SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(HP) 2707

IN THE HIGH COURT OF HIMACHAL PRADESH SHIMLA
Romesh Verma, J
BHUPAL – Appellant
Versus
NHAI AND ANOTHER – Respondent
Arb. Case No. 111 of 2026



Advocates:
For the Appellants/Petitioners: Sneh Bhimta, Shreya Chauhan
For the Respondents: Vikrant Thakur, Diwakar Dev Sharma

When a statute prescribes a specific timeframe for an arbitrator to pass an award, the onus is on the arbitrator to adhere to that schedule, and any delay must be bonafide and explainable.

Headnote:The petitioner sought an extension of time for the completion of arbitration proceedings under Section 29-A (4) of the Arbitration and Conciliation Act, 1996, and Section 3 (G) (5) of the National Highways Act, 1956. The dispute arose from land acquired in District Mandi for National Highway construction, where the landowner filed an arbitration case in 2023. The court found that the arbitral proceedings were not adjudicated within the statutory period, and the Arbitrator had closed the proceedings after the time limit elapsed. The court addressed whether the Arbitrator failed in their statutory duty to pass an award within the prescribed timeframe. The court held that when a statute envisages an authority to perform an act in a prescribed time schedule, the onus is upon that authority to perform the task within that schedule, and any delay must be bonafide and explainable. The Arbitrator-cum-Divisional Commissioner, Kangra at Mandi, is directed to conclude the arbitral proceedings and to pass the arbitral award in Arbitration Case No. 20 of 2023, on or before 20th November, 2026.

Table of Content
1. landowner seeks extension for delayed arbitral proceedings regarding land acquisition. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. arbitrators must adhere to statutory time limits for passing awards. (Para 7)
3. court grants extension for completion of arbitration proceedings. (Para 8 , 9)

Whether approved for reporting?1Whether reporters of the local papers may be allowed to see the judgment?

Romesh Verma, Judge (Oral).

Notice.

2. Mr. Vikrant Thakur, learned counsel and Mr. Diwakar Dev Sharma, learned Additional Advocate General appear and waive service of notice on behalf of the respective respondents.

3. The present petition under Section 29-A (4) of the Arbitration and Conciliation Act, 1996 has been filed by the petitioner seeking extension of time for completion of the arbitration proceedings in Arbitration Case No.20 of 2023, titled as Bhawan Dev vs. NHAI, pending before the Divisional Commissioner-cum-Arbitrator, Kangra at Mandi, H. P., exercising the powers of Arbitrator under Section 3 (G) (5) of the National Highways Act, 1956.

4. The arbitral dispute has arisen out of the land acquired in District Mandi, H.P. for the purpose of construction of the National Highway, under the provisions of National Highways Act, 1956.

5. Feeling aggrieved by the award passed by the competent authority, the landowner has preferred Arbitration Case No.20 of 2023, before the Arbitrator-cum-Divisional Commissioner, Kangra at Mandi, H.P. and non adjudication of the arbitral proceedings within the statutory period has resulted in filing of the instant petition.

6. The Reference Petition against the Award was filed by the landowner in the year 2023. According to the petitioner, on account of unforeseen circumstances in the case, the same has resulted in unnecessary delay in the announcement of the award by the learned Arbitrator, i.e. the Divisional Commissioner, Kangra at Mandi, H.P.

7. This Court has gone through the material available on record carefully and finds that the proceedings have been conducted by the Arbitrator in violation of statutory provisions, as contained in the Arbitration and Conciliation Act, 1996. This Court is of the view that when a statute envisages an authority, be it an Arbitrator, to do a particular act in a particular manner and in a prescribed time schedule, then the onus is upon the said authority/Arbitrator to perform the task entrusted to it within the time schedule prescribed in the statute. The delay, if any, has to be bonafide and explainable. However, in the present petition even after completion of the pleadings, the Arbitrator has closed the proceedings since the time limit for arbitral proceedings to pass an award had elapsed.

8. In view of aforesaid discussions and taking into consideration the attending facts and circumstances of the instant case, the Arbitrator-cum-Divisional Commissioner, Kangra at Mandi, exercising the powers of Arbitrator under Section 3 (G) (5) of the National Highways Act, 1956, is directed to conclude the arbitral proceedings and to pass the arbitral award in Arbitration Case No. 20 of 2023, on or before 20th November, 2026.

9. The petition stands disposed of in the aforesaid terms.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top