SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Online)(HP) 551


IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA Arbitration Case No.573 of 2024 Date of Decision : 08.07.2024 Kamla Devi …… Petitioner Versus Land Acquisition Officer-cum-Competent Authority and another ……Respondents Coram:
The Hon’ble Mr. Justice Bipin Chander Negi, Judge Whether approved for reporting?1 For the petitiConer : Mr. Varun Rana, Advocate.
For the respondents : Mr. Raj Kumar Negi, Additional Advocate General, for respondent No.1/State.
Ms. Shreya Chauhan and Ms. Sneh Bhimta, g Advocates, for respondent No.2.

Petitioner Advocates:Varun Rana Suneet Verma ,Respondent Advocate: AG Shreya Chauhan

Bipin Chander Negi, Judge (oral )

The arbitral dispute arises out of the land acquisition in District Bilaspur, H.P. for the purpose of building (widening/ four laning etc.) maintenance, management and operation of National Highway- 21. The land has been acquired under the provisions of National Highways Act, 1956.

2. Arbitration case No. 573 of 2024 pertains to Award No. 37-2016-17 dated 25.11.2016 and structure vide supplementary Award No.37/2 dated  22.01.2018, with respect to which the petitioner had preferred Reference Petition No. 329 of 2019. In the aforesaid reference, the Arbitrator had issued notices for 11.10.2019. The right to file reply was closed on 31.12.2021. Vide order dated 26.12.2022, it was observed that the mandate of the Arbitrator had expired. Hence , the aforesaid arbitral proceedings were kept in abeyance, till othe time period for completing the arbitral proceedings, was extended under Section 29-A.

3. From a perusal of the aforesaid, it is evident that the Reference Petition against the awaurd had been filed by the land owners about 5 years back.

4. The relevant extract of the provisions involved in the present lis, as amended by the Act No 33 of 2019 w.e.f 31.08.2019, are being reproduced here-in-below for a ready reference:-

29-A. Time limit for arbitral award.—(1) The award in matters other than international commercial arbitration be imade by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub- section (4) of Section 23:

(2)…………..

(3) The parties may, by consent, extend the period specified in sub-section (1) for making award for a further period not exceeding six months.

(4) If the award is not made within the period specified in sub-section (1) or the extended period specified under sub- section (3), the mandate of the arbitrator(s) shall terminate unless the court has, either prior to or after the expiry of the period so specified, extended the period: Provided that while extending the period under this sub- section, if the court finds that the proceedings have been delayed for the reasons attributable to the arbitral tribunal, then, it may order reduction of fees of arbitrator(s) by not exceeding five per cent for each month of such delay: Provided further that where an application under sub- section (5) is pending, the mandate of the arbitrator shall continufe till the disposal of the said application: Provided also that the arbitrator shall be given an opportunity of being heard before the fees is reduced. t (5) The extension of period referred to in sub-section (4) may be on the application of any of the parties and may be granted only for sufficient cause and on such terms and conditions as may be imposed by the court.

Section 23. Statements of claim and defence (4) The statement of claim and defence under this section hshall be completed within a period of six months from the date the arbitrator or all the arbitrators, as the case may be, received notice, in writing, of their appointment.”

The sum and substance of the aforesaid provisions is that from the date the arbitrator receives notice the statement of claim and defence (pleadings) shall be completed within a period of six months there from. Further the award shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings. However, the parties may, by consent, extend the period specified for making award for a further period not exceeding six months. If the award is not made within the period specified or the extended period specified the mandate of the arbitrator shall terminate unless the court has, either prior to or after the expiry of the period so specified, extended the period. The extension may be on the application of any of the parties .The same may be granted only for sufficient cause and on such terms and conditions as may be imposed by the court.

5. Having gone through the order shoeets appended with the petitions carefully, th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top