SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 6567

IN THE HIGH COURT OF DELHI AT NEW DELHI
Harish Vaidyanathan Shankar, J
Subhash Chander – Appellant
Versus
Delhi Development Authority – Respondent
ARB.P. 102/2026



Advocates:
For the Appellants/Petitioners: Rajasree Ajay
For the Respondents: Sanjay Vashishtha, Siddharth Goswami, Krish Bhatia, Aditya Sachdeva

A referral court's jurisdiction under section 11 is strictly limited to a prima facie examination of the existence of an arbitration agreement. All contested questions of law and fact, including issues of accord and satisfaction, are within the exclusive adjudicatory competence of the Arbitral Tribunal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11 - Appointment of Arbitrator - Scope of judicial scrutiny - Referral Court's power is limited to a prima facie examination of the existence of a valid arbitration agreement - Any contested issues of fact or law, including claims concerning 'accord and satisfaction,' are reserved for the determination of the Arbitral Tribunal - (Paras 5, 6, 7).

(B) Judicial Interference - Principles of arbitration - Referral court must refrain from performing a laborious enquiry at the nascent stage to uphold the legislative intent of minimal judicial interference - (Paras 5, 114, 127).

Facts of the case:
The petitioner approached the court seeking the appointment of a sole arbitrator pursuant to an arbitration clause in the agreement executed between the parties. The respondent raised objections in its counter-affidavit, which the court observed could be effectively raised before the arbitrator. The parties were in agreement that a mechanism for appointing an arbitrator was required.

Findings of Court:
The court held that as the parties were ad idem regarding the referral to arbitration and the arbitration agreement existed, there was no impediment to granting the request. All contentions raised by the parties were left open to be decided by the tribunal on their merits in accordance with law.

Issues: The main issue addressed was the scope and standard of judicial scrutiny by a referral court under section 11 of the Act when the counter-party raises objections to the appointment of an arbitrator.

Ratio Decidendi: The court maintained that the role of the referral court is merely facilitative and procedural. In line with established precedent, it is required only to determine if an arbitration agreement exists prima facie; it is not for the court to adjudicate on contentious factual or legal matters which fall within the exclusive jurisdiction of the arbitral tribunal, thereby preserving the principle of competence-competence.

Result: Petition allowed; Sole Arbitrator appointed.

Table of Content
1. initiation of section 11 petition based on contractual arbitration clause. (Para 1 , 2 , 3)
2. scope of section 11 is limited to prima facie existence of arbitration agreement. (Para 4 , 5 , 6 , 7)
3. court appoints arbitrator subject to contractual qualifications and procedural guidelines. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18)

% JUDGEMENT (ORAL)

1. The present Petition, under Section 11 of the Arbitration and Conciliation Act, 19961, seeks the appointment of a Sole Arbitrator for adjudication of the disputes as are stated to have arisen inter se the parties in terms of Clause 25 of the Agreement dated 10.12.2022, as executed between the parties. The said clause reads as under:

“CLAUSE 25 Settlement of Disputes & Arbitration Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings, and instructions here-in-before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter, or thing whatsoever in any way

1 The Act

rising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders, or these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion, or abandonment thereof shall be dealt with as mentioned hereinafter:

i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record, or decision given in writing by the Engineer-in-Charge or if the Engineer-in-Charge considers any act or decision of the contractor on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable and is disputed, such party shall promptly within 15 days of the arising of the disputes request the EM or where there is no who shall refer the disputes to Dispute Redressal Committee (DRC) within 15 days along with a list of disputes with amounts claimed if any in respect of each such dispute. The Dispute Redressal Committee (DRC) shall give the opposing party two weeks for a written response, and, give its decision within a period of 60 days extendable by 30 days by consent of both the parties from the receipt of reference from EM. The constitution of Dispute Redressal Committee (DRC) shall be as indicated in Schedule 'F'. Provided that no party shall be represented before the Dispute Redressal Committee by an advocate/legal counsel etc.

If the Dispute Redressal Committee (DRC) fails to give its decision within the aforesaid period or any party is dissatisfied with the decision of Dispute Redressal Committee (DRC) or expiry of time limit given above, then either party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), give notice to the EM/DDA, in charge of the work or for appointment of arbitrator on, prescribed proforma as per Appendix XV under intimation to the other party.

It is a term of contract that each party invoking arbitration must exhaust the aforesaid mechanism of settlement of claims/disputes prior to invoking arbitration.

The EM/DDA shall in such case appoint the sole arbitrator or one of the three arbitrators as the case may be within 30 days of receipt of such a request and refer such disputes to arbitration. Wherever the Arbitral Tribunal consists of three Arbitrators, the contractor shall appoint one arbitrator within 30 days of making request for arbitration or of receipt of request by Engineer-in-charge to EM/DDA for appointment of arbitrator, as the case may be, and

two appointed arbitrators shall appoint the third arbitrator who shall act as the Presiding Arbitrator. In the event of:

a. A party fails to appoint the second Arbitrator, or b. The two appointed Arbitrators fail to appoint the Presiding Arbitrator

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top