2026 Supreme(Online)(Del) 23672
IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 13th OCTOBER, 2026
CNR No. DLHC010009452022
O.M.P. (COMM) 23/2023 & I.A. 1241/2023
SOM SHIVA IMPEX LTD. .....Petitioner
versus
NATIONAL RESERACH DEVELOPMENT CORPORATION & ANR. .....Respondents
Through: Mr. Rajshekhar Rao, Sr. Adv. with Mr. Malak Bhatt and Ms. Sukanya Joshi, Advs.
Through: Mr. JM Kalia, Mr. Siddhartha Shukla and Mr. Dhruv Kalia, Advs. Along with Mr. AP Singh, Sr. Manager (Legal).
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
SUBRAMONIUM PRASAD, J
OCTOBER 13, 2026
VG
JUDGMENT
1. The present petition has been filed under Section 34 of the Arbitration and Conciliation Act, 1996 (herein referred to as the “Act”) against the award dated 29.09.2022 passed by the Learned Sole Arbitrator.
2. Shorn of unnecessary details, the facts leading to the filing of the present petition are as under:
3. The Petitioner, M/s. Som Shiva (Impex) Limited (hereinafter referred to as “SSIL”), is a company incorporated under the provisions of the Companies Act, 1956, having its registered office in Ahmedabad, Gujarat, and is primarily engaged in the commercial manufacturing of plastic master batches. SSIL was the original Respondent and Counter-Claimant in the arbitral proceedings.
4. Respondent No. 1, National Research Development Corporation (hereinafter referred to as “NRDC”), is an enterprise of the Government of India under the administrative control of the Department of Scientific and Industrial Research, established with the mandate to promote, develop, and commercialise industrial technology and innovations.
5. Respondent No. 2, the Department of Scientific and Industrial Research (hereinafter referred to as “DSIR”), is a department under the Ministry of Science & Technology, Government of India. NRDC and DSIR were the joint Claimants in the arbitral proceedings.
6. In June 2010, DSIR launched the Technology Development and Demonstration Programme under the broader Technology Promotion, Development and Utilisation scheme to provide partial financial support to Indian industrial units for research, development, and commercialisation of indigenous technologies.
7. Pursuant to the launch of the scheme, SSIL submitted a formal project proposal on 01.10.2010 titled “New Process Development for Special Elastomer Compound”, aimed at developing an innovative modified Polycarbonate and Nylon 6 blend.
8. Upon evaluating the proposal, DSIR issued a financial sanction on 24.10.2011 approving partial financial assistance to the extent of ₹2,70,00,000/- (Rupees Two Crores Seventy Lakhs) against an estimated overall project cost of ₹7,74,25,000/-. In execution of the sanction, DSIR actually disbursed a total sum of ₹2,40,00,000/- (Rupees Two Crores Forty Lakhs) across multiple tranches between the years 2011 and 2015.
9. On 12.10.2011, to formalise the terms of funding, development, and commercialisation, the parties executed two distinct bilateral and multilateral instruments, namely, a Tripartite Agreement (TPA) executed between DSIR, NRDC, and SSIL to define the project parameters, timeline, monitoring mechanism, funding milestones, and post-completion obligations and a Royalty Agreement (RA) executed between NRDC and SSIL to govern the financial return, royalty recovery, and repayment schedule. Under the said agreements, there were certain core contractual obligations. Clause 7 of the TPA stipulated that the project was to be completed within a strict period of 24 months from the date of commencement. Under Clause 4.1(f) read with Clause 11(a) of the TPA and Clause 3 of the RA, SSIL was obligated to pay NRDC an annual royalty calculated at 26% of the actual funds disbursed by DSIR over a span of 5 years (aggregating to 1.3 times the financial grant received) along with applicable GST. Crucially, the liability to pay royalty was expressly contingent upon the commencement of production for captive use and/or commercial sale. In addition to this, in the event of default or delay in remitting royalty instalments, interest was chargeable at the rate of 12% per annum for the initial six months of delay, escalating to 18% per annum thereafter.
10. Another imperative clause was the technology transfer clause being Clause 11(e) of the TPA, according to which, SSIL undertook to assign and transfer the complete technology, design, and know-how documentation to NRDC within 60 days if:
a. SSIL explicitly refused to commercialise the technology within 1 year of project completion; or
b. SSIL failed to achieve commercialisation