SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 6499

IN THE HIGH COURT OF DELHI AT NEW DELHI
Mini Pushkarna, J
NK Toll Road – Appellant
Versus
National Highways Authority of India – Respondent
ARB. A. (COMM.) 12/2026



Advocates:
For the Appellants/Petitioners: Ankur Kashyap, Hasan Murtaza, Aman Bajaj, Sameer Sharma, Aman Bajaj, Purushartha Singh, Ankit Kr. Singh, Siddharth Dua, Jaideep Khot
For the Respondents: Nishant Awana, Rini Badoni, Nitya Sharma

An appellate court must exercise judicial restraint regarding interim arbitral orders, refusing to substitute its own discretion for the tribunal's plausible contractual interpretation unless the order is shown to be perverse or patently illegal, notwithstanding the pendency of related performance disputes.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 17 and 37(2)(b) - Scope of appellate interference - Interim order passed by Arbitral Tribunal - Appellate court must exercise judicial restraint under Section 37(2)(b) - Not to substitute its own discretion for that of Tribunal unless decision is afflicted by perversity or patent illegality - An order is not to be interfered with simply because another view is possible. (Paras 20, 21)

(B) Concession Agreement - Contractual obligations - Divestment requirement regarding retention of funds or bank guarantee - Characterized as an independent covenant - Compliance of such obligation is not contingent upon the outcome of disputes regarding other performance obligations such as overlay works or road maintenance - Contractual interpretation by Tribunal holding such obligation as distinct and enforceable in the interim is a plausible view protected from interference. (Paras 14, 18)

Facts of the case:
The appellant challenged an order passed by the Arbitral Tribunal, which had partially allowed an application for interim measures under Section 17 of the Arbitration and Conciliation Act. The Tribunal had stayed the operation of a cure period notice issued by the authority regarding specific maintenance and penalty claims, as those issues were sub-judice. However, the Tribunal allowed the authority to proceed with the cure period notice insofar as it related to the appellant's failure to maintain a reserve fund or provide a bank guarantee as required by the contract. The appellant sought to set aside the latter portion of the order, arguing that the divestment obligation was linked to the performance of disputed overlay works.

Findings of Court:
The court held that the requirement to retain funds or provide a bank guarantee in the final years of the concession is an independent contractual obligation that exists notwithstanding other disagreements. The Tribunal's finding that this obligation is not dependent on the completion of specific overlay cycles was a plausible interpretation of the contract. Consequently, the court found no infirmity or perversity in the Tribunal's decision and affirmed that appellate jurisdiction is not meant to re-adjudicate merits when the Tribunal’s view is rooted in the contractual language.

Issues: Whether the Arbitral Tribunal erred in bifurcating the obligations related to road renewal from the divestment requirement for interim relief; and whether the interference under Section 37(2)(b) is warranted when the Tribunal’s interpretation of the contract is a plausible one.

Ratio Decidendi: The court maintained that the divestment requirement is a standalone safeguarding mechanism in the project agreement. Since the Tribunal’s interpretation regarding the independence of this clause was reasonable, and since the Tribunal had not exceeded its jurisdiction, the court should not substitute its own discretion. Judicial intervention in arbitral interim orders is limited to instances of patent illegality or clear perversity.

Result: Appeal dismissed.

Table of Content
1. factual background and procedural history of the concession and arbitration dispute. (Para 1 , 2 , 3 , 4)
2. contentions regarding the scope of interim protection and contractual obligations during arbitration. (Para 5 , 6 , 7)
3. independence of article 34.11 divestment obligations from main arbitral disputes. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19)
4. scope of appellate interference under section 37 of the arbitration act. (Para 20 , 21 , 22 , 23)

Background

1. The present appeal has been filed under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) against the interim order dated 03rd January, 2026 (“impugned order”), passed in the on-going arbitration proceedings, titled as “N.K. Toll Road Limited Versus National Highway Authority of India”. The Arbitral Tribunal, vide the impugned order, disposed of the application of the appellant/claimant/concessionaire, i.e., N.K. Toll Road Limited, filed under Section 17 of the Arbitration Act, seeking stay on the operation and effect of the Cure Period Notice dated 07th October, 2025, issued by the respondent, namely, National Highway Authority of India (“NHAI”) under Articles 32.1.1 and 32.1.3 of the Concession Agreement dated 30th January, 2006 (“Concession Agreement”), executed between the parties.

2. More particularly, the Arbitral Tribunal restrained the respondent from taking any action with respect to the breaches/defaults alleged by it in Para 9(a)(i) to (iii) of the Cure Period Notice, since the said allegations were subject matter of adjudication by the Arbitral Tribunal in the on-going arbitration proceedings. However, the Arbitral Tribunal held that the respondent would be well within its right to proceed with the Cure Period Notice in respect of the alleged default of non-compliance of divestment requirements under the Concession Agreement, as mentioned in Para 9(a)(iv) of the Cure Period Notice.

3. By way of the present appeal, the appellant has confined its challenge to the limited extent that while the Arbitral Tribunal has granted interim protection to the appellant against the alleged defaults relating to periodic overlay obligations, consequential damages, and FASTag remittance forming part of the Cure Period Notice [Para 9(a)(i) to (iii)], it nevertheless permitted the respondent to proceed further with the said Cure Period Notice, insofar as it concerns the alleged non-compliance of Article 34.11 of the Concession Agreement [Para 9(a)(iv)], thus, rendering the Concession Agreement exposed to forthwith termination.

Factual Matrix

4. The facts, in brief, leading to the filing of the present appeal are as follows:

4.1. The parties entered into the Concession Agreement dated 30th January, 2006 for design, construction, development, finance, operation and maintenance of a project highway from Km 258.645 (end of Namakkal Bypass) to Km 292.600 (start of Karur Bypass), on NH-7 from a two-lane to a four-lane highway, covering 33.48 Kms to be executed on a Build-Operate-Transfer (“BOT”) Toll basis. Additionally, the project involved the improvement, operation and maintenance of the Sections from Km 248.625 (start of the proposed flyover on Namakkal Bypass) to Km 258.645 (end of Namakkal Bypass) on NH-7 on a BOT basis.

4.2. The aforesaid Concession Agreement commenced from 29th July, 2006, and is scheduled to expire on 28th July, 2026, i.e., for a period of twenty (20) years, which is further extendable by three (3) months.

4.3. In furtherance of the Concession Agreement, the appellant completed the construction of the project highway, and thereby, commenced the toll operations. However, during the operation and maintenance of the project highway, various disputes arose between the parties, in relation to the interpretation and enforcement of specific provisions of the Concession Agreement.

4.4. Upon failure of resolution of the disputes amicably, the appellant herein invoked the arbitration clause, i.e.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top