2026 Supreme(Online)(Del) 15127
IN THE HIGH COURT OF DELHI AT NEW DELHI
Neena Bansal Krishna, J
RAVINDER SONI AND OTHERS – Appellant
Versus
SANATAN DHARAM SABHA HARI MANDIR REGD AND OTHERS – Respondent
RSA 198/2023|CM APPL. 30826/2025
Important Points
Subject
Civil Law - Property Law
Act Referred
DMC Act: S.477, S.478, S.343, S.344, S.345A
Specific Relief Act, 1963: S.41(j)
Easement Act, 1882: S.15, S.33
Headnote
For the Appellants/Petitioners: R.K. Bhardwaj
For the Respondents: Nusrat Hossain, Manish Kumar Singh, Sarv Mangla, Chetanya Singh, Chetan Sharma, Swati
| Table of Content |
|---|
| 1. suit for injunction against unauthorized construction dismissed as relief was already satisfied by municipal sealing and demolition. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15) |
| 2. challenge to the finding that relief was satisfied and questioning the locus standi of the plaintiffs. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26) |
| 3. reliefs for restraining future construction are premature and current reliefs are infructuous. (Para 27 , 28 , 29 , 30) |
| 4. residency alone does not grant locus standi without proof of infringement of easementary rights. (Para 31 , 32 , 33 , 34 , 35 , 36 , 37) |
| 5. appeal dismissed due to lack of merit and absence of substantial questions of law. (Para 38 , 39 , 40) |
J U D G M E N T
NEENA BANSAL KRISHNA, J.
1. Second Regular Appeal under Section 100 of the Code of Civil Procedure, 1908 (hereinafter referred to as „CPC‟) has been filed on behalf of the Appellants against the Judgment and decree dated 19.04.2023 whereby the learned Additional Senior Civil Judge, Delhi had upheld the Judgment of learned Civil Judge dated 12.02.2020, dismissing the Suit of the Plaintiff for Permanent Injunction for restraining the Defendant Nos. 2 to 6 from raising an illegal and unauthorised construction in the Suit Property and for Mandatory Injunction for directing the Defendants to demolish the unauthorised construction raised in the Suit Property and further to restrain them from raising any unauthorised construction in future.
2. The Plaintiffs/Appellants had instituted Civil Suit No. 873/2018 for Permanent Injunction and Mandatory Injunction.
3. The facts in brief, as narrated in the Plaint, were that the Plaintiffs were residing in the same locality at the addresses mentioned in the Memo of Parties and had since long also been working as social workers in the locality.
4. It was asserted that the Defendant Nos. 2 to 6, who are the officials of the Defendant No. 1, a registered Organisation, in connivance with the Defendant Nos. 7 and 8, were raising unauthorised and illegal construction of a multi-storey commercial complex for shops and multiple floors, at the Property bearing No. 6893, Qila Kadam Sharif, Nabi Karim, Paharganj, New Delhi-110055 (hereinafter referred to as “the suit property”).
5. It was claimed that such construction would create a problem of parking and hurdles in the street, due to increase in the number of occupants/owners in such illegally constructed portions of the suit property. The Plaintiffs claimed that the area was thickly populated and congested and it would be unsafe for the Plaintiffs to pass through the said gali/road.
6. The Plaintiffs had made several complaints to Defendant Nos. 7 and 8 for taking action against the unauthorised and illegal construction, but all in vain.
7. Hence, the Suit for Permanent and Mandatory Injunction was filed by the Plaintiffs/Appellants.
8. Defendant No. 7, NDMC, in their Written Statement, took the preliminary objections that the Suit was barred under Sections 477 and 478 of DMC Act , for want of service of Statutory Notice under DMC Act .
9. It was further asserted that the Suit Property was inspected on 07.03.2018 by the Field Staff of NDMC and during inspection, unauthorised construction of Ground Floor and rooms, etc. on First Floor were noted, which were booked vide File dated 07.03.2018 under Section 343 and 344 of the DMC Act . Show Cause Notice was issued on 07.03.2018 to the owner/builder of the Property to the respondent within three days, as to why demolition Order be not passed in regard to unauthorised construction carried out on the Property. It was stated that the action against unauthorised construction on the Property was under contemplation and would be taken, as per the provisions of DMC Act .
10. There was no ongoing construction in the Property, which has been stopped with the help of local Police. Sealing action