SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 393

IN THE HIGH COURT OF DELHI AT NEW DELHI
TEJAS KARIA, J.
Nbcc India Limited - Petitioner
Versus
Gnc Infra Llp And Anr. - Respondents
CM(M) 1181 of 2022 & CM Nos. 47354 of 2022, 47355 of 2022, 42813 of 2025 & 60377 of 2025
Decided On : 15-06-2026

Advocates Appeared:
For the Petitioner:Mr. Mohit Arora, Advocate
For the Respondent:Mr. Alok Bhachawat, Mr. Ishan Jain, Mr. Vishnu Dhangal, Advocates.

An interim direction for a third party to deposit funds is legally unsustainable in the absence of a decree or a crystallized, undisputed liability, particularly when the party is not privy to the underlying contract in dispute.

Headnote:(A) Code of Civil Procedure, 1908 - Order XXXIX Rules 1 and 2 - Interim relief - Deposit of amount in court - A court cannot direct a third party to deposit an amount in court as an interim measure in the absence of a crystallized, undisputed liability or a prior decree. (Paras 14, 15, 17)

(B) Impleadment - Proper party - A party maintaining no privity of contract with the plaintiff and against whom no substantive relief is sought is neither a necessary nor a proper party to the suit. (Paras 20-22)

Facts of the case:
A plaintiff instituted a civil suit for recovery against a contractor and a third party, who was the principal entity in the project. The trial court directed the third party to deposit the suit amount in the court as an interim measure. The third party approached the appellate court, challenging the order on the grounds that they had no contract with the plaintiff and that the trial court's order was an unreasoned direction without established liability.

Findings of Court:
The court observed that a garnishee-like direction at a pre-decree stage is impermissible when the underlying debt is not admitted or adjudicated. It further noted that as the third party had no direct contractual obligation to the plaintiff, the initial order was legally unsustainable as it lacked foundation in law or fact.

Issues: Whether an interim direction compelling a third party to deposit funds is permissible in the absence of a decree or a crystallized debt, and whether such a party constitutes a necessary party to the litigation.

Ratio Decidendi: The court held that interim directives against third parties are legally untenable in the absence of a proven, crystallized liability. A court cannot rely on the whims of the parties to create an obligation for a third party when that party is not a necessary entity to the substantive dispute.

Result: Petition allowed.

Table of Content
1. establishing the factual and procedural nexus of the litigation dispute. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. contentions regarding privity of contract and necessity of party impleadment. (Para 7 , 8)
3. analysis of the validity of interim orders in the absence of reasoning. (Para 9 , 10 , 11 , 12 , 13)
4. garnishee orders require crystallized and admitted liability for enforcement. (Para 14 , 15 , 16 , 17 , 18 , 19)
5. effect of an order deleting a party from the array of defendants. (Para 20 , 21)
6. precedents on the non-sustainability of financial directions against non-party garnishees. (Para 22 , 23 , 24)
7. final judicial determination setting aside the unsustainable trial court order. (Para 25)

JUDGMENT :

TEJAS KARIA, J.

INTRODUCTION

1. The present Petition assails the Order dated 27.09.2022 (“Impugned Order”) passed by the Court of Ms. Nirja Bhatia, District Judge (Commercial Court-06), South-East District, Saket District Courts (“Trial Court”), in CS (Comm) No. 350/2020 (“Suit”), instituted by Respondent No. 1 against Respondent No. 2 and the Petitioner, who were arrayed as Defendant Nos. 1 and 2, respectively.

FACTUAL MATRIX

2. In the Suit, it is the case of Respondent No. 1 / the Plaintiff that:

2.1. On 02.09.2015, the Petitioner awarded a contract to Respondent No. 2, vide a Letter of Award, for the construction of the National Investigation Agency (“NIA”) Branch Office, Residential Building, and allied works at HI-Tech City, Hyderabad, Telangana (“Project”). Pursuant thereto, an agreement was executed between the Petitioner and Respondent No. 2 on 26.10.2015.

2.2. After the award of the work to Respondent No. 2, Respondent No. 2 further sub-contracted the same to Respondent No. 1. Owing to payment disputes, the sub-contract was mutually terminated. Thereafter, on 10.11.2018, Respondent No. 1 and Respondent No. 2 arrived at an understanding that the payment disputes would be evaluated on the basis of the work executed by Respondent No. 1 from October 2017 to April 2018, along with the evaluation and reconciliation of RA Bill Nos. 14 to 17.

2.3. Thereafter, the work executed by Respondent No. 1 was evaluated and, on the basis of such evaluation, a Settlement Agreement dated 20.11.2018 was executed between Respondent No. 1 and Respondent No. 2. In terms of the said Settlement Agreement, Respondent No. 2 agreed to pay Respondent No. 1 a sum of Rs. 1,00,00,000/- towards full and final settlement of all dues payable to Respondent No. 1 up to 20.11.2018.

2.4. In discharge of the aforesaid liability, Respondent No. 2 issued two cheques in favour of Respondent No. 1 aggregating to Rs. 60,00,000/- and further assured that the balance amount of Rs. 40,00,000/- would be paid on or before 30.11.2019. Subsequently, both the cheques issued by Respondent No. 2 in favour of Respondent No. 1 were allegedly dishonoured on the grounds of “Funds Insufficient” and “Payment Stopped by Drawer”.

2.5. In respect of the aforesaid dishonour of cheques, Respondent No. 1 instituted two complaints against Respondent No. 2, which are stated to be pending adjudication before the Court of the Metropolitan Magistrate, Saket Courts, Delhi.

2.6. Respondent No. 1 further issued a legal notice to the Petitioner, requesting that any outstanding amount payable to Respondent No. 2 in relation to the Project not be released in favour of Respondent No. 2 from the bank guarantee furnished by Respondent No. 2.

2.7. Thereafter, another notice was issued to the Petitioner, whereby Respondent No. 1 claimed release of an amount of Rs. 1,00,00,000/- in its favour.

3. As Respondent No. 2 allegedly failed to make the payment of the settlement amount in terms of the Settlement Agreement dated 20.11.2018, Respondent No. 1 filed the Suit against both Respondent No. 2 and the Petitioner, inter alia, praying for the following relief:

“It is therefore, most respectfully prayed that this Court may be pleased to pass a decree:

a) In favor of the Plaintiff firm and against the defe

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top