IN THE HIGH COURT OF DELHI AT NEW DELHI
ANIL KSHETARPAL, AMIT MAHAJAN, JJ.
M/s Sapphire Media Limited - Petitioner
Versus
Nbcc Services Limited And Anr. - Respondents
W.P.(C) 4147 of 2026, CM APPL. 20278 of 2026, CM APPL. 20279 of 2026, CM APPL. 20280 of 2026, CM APPL. 22033 of 2026
Decided On : 11-05-2026
| Table of Content |
|---|
| 1. factual background of the tender dispute and disqualification. (Para 1 , 2) |
| 2. parties' contentions regarding tender eligibility and document submission. (Para 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14) |
| 3. judicial review criteria in tender matters and prevention of hyper-technical exclusions. (Para 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29) |
| 4. order setting aside disqualification and directing reconsideration of the bid. (Para 30 , 31) |
JUDGMENT :
AMIT MAHAJAN, J.
1. By the present petition, the Petitioner challenges the disqualification of its Technical Bid, communicated vide email dated 28.03.2026 pertaining to the Tender No. NSL/CEO/IIAC/NIT/2026/845 for “Interior and Fitout work for IIAC at 4th & 5th, Tower A, World Trade Centre, Nauroji Nagar, New Delhi” for “India International Arbitration Centre issued by Respondent No. 1.
2. Briefly stated, the relevant facts circumscribing the adjudication of the present petition are as follows:
2.1. On 14.03.2026, Respondent No. 1 issued a tender for Interior and Fitout work for the India International Arbitration Centre. The last date and time of submission of the online tender was up to 23.03.2026 by 11 PM. The estimated cost of the work was Rs. 31,64,86,727/-. As per the Notice Inviting Tender (‘NIT’), the eligibility criteria required the bidder to furnish, inter alia, in Form E, a self-certified Bank Solvency Certificate issued by a Nationalised or Scheduled Bank for an amount that was not less than 40% of the estimated cost of work and issued within 6 months from the original last date of submission of tender. The relevant clause is reproduced as follows:
“Self-Certified copy of Bank Solvency Certificate issued from Nationalized or any Schedule Bank should be one in number for at least 40% of the estimated cost of the project put to tender. The certificate should have been issued within 6 months from original last date of the submission of the tender.”
2.2. The Petitioner submitted its comprehensive bid including a financial offer of Rs. 20,67,29,130.08/- on 22.03.2026. Along with the Bid, the Petitioner submitted two solvency certificates – one issued by Axis Bank dated 30.08.2025 and another issued by Kotak Mahindra Bank dated 12.03.2025. By communication dated 24.03.2026, Respondent No. 1 issued certain technical objections and sought clarifications regarding the Petitioner’s financial documentation. Amongst other things, the communication dated 24.03.2026 specified that the Bank Solvency Certificate submitted by the bidder/Petitioner was not in line with the uploaded NIT. The same is reproduced as follows:
“Bank solvency certificate is submitted by the bidder, however the submitted solvency certificate is not inline with the uploaded NIT “Self-Certified copy of Bank Solvency Certificate issued from Nationalized or any Schedule Bank should be one in number for at least 40% of the estimated cost of the project put to tender. The certificate should have been issued within 6 months from original last date of the submission of the tender”, the bank solvency certificate submitted is beyond the period of 6 months earlier from the date of the submission of the NIT (Expired). Further, solvency certificate submitted by the bidder is in the name of NBCC (India) limited and maha Mumbai metro operation limited. Revised solvency certificate to be submitted issued by the bank from the date prior to the last date of the submission of the Tender as per NIT.”
2.3. The clarification sought required the Petitioner to submit query related documents by 25.03.2026 up to 5 PM positively. In response thereof, the Petitioner submitted two certificates – one issued by Kotak Mahindra Bank dated 23.03.2026 ( Rs. 35 crores) and another issued by PNB dated 11.02.2026. On 28.03.2026, Respondent No. 1 issued an email, thereby disqualifying the Petitioner for “not meeting the eligibility criterion” without assigning any reasons. Aggrieved by the same, the Petit
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.