IN THE HIGH COURT OF DELHI AT NEW DELHI
MINI PUSHKARNA, J.
M/s Jiangxi Construction Engineering Group Co Ltd & Anr. - Petitioners
Versus
M/s Varaha Infra Ltd. - Respondent
ARB.P. No. 247 of 2026 & I.A. No. 11845 of 2026, O.M.P.(I) (COMM.) No. 23 of 2026 & I.A. Nos. 1536 of 2026 & 11844 of 2026
Decided On : 26-05-2026
| Table of Content |
|---|
| 1. factual background leading to breach of settlement and arbitration. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 2. parties' contentions regarding breach and necessity of interim relief. (Para 17 , 18 , 19 , 20 , 21 , 22) |
| 3. section 21 notice not strictly required for repeated arbitration. (Para 23 , 24 , 25 , 26 , 27 , 28) |
| 4. intertwined disputes arising from consolidated settlement agreements require unified arbitration. (Para 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39) |
| 5. appointment of sole arbitrator and consolidation of claims. (Para 40 , 41 , 42 , 43) |
JUDGMENT :
MINI PUSHKARNA, J.
1. ARB.P. 247/2026 has been filed under Section 11 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”) seeking appointment and/or grant of fresh mandate for the earlier Arbitrator, to adjudicate the disputes between the parties, arising out of and in connection with the Settlement Agreement dated 21st December, 2021 (“Settlement Agreement”), as incorporated into the Consent Arbitral Award dated 23rd February, 2022 (“Consent Arbitral Award”) passed by the Arbitral Tribunal, including, disputes arising from the alleged breach, non-compliance, revival of original claims and other consequential and additional claims.
2. O.M.P.(I) (COMM.) 23/2026 has been filed under Section 9 of the Arbitration Act, seeking interim measures for preservation of the subject matter under the Consent Arbitral Award, read with the Settlement Agreement, on the premise of the respondent’s persistent, wilful and fundamental breach of the Settlement Agreement entered into between the parties.
3. As per the facts, culled out from the pleadings and documents on record, the petitioners entered into a Memorandum of Understanding (“MoU”) with the respondent on 31st May, 2017, for the purposes of forming a Joint Venture (“JV”) and for participating in tenders for various construction works issued by the National Highways Authority of India (“NHAI”) and State Governments.
4. By way of the aforesaid MoU, it was agreed between the parties that the respondent shall arrange only the bid security/earnest money deposit, and upon award of any project to the JV, the petitioners shall arrange the following:
A. Performance Bank Guarantee.
B. Additional Performance Bank Guarantee (if required).
C. Retention Bank Guarantee.
D. Mobilization or Advance Bank Guarantee.
5. It was further agreed upon by the parties that if the petitioners failed to submit the Bank Guarantee in terms of the aforesaid, then it shall not be entitled to receive any fee or compensation.
6. The JV between the petitioners and the respondent was awarded the following three contracts:
a) Upgradation of 6 lane with paved shoulders of Limbdi – Sayla section of NH 8A (New NH 47) from Km. 99+000 to Km. 138+000 on EPC mode in the State of Gujarat (‘Project’) (hereinafter referred to as Package 3 of Gujarat Projects)
b) Upgradation of 6 lane with paved shoulders of Rajkot - Bamanbore section of NH 8B (New NH 27) from Km. 185+230 to Km. 216+000 on EPC mode in the State of Gujarat (‘Project’) (hereinafter referred to as Package 5 of Gujarat Projects)
c) Six lanning of existing 4 lane road from Gundugolanu (Design Km 1023.280) to Kalapurru (Design Km 1050.680) of NH – 5 (New NH – 16) (Design lenth = 27.400 km) in the State of Andhra Pradesh under NHDP Phase-V under Bharatmala Pariyojana on EPC (Engineering Procurement and Construction) Mode (hereinafter referred to as Vijayawada Project)
7. With respect to the aforesaid Engineering, Procurement and Construction Contracts (“EPC Contracts”) mentioned at serial nos. (a) and (b), upon issuance of a Letter of Acceptance dated 01st December, 2017 to the JV by the Government of Gujarat, the petitioners and the respondent executed two separate Joint Venture Agreements dated 31st December, 2017, in respect of Package-3 and Package-5 of the Gujarat Projects. As per the said JV Agreements, the petitioner no. 1 undertook to furnish the Ban




Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.