IN THE HIGH COURT OF JHARKHAND AT RANCHI
(Letters Patent Appellate Jurisdiction)
------
L.P.A. No. 394 of 2010
-------
Employers in relation to the Management of Jarangdih Colliery of Central
Coalfields Limited, PO and PS Jarangdih, District Bokaro, having its
registered office at Darbhanga House, Ranchi, District Ranchi
…
… Petitioner/Appellant
Versus
Their workmen, represented by Area Secretary, Bihar Colliery Kamgar
Union, Kathara Area, PO- Kathara, P.S. Gomia, District Bokaro
… … Respondent
PRESENT
HON’BLE MR. JUSTICE SHREE CHANDRASHEKHAR
HON’BLE MR. JUSTICE RATNAKER BHENGRA
------
For the Appellant
: Mr. Amit Kumar Das, Advocate;
Mr. Saurav Kumar, Advocate
For the Respondent
: Mrs. M.M.Pal, Sr. Advocate
------
J U D G M E N T
12th January 2023
Per, Shree Chandrashekhar,J.
The Central Coalfields Limited (in short, 'CCL') has challenged
the order dated 13th November 2009 by which the writ petition filed by the
CCL taking exception to the award dated 27th March 2001 in Reference Case
No. 96 of 1995 has been dismissed.
2.
By an order dated 22nd August 1995, in exercise of the powers
under section 10(2-A) of the Industrial Disputes Act, 1947 the Central
Government has made the following reference for adjudication by the Central
Government Industrial Tribunal No.1 (in short, 'Tribunal'), Dhanbad:
“Whether the demand of the Union for the regularization of the
services of S/Shri Laljee Saw and others (as per list enclosed) by
the management of Jarangdih Colliery of M/s Central Coalfields
Ltd. is justified? If so, to what relief are the concerned workmen
entitled?”
3.
Before the Tribunal, the workmen set up a plea that the work
performed by them through different contractors was permanent and
perennial in nature; they were working under the direct control and
supervision of the CCL inasmuch as they have been rendering services and
producing goods for the benefits of the CCL. In opposition, the CCL raised
serious dispute on the nature of the work performed by the workmen. It has
put forth a plea that the concerned workmen were never engaged for any
2 LPA No. 394 of 2010
work of permanent and perennial nature rather they were engaged for
short-term jobs by the respective contractors. The CCL has, therefore,
disputed employer-employee relationship between the parties.
4.
During the trial before the Tribunal, the following documents
were laid in evidence on behalf of the workmen:
(i) Identity Cards of the individual workmen (Ext. M-3 series),
issued to them by different contractors.
(ii) Xerox copy of cap-lamp issue register relating to the period
1992 to 1996 (Ext.W-1 series), issued by the Management of
Jarangdih Colliery on different dates.
(iii) Attendance chart (Ext.W-2 Series)prepared purportedly by the
Management of Jarangdih Colliery indicating that the concerned
workmen were engaged under different contractors at different
periods.
5.
The CCL has also produced work orders vide Exts. M-1 and
M-2 issued in favour of M/s Munna Singh, work order vide Ext. M-1/1 in
favour of M/s Bagga Construction, bills submitted by M/s Munna Singh
against the execution of work order vide Ext.M-3 series, registration
certificates under the Contract Labour (Regulation and Abolition) Act, 1970
vide Ext.