Tejas Karia, J
CENTRAL TRANSMISSION UTILITY OF INDIA LTD – Appellant
Versus
IDBI BANK LIMITED & ANR. – Respondent
LPA 456/2026 | CM APPLs. 39702/2026 | CM APPLs. 39703/2026 | CM APPL. 39701/2026



Important Points

Disputes regarding the interpretation of bank guarantee terms and the validity of their invocation involve disputed questions of fact and are civil in nature, making them unsuitable for writ jurisdiction under Article 226 of the Constitution of India.

Subject

Civil - Banking Law

Act Referred

Limitation Act, 1963: S.5
Constitution of India, 1950: Art.226

Headnote

The case involves a dispute over the invocation of a bank guarantee under a Transmission Agreement. The appellant sought a direction under Article 226 of the Constitution of India, 1950, for the release of ₹8.7 crores, which the respondent bank refused on the grounds that the guarantee was not invoked within the stipulated timelines. The court found that the dispute is essentially contractual and involves disputed questions of fact. The primary issue is whether the writ jurisdiction under Article 226 is maintainable for disputes concerning the interpretation of bank guarantee terms and the validity of its invocation. The court reasoned that such disputes "fall within the domain of civil proceedings and ought not to be agitated in the writ jurisdiction" as they require a detailed examination of evidence and contractual terms, and where an alternative efficacious remedy exists, the extraordinary writ jurisdiction should not be invoked. Consequently, the present Appeal, along with pending Applications, is dismissed.

Advocates:
For the Appellants/Petitioners: S.B. Upadhyay, Amisha Upadhyay, Sidharth Sharma
For the Respondents: None

Table of Content
1. disposal of interlocutory applications regarding exemptions and condonation of delay. (Para 1 , 2 , 3 , 4 , 5)
2. factual background of the dispute regarding the invocation of a bank guarantee. (Para 6 , 7)
3. arguments on the maintainability of a writ petition for enforcing regulatory banking obligations. (Para 8 , 9 , 10 , 11)
4. analysis of whether contractual disputes over bank guarantees are amenable to writ jurisdiction. (Para 12 , 13 , 14 , 15)
5. principle that disputes involving factual inquiries and contractual terms require civil proceedings over writ jurisdiction. (Para 16 , 17 , 18 , 19)
6. final dismissal of the appeal based on the availability of an alternative efficacious remedy. (Para 20)

TEJAS KARIA, J. (Oral)

CM APPLs. 39702/2026 & 39703/2026 (Exemptions)

1. Exemption is allowed, subject to all just exceptions.

2. The Applications stand disposed of.

CM APPL. 39701/2026 (Condonation of Delay)

3. The present Application has been filed under Section 5 of the Limitation Act, 1963 seeking condonation of delay in filing the present Appeal.

4. For the reasons stated in the Application, the same is allowed. Accordingly, the delay of 30 days in filing the present Appeal is condoned.

5. The Application stands disposed of.

LPA 456/2026

6. The present intra-court Appeal has been filed assailing the Order dated 19.03.2026 (“Impugned Order”) passed by the learned Single Judge in W.P.(C) No. 9305/2024 (“Writ Petition”), wherein the Appellant prayed for issuance of direction to Respondent No. 1 to release an amount of ₹8.7 crores to the Appellant under the bank guarantee dated 26.05.2016 bearing No. 1601331BGP00255 (“Bank Guarantee”). By way of the Impugned Order, the Writ Petition was disposed of with liberty to the Appellant to file a suit in accordance with law.

7. The brief facts of the case leading to the filing of the present Appeal are as under:

7.1. The Appellant, Central Transmission Utility of India Limited, and Respondent No. 2, Lanco Vidarbha Thermal Power Limited, entered into a Transmission Agreement dated 31.03.2016 (“Transmission Agreement”), whereby connectivity and a dedicated transmission system were to be provided for evacuation of power from the proposed generating station at Warora, Maharashtra, to the inter-State transmission system.

7.2. Pursuant to the Transmission Agreement, Respondent No. 2 furnished 22 bank guarantees in favour of the Appellant, aggregating to ₹66 crores. The Appellant invoked 11 bank guarantees amounting to approximately ₹32 crores, including the Bank Guarantee of ₹8.7 crores, vide letter dated 17.12.2020 (“Invocation Letter”).

7.3. Thereafter, the Appellant, by letter dated 12.01.2024, called upon Respondent No. 1 to remit the full guaranteed sum in terms of the Invocation Letter. Respondent No. 1, however, by letter dated 05.02.2024, declined the said request on the ground that the Bank Guarantee had not been invoked within the stipulated timelines.

7.4. Subsequently, by letter dated 12.02.2024, the Appellant once again called upon Respondent No. 1 to release the amount in terms of the Invocation Letter. Respondent No. 1, by letter dated 16.02.2024, reiterated its refusal, asserting that the Appellant had neither invoked the Bank Guarantee within the prescribed period nor requested extension thereof.

7.5. The Appellant asserts that the validity of the Invocation Letter issued by it had been upheld by both the National Company Law Tribunal (“NCLT”) and the National Company Law Appellate Tribunal (“NCLAT”). Despite the same, Respondent No. 1 failed to honour the Bank Guarantee issued in favour of the Appellant.

7.6. Consequently, the Appellant instituted the Writ Petition before this Court, which came to be disposed of by the Impugned Order, granting liberty to the Appellant to institute appropriate civil proceedings in accordance with law. Aggrieved thereby, the present Appeal has been preferred before this Court.

8. Learned Senior Counsel for the Appellant

1