2026 Supreme(Guj) 2708
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
J. C. DOSHI, J.
Mukesh Corporation – Appellant
Versus
State Of Gujarat And Anr. – Respondents
R/First Appeal No. 5673 Of 1999, R/First Appeal No. 586 Of 2000
Decided On : 02-07-2026
Act Referred
For the Appellant : Mr Kg Sukhwani
For the Respondent: Ms Kinjal Vyas Assistant Government Pleader
JUDGMENT :
J. C. DOSHI, J.
1. The judgment and decree in Civil Suit No.955 of 1986 dated 19.07.1999 passed by the learned City Civil Judge, Court No.14, Ahmedabad has given rise to the aforesaid two appeals, one by the original plaintiff – M/s. Mukesh Corporation and another by the State of Gujarat and the Executive Engineer, the original defendants. Upon consent of learned Advocate appearing for both the parties, these appeals are decided by common judgment.
2. In Civil Suit No.955 of 1986 filed by the plaintiff – Mukesh Corporation, the learned City Civil Court passed following final order:
“I. The suit is partly allowed.
II. The plaintiff firm is entitled to recover the amount of Rs.46,234.34/- from the defendants along with the interest at the rate of 6% p.a. from the date of the suit till realization.
III. Decree to be drawn up accordingly.”
3. The aforesaid final order came to be passed in backdrop of the fact that the plaintiff – Mukesh Corporation is a registered partnership firm of engineers and contractors doing construction work on contract basis. The Execution Engineer, City (B & C) Division, Ahmedabad invited the tender for construction of Circuit House annexe Building at Ahmedabad in the year 1981. The plaintiff’s tender was accepted for Rs.12,96,057.80/- as against the estimated cost of Rs.10,21,535.51/-. The work order was issued in favour of the plaintiff-firm on 29.12.1981 with a condition to complete the work within a period of 12 months i.e. on or before 28.12.1982. Pursuant to the issuance of work order, an agreement was also executed.
3.1 The plaintiff - firm did not complete the work within the stipulated time period and thus, the work was completed at the risk and cost of the plaintiff - firm. The plaintiff put the blame upon the State Government with usual contention that the State Government failed to perform reciprocal, contractual obligation as much as they could not hand over the site along with the work order and did not supply the material, in as much as, item-wise program, as per clause (2) of the agreement. These dealings were contended for result of not completing the work within the stipulated time period. In addition thereto, the plaintiff pleaded that he had not received regular payment as agreed in contract.
3.2 Absolving itself from not completing the work within the stipulated time period, the plaintiff alleged fundamental breach of contract to the defendant – State, it is stated by the plaintiff that State has wrongly terminated contract on 09.12.1983 and imposed the penalty and levied the compensation. The levy of penalty of Rs.100/- per day commencing from 27.01.1983 to 31.08.1983 is also termed as illegal. It is contended that the plaintiff – firm was not awarded a reasonable opportunity of hearing, nor has been served with a show-cause-notice before imposing penalty and passing of order of termination and thereby the principle of audi alteram partem was not observed. It is further contended that, since time was not the essence of the contract nor it was made as per Section 55 of the Indian Contract Act, imposing of penalty thereof is always in terrorem. Validity of the authority who has passed the termination order is also questioned by the plaintiff on the ground that the competent authority has not received the sanctioned, who has sanctioned the tender, and therefore, in absence of valid termination of contract, the State Government cannot levy penalty.
3.3 In juxtaposition of aforesaid contention, the plaintiff came out with a case that plaintiff is entitled to recover the loss of profit at 20% of remaining un-executed work of Rs.11,00,000/- which would come to Rs.2,20,000/-. The plaintiff also pleaded to add some other amount and filed the suit to recover the amount of Rs.2,88,314.34/- with interest.
3.4 In the written statement filed at Exh.12, the State Government firstly contended that suit is time barred. Secondly, it contended that as per the terms and conditions of the tender agreeme