HIGH COURT OF JHARKHAND
GANAURI MISTRY – Appellant
Versus
Human Resource Development – Respondent
WPC 7375/2012
['DHANAJAY KR DUBEY', '', 'AKSHAY KR MAHATO', 'Sr S C -III']
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P.(S) No. 7375 of 2012
Ganauri Mistry
...
…
…
Petitioner
Versus
1. The State of Jharkhand
2. Secretary, Human Resources Development Department,
Government of Jharkhand, Ranchi
3. Deputy Secretary, Human Resources Development Department,
Government of Jharkhand, Ranchi
4. Director, Primary Education, Human Resources Development
Department, Government of Jharkhand, Ranchi ...
...
Respondents
CORAM:
HON’BLE MR. JUSTICE ALOK SINGH
For the Petitioners
: M/s D.K. Dubey, A.K. Mahato, Advocates
For the State
: Mr. S. Choudhary, G.A., R.K. Shahi, J.C. to G.A.
-----
04/18.12.2012
Present petition is filed assailing the order dated 06.12.2012 (Annexure-
5 to the writ petition), whereby petitioner was placed under suspension for
non-compliance of the order passed by this Court in W.P.(S) No. 900 of 2005.
This case for the first time was taken on 14.12.2012 and learned
counsel for the respondent-State was directed to seek instruction on the
averments made in the writ petition. Case was taken up again yesterday i.e.
on 17.12.2012 and after hearing both the sides for quite sometime, it was
adjourned for today. With the consent of the learned counsel for the parties, it
is being heard and disposed of finally at the admission stage.
Undisputedly, this Court in W.P.(S) No. 900 of 2005, vide judgment
dated 18.10.2008 had directed the respondents of that writ petition to pay the
arrears of salary in favour of the petitioner and also to fix pay of the
petitioner in the appropriate scale in consonance with the recommendations of
the Fitment Committee. This exercise was to be undertaken by the
respondents within four months from the date of receipt of a copy of that
order.
Undisputedly, the present petitioner has joined as District
Superintendent of Education, Hazaribagh on 05.07.2012. Undisputedly, for
the first time, in the month of November, 2012, a representation (Annexure
-1) was placed before the petitioner requesting him to make compliance of the
judgment of this Court dated 18.10.2008 passed in W.P.(S) No. 900 of 2005.
Undisputedly, a Contempt Case was also preferred before this Court for non-
compliance of the judgment of this Court passed in W.P.(S) No. 900 of 2005.
Undisputedly, the judgment of this Court passed in W.P.(S) No. 900 of 2005
2
has already been complied with and reply to the show cause issued in
Contempt Case has already been filed by the petitioner.
The contention of the petitioner is that after joining as District
Superintendent of Education, Hazaribagh, on 05.07.2012, he has taken
prompt action ensuring the compliance of the judgment of this Court dated
18.10.2008 passed in W.P.(S) No. 900 of 2005, and without wasting any time
after receiving the representation (Annexure- 1) on 06.11.2012, entire
payment has been released in favour of the petitioner of W.P.(S) No. 900 of
2005 on 06.12.2012 i.e. within 30 days from the date of receiving the
representation, therefore, placing the petitioner under suspension, vide
impugned order dated 06.12.2012, is totally unjustified, arbitrary and result
of non-application of mind.
Mr. D.K. Dubey, learned counsel appearing for the petitioner, has
vehemently argued that order impugned does not show that any disciplinary
enquiry is contemplated against the petitioner for any misconduct on the part
of the petitioner. He further argues that although the Government servant can
be placed under suspension in contemplation of the disciplinary action or
during the pendency of the disciplinary enquiry, however, suspension order
cannot be automatic and can only be passed when misconduct is so grave
which can result in dismissal or any other major penalty or there is
apprehension that while attending the duties, delinquent employee may
influence the disciplinary acti