IN THE HIGH COURT OF DELHI AT NEW DELHI
Harish Vaidyanathan Shankar, J
Rudra Interiors Pvt. Ltd. – Appellant
Versus
Hindustan Prefab Limited – Respondent
ARB.P. 1358/2025
| Table of Content |
|---|
| 1. parties' correspondence and contentions regarding pre-arbitration procedures. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 2. contractual interpretation of mandatory versus optional pre-arbitral redressal steps. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23) |
| 3. scope of section 11(6) judicial scrutiny and prohibition of unilateral arbitrator appointment. (Para 24 , 25 , 26) |
| 4. appointment of sole arbitrator and formal disposal of the petition. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33) |
JUDGEMENT (ORAL)
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition has been filed by M/S Rudra Interiors Pvt. Ltd.1Petitioner under Section 11 of the Arbitration and Conciliation Act, 19962A&C Act, seeking the appointment of a Sole Arbitrator to adjudicate upon the disputes inter se the parties.
2. At the outset, it is noted that vide Order dated 09.12.2025, National Disaster Response Force3NDRF/Respondent No.2 was impleaded as Respondent No. 2 to the present Petition.
3. Learned CGSC, Ms. Pratima N. Lakra, appearing for Respondent No. 2 submits that she has no objection to the disputes being referred to arbitration.
4. Learned counsel for Hindustan Prefab Limited4Respondent No.1 however, objects to the present Petition on the ground that the Agreement dated 19.08.20205Agreement, as entered into between the parties, prescribes a specific procedure, particularly articulated under Clause 26 of the Special Conditions of Contract6SCC therein, non-compliance with which would disentitle reference of disputes to arbitration.
5. Learned counsels appearing on behalf of the Parties are ad idem that the Petitioner had initially approached the Project-In-charge of Respondent No.1 and communicated his grievances to him vide letter dated 21.11.2024, however the same came to be rejected by virtue of communication dated 19.12.2024.
6. Subsequent thereto, the Petitioner vide communication dated 21.12.2024 appealed against the abovesaid rejection by the Project-In charge to the CMD/ Chief Engineer of Respondent No.17CMD, who replied to the said communication on 01.01.2025 by contending as follows:
“In this connection, I would like to draw your attention which respect to agreed clause no. 26 of SCC and Clause no.25 of GCC. As per clause, you have filed an appeal before CMD/Chief Engineer against project in charge, HPL letter dated 21.11.2024. In this regard, it is informed you that, appeal is without any cogent reason/ground dissatisfaction to the decisions of Project in charge in respect of your claims.
In view of above, your letter dated 21.12.2024, cannot be considered as appeal. Since no justification/reason has been given by you (M/s, Rudra Interiors Pvt. Ltd.), hence it may be appropriate for M/s Rudra Interiors Pvt. Ltd. to file a fresh appeal with all particulars in respect of each claim before the CMD for reconsideration”
(emphasis supplied)
7. As is apparent from the aforesaid Reply, Respondent No.1 took the stand that the communication dated 21.12.2024, by the Petitioner to the CMD, cannot be construed as an appeal, inasmuch as it does not set out any elaborate reasons or grounds for preferring the same.
8. It is further noted that Respondent No.1 persisted with the abovesaid stand in subsequent communications and further indicated to the Petitioner that a fresh appeal was required to be filed.
9. It is noted that, in pursuance of the foregoing, the Petitioner addressed a further communication dated 14.02.2025 to the CMD seeking an opportunity to meet and explain the various issues and grievances; however, Respondent No.1, vide letter dated 12.03.2026, maintained its stand that the earlier communication did not constitute an appeal and that a fresh appeal was required to be filed.
10. In view of the above-said, the Petitioner, being left with no alternative, issued a Notice dated 10.04.20258Notice as per Section 21 of the A&C Act, invoking arbitration.
11. However, Respondent No. 1, in its reply dated 03.05.2025
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.