IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA


Arb. Case No. 340 of 2025


Decided on: 1.4.2026


Ramesh Chand & ors.… Petitioners Versus UOI & ors.f …Respondents


Coram Hon’ble Mr. Justice Virender Singh, Judge


Whether approved for reporting?___________________________________________________


For the Petitioners: Mr. Y.P. Sood, Advocate.

For the Defeondants : Mr. Aditya Singh Thakur, Central Government Counsel, for respondent No. 1.

Ms. Sneh Bhimta, Advocate vice Ms. Shreya Chauhan,h Advocate, for respondent No.2.

Ms. Ayushi Negi, Dy. A.G., for respondent No. 3/State.


(Virender Singh)


Judge


1.4.2026


Kalpana

Petitioner Advocates:Y P Sood ,Respondent Advocate: DSGI AG Shreya Chauhan Shreya Chauhan

##PAGE1##

1

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA

Arb. Case No. 340 of 2025

Decided on: 1.4.2026 Ramesh Chand & ors.

… Petitioners Versus

UOI & ors.

f …Respondents _____________________________ _o_____________

Coram Hon’ble Mr. Justice Virender Singh, Judge

Whether approved for reporting?

___________________________________________________

For the Petitioners: Mr. Y.P. Sood, Advocate.

For the Defeondants : Mr. Aditya Singh Thakur, Central Government Counsel, for respondent No. 1.

Ms. Sneh Bhimta, Advocate vice Ms. Shreya Chauhan,

h Advocate, for respondent No.

2.

Ms. Ayushi Negi, Dy. A.G., for respondent No. 3/State.

Virender Singh, Judge (oral) Reply on behalf of respondent No. 1 not filed.

However, it is submitted by learned counsel for respondent No. 1 that reply filed by respondent No. 2 be treated as reply on behalf of respondent No. 1. His

statement is taken on record. Ordered accordingly.

::: Downloaded on - 07/04/2026 20:43:25 :::CIS

##PAGE2##

2

2. The present petition under Section 29 A (4) (5)of the Arbitration and Conciliation Act, 1996 has been filed by the petitioners seeking extension of time for completion of the arbitration proceedings in Arbitration Reference Case No. 102/2017, titled as Ramesh Chand & others vs. NHAI and anr., fpending before the Divisional Commissioner-cum- Arbitrator at Shimla. H.P., exercising the powers of Arbitrator under Section 3

of the National Highways Act, 1956.

3. The arbitral dispute has arisen out of the land acquired in District Shimla H.P. for the purpose of construction of the National Highway, land, for which, has been acquired under the provisions of National

Highways Act, 1956.

4. Feeling aggrieved by the award passed by the competent authority, the landowners have preferred Arbitration Reference Case No.102/2017. before the Arbitrator cum- Divisional Commissioner, at Shimla, and non adjudication of the arbitral proceedings within the statutory period has resulted in filing of the instant

petition.

::: Downloaded on - 07/04/2026 20:43:25 :::CIS

##PAGE3##

3

5. The Reference Petition against the Award was filed by the land owners in the year 2017. According to the petitioners, on account of unforeseen circumstances in the case, unnecessary delay in the announcement of the award by the learned Arbitrator, i.e. the Divisional Commissioner, Shimla District Shfimla, HP., has been

caused.

6. This Court has gone through the material available on record carefully and finds that the proceedings have been conducted by the Arbitrator in violation of statutory provisions, as contained in the Arbitration and Conciliation Act, 1996. This Court is of the view that when, a statute envisages an authority, be it an Arbitrator, to do a particular act in a particular manner and in a prescribed time schedule, then, the onus is upon the said authority/Arbitrator to perform the task entrusted to it, within the time schedule prescribed in the statute. The delay, if any, has to be bonafide and explainable. However, in the present petition, even after completion of the pleadings, the

::: Downloaded on - 07/04/2026 20:43:25 :::CIS

##PAGE4##

4

Arbitrator has closed the proceedings since the time limit

for arbitral proceedings to pass an award had elapsed.

7. In view of aforesaid discussions and taking into consideration the attending facts and circumstance of the case, the Arbitrator-cum-Divisional Commissioner, Shimla. H.P., exercising the powerfs of Arbitrator under Section 3 of the National Highways Act, 1956, is directed to conclude arbitral proceedings and to pass the arbitral award in Arbitration Reference Case No.102/2017, on or

before 25th September, 2026.

8. The petition stands disposed of in the aforesaid

terms.

(Virender Singh)

1.4.2026 Judge

Kalpana

::: Downloaded on - 07/04/2026 20:43:25 :::CIS

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top