received by the Petitioner on 17th November, 2011.
6. Before this Court, the submissions of Mr. Rout, ld. Counsel appearing for the Petitioner are two-fold. Firstly, that the notice issued by the Respondent under Section 12(2) of the Act, notifying him of the award dated 30th March, 2009 was issued at the wrong address and the Petitioner did not receive the same. This is despite the Department having the correct address of the Petitioner.
7. Secondly, it is stated that immediately upon the compensation being received by the Petitioner on 17th November, 2011, the reference petition u/s 18 of the Act was filed on 19th December, 2011. Hence, the same could not have been held to be time barred.
8. On behalf of the Petitioner, it is also submitted that the reference petition u/s 18 of the Act could not be dismissed by the LAC and ought to have been sent to ld. District Judge itself.
9. On behalf of the LAC, Mr. Jha, ld. Counsel submits that in terms of Section 18(2)(b) of the Act, the award in this case was passed on 30th March, 2009 and reference petition was filed only on 19th December, 2011, which is beyond the six months period prescribed in the said provision.
10. The Court has considered the matter. A perusal of the counter affidavit filed by the Respondent and notices attached thereto would show that the notice under Section 12(2) of the Act, notifying the Petitioner of the award dated 30th March, 2009 was issued on 3rd August, 2009 to Mr. Anand Khanna S/o R.K. Khanna, RZ-73, Inder Puri, New Delhi.
11. Previous notices under Sections 9 & 10 of the Act dated 10th July, 2008 have also been issued to the Petitioner on the same address.
12. The impugned order, however, has been passed with the correct address of the Petitioner i.e. RA-53, Inderpuri, Delhi-110012. Thus, the notices were clearly sent at the wrong address.
13. Reliance has also been placed by the Petitioner on a similar case in W.P.(C) 7817/2017 titled Chet Singh Rana v. Union of India where the Division Bench of this Court, vide order dated 5th September, 2017, has held that in any event, the Petitioner ought to be forwarded to the concerned District Judge, who would also decide the issue of limitation u/s 18 of the Act. The said order dated 5th September, 2017 is extracted below:
“Issue notice. Sh. Yeeshu Jain, Advocate accepts notice.
The limited relief claimed in this petition under Article 226 of the Constitution is to set-aside an order of the respondent/LAC dated 31.01.2017, declining to forward the reference under Section 18 of the Land Acquisition Act, 1894 [hereafter “the 1894 Act”].
The Award in this case was made on 01.02.2012. The petitioner in this case requested for a reference on 15.01.2014. It was stated that the petitioner received the compensation on 28.11.2014 and he was in the dark till the impugned order, as to whether t
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.