HIGH COURT OF JHARKHAND
ILA RANI SAHAY – Appellant
Versus
THE STATE OF JHARKHAND AND ORS – Respondent
WPC 7197/2013
['PANDEY A N ROY', '', 'PRAGATI PRASAD', 'G A -III', '', 'RAY RAJAT NATH']
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P.(C) No. 7197 of 2013
-------
ILA RANI SAHAY W/O Satish Kumar Sinha, Resident of Indraprasth
Colony, Jora Talab, Bariyatu, PO & PS Bariyatu, Dist. Ranchi
...Petitioner
Versus
1. The State of Jharkhand
2. Chief Executive Officer, Ranchi Municipal Corporation, PS Kotwali,
PO GPO, Dist. Ranchi
3. Mukesh Pandey S/O Ram Deo Pandey, Resident of Taj Mahal
Apartment, Club Road, Chutia, PO & PS Chutia, Dist. Ranchi
... Respondents
-------
CORAM
: HON'BLE MR. JUSTICE SHREE CHANDRASHEKHAR
------
For the Petitioner
: Mr. P. P. N. Roy, Sr. Advocate
: Ms. Pragati Prasad, Advocate
For the Respondent-State
: Mr. Ashutosh Kumar Singh,
J.C. to S.C. (Mines)
For the Respondent-R.M.C
: Mr. R. R. Nath, Advocate
-------
06/21.01.2016
On 05.01.2016 the matter was adjourned for considering
the question of maintainability of the writ petition.
2.
Mr. P. P. N. Roy, the learned Senior counsel for the
petitioner referring to order dated 28.02.2011 in W.P.(PIL) No. 1076
of 2011 submits that since this Court has taken suo-motu cognizance
of the illegal construction and business activities in the parking of the
private apartments, the petitioner can maintain the present writ
petition. It is submitted that the petitioner is one of the co-sharers of
the property in question and on that count also, the petitioner has a
valuable interest involved in the matter.
3.
Mr. R. R. Nath, the learned counsel for the
respondent-R.M.C. opposing the writ petition submits that the
present writ petition is directed against an individual that is, the
builder.
2
4.
A perusal of the writ petition discloses that the petitioner
claims herself one of the co-sharers of the land comprised under M.S.
Plot No. 1297 and 1298 admeasuring about 10 kathas. It appears
that an agreement was executed with the respondent no. 3 for
construction of an apartment however, the persons who have
executed the agreement that is, defendant nos. 1 to 3 in the partition
suit, have not been made party in the present proceeding. The
agreement was executed on 31.05.2004 and the petitioner admits
that the property is the suit schedule property in the Partition Suit
No. 50 of 2003. It is averred that after the death of defendant no. 3
who was mother of the plaintiff and defendants of the suit, plaintiff
filed an amendment petition which was allowed vide order dated
05.02.2009 however, she has failed to aver whether an injunction
petition was filed in the suit or not. She also does not claim herself a
resident of Madhukar Apartment. The learned Senior counsel for the
petitioner referring to letter dated 25.11.2011 submits that noticing
illegal construction and commercial activity in the parking of
Madhukar Apartment, the petitioner made a complaint to the Ranchi
Municipal Corporation and the builder was directed to produce map
however, he failed to produce the sanctioned map for construction of
Madhukar Apartment. It is a fact that Partition Suit No. 50 of 2003 is
pending in the Court of Sub-Judge-I, Ranchi. In the said suit there
are as many as seven defendants and the petitioner is one of the
defendants. The petitioner being a co-sharer cannot claim to have an
exclusive right over the property on which the apartment has been
constructed. In these facts, the petitioner cannot claim herself
aggrieved by the alleged illegal construction and commercial
activities in the parking of Madhukar Apartment. The fact that this
Court has taken suo-motu cognizance of the commercial activities in
the parking of the residential apartments in the city of Jharkhand can
not be a ground on which the petitioner can maintain the present
writ petition. The petitioner has produced different note-sheets and
order-sheet of Ranchi Municipal Corporation which appear to be