SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 632

2026 DHC 4386
IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
M/s Sarvpriya Securities Pvt Ltd - Petitioner
Versus 
M/s Ank Hotels Pvt Ltd - Respondent
O.M.P. (COMM) 432 of 2023
Decided On : 18-05-2026
Advocates Appeared : 
For the Petitioner : Mr. Ashish Aggarwal, Mr. O.P. Faizi, Mr. Anand Aggarwal, Mr. Madhur Sapra, Ms. NishthaVerma, Ms. Lisha Arora, Mr. Himanshu Singh, Ms. Anjali
Kashyap & Ms. Ishita, Advs.
For the Respondent : Mr. Manu Bajaj, Ms. Parul, Advs.

An arbitral award must contain intelligible reasoning as mandated by Section 31(3). Furthermore, retention of an advance payment in the absence of an explicit forfeiture clause requires proof of actual loss or damage under contract law principles, as breach of contract does not automatically validate forfeiture.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 31(3) - Requirement of a reasoned award - Section 34 - Scope of interference - Contract Act, 1872 - Sections 73 and 74 - Forfeiture of advance - Requirement of proof of loss.

(B) Reasoned Award: Under Section 31(3), an award must be reasoned, intelligible, and adequate. A mere acknowledgment of submissions without legal reasoning fails to satisfy the mandate of the statute.

(C) Forfeiture of Advance: In the absence of a specific forfeiture clause within an agreement, the principles of the Contract Act apply. A party claiming the right to retain an advance payment must substantiate the actual loss or damage sustained due to the breach of contract. (Paras 10, 11, 12).

Facts of the case:
The parties entered into an agreement regarding the management of a property. Due to irreconcilable differences regarding the scope of the project, including demands for additional space and a failure to reach a mutual consensus on termination, the project remained a non-starter. The arbitrator rejected both the primary claim and the counter-claim for the refund of advance money, finding that there was no clause in the agreement regarding the subject matter of the payments.

Findings of Court:
The dismissal of the counter-claim regarding the refund of the advance was found to be bereft of reasoning. There was no evidence that the party retaining the money suffered any actual damage or loss, and the absence of a forfeiture clause precluded the legal right to retain the payment under the law governing contracts.

Issues: Whether the arbitral award was sufficiently reasoned under the Act and whether the retention of advance money was legally justified in the absence of a forfeiture agreement and proof of actual damages.

Ratio Decidendi: An arbitral award that fails to provide substantive reasoning for its findings, particularly when adjudicating the right to retain advance payments, is unsustainable. The law stipulates that forfeiting an advance without a specific contractual clause requires the claimant to prove actual financial injury or loss, which was not demonstrated in this instance.

Result: Petition allowed; award set aside to the extent of the dismissal of the counter-claim of the petitioner.

Table of Content
1. factual background and contractual dispute regarding project implementation (Para 1 , 2 , 5 , 6 , 7)
2. respective arguments regarding contract breach and retention of advance payments (Para 3 , 4)
3. mandatory requirement of reasoned arbitral awards under section 31(3) (Para 8 , 9 , 10 , 11)
4. principles of section 73 of the contract act and severability of arbitral awards (Para 12 , 13 , 14 , 15 , 16 , 17 , 18)
5. final court order setting aside part of the arbitral award (Para 19)

JUDGMENT :

AVNEESH JHINGAN, J.

1. This petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act’) seeking setting aside of the arbitral award dated 01.07.2023 (for brevity ‘the award’).

2. The relevant facts are that the petitioner is engaged in business of developing real estate projects. In the year 2017 petitioner was developing Signature Global Mall (for short ‘the Mall’) in Ghaziabad, Uttar Pradesh under its own brand name. The parties to the lis entered into a Memorandum of Understanding (MoU) dated 18.05.2018 whereby the respondent agreed to operate and maintain service apartments/hotels at 3rd to 6th floor of the Mall under the name of ‘Clark Premier’.

2.1 In terms of clause 14 of the MoU, the petitioner had to pay a sum of Rs.50,00,000/- plus GST after deduction of TDS towards one time brand collaboration fee and an amount of Rs.50,00,000/- towards technical support fee. The respondent was entitled to an additional amount of Rs.1,70,00,000/- (rupees one-crore seventy lakhs) plus GST towards administrative marketing of the property, operational and pre-opening expenses to commence service apartment/hotel operation, within a period of six to eight months from the date of signing of the MoU. As per Clause 20 of the MoU, the prior discussions between the parties were agreed to be merged in the MoU and no further modification would be effected unless mutually agreed between the parties in writing.

2.2 The respondent through emails dated 08.08.2018 and 18.11.2018 sought additional space beyond what was initially agreed between the parties. The request was denied by the petitioner through communications dated 10.08.2018 and 01.12.2018. Thereafter, the respondent sent three emails in December, 2018 agreeing to the denial for the additional space. Meeting was held between the parties on 18.12.2018 and on 08.02.2019, the petitioner sent an email attaching undertaking for mutual termination of the MoU.

2.3 Thereafter in September, 2019 the petitioner demanded a refund of Rs.1,18,00,000/- (rupees one-crore eighteen lakhs) paid as advance. The respondent vide communication dated 21.09.2019, declined the refund and instead demanded payment of the balance amount of Rs.1,70,00,000/- (rupees one-crore seventy lakhs).

2.4 Dispute arose between the parties and arbitration was invoked at the instance of the respondent by issuing notice dated 09.01.2020. The arbitrator was appointed by this court on 30.11.2021 and the arbitral proceedings culminated in the impugned award. The claim of the respondent of rupees one-crore seventy lakhs was rejected and the counter-claim of the petitioner seeking refund of rupees one-crore eighteen lakhs was also dismissed.

3. Learned counsel for the petitioner contends that the award is non-speaking and suffers from patent illegality. The arbitrator erred in concluding that the advance paid by the petitioner was not subject to incurring of expenses.

3.1 The submission is that the MoU contained no clause for forfeiture of the advance paid and that the sums paid were not earnest money.

3.2 Reliance is placed upon the decisions of the Supreme Court in Kailash Nath Associates v. DDA & Anr. 2015 4 SCC 136, Union of India v. Rampur Distillery & Chemical Co. Ltd. AIR 1973 SC 1098, Rajesh Gupta v. Ram Avtar 2022 SCC OnLine Del 1482, Amrit Pal Singh v. Kawaljeet Singh 2022 SCC OnLine 1619, ONGC v. Saw Pipes Ltd. (2003) 5 SCC 705 and Patel Engineering Ltd. v. North Eastern Electric Power C

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top