2026 Supreme(Online)(J&K) 906
Supple -1 HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU (through Virtual Mode)
Pronounced on 06.10.2026 Uploaded on 07.10.2026
CRM(M) No.779/2024
CrlM No. 1600/2024
c/w
CRM (M) No. 116/2025
CrlM No. 237/2025
CrlM No. 506/2025
Manhar Gupta and ors …Petitioner(s)(with clubbed matter)
VS.
Union Territory of J&K and Others. ...Respondent(s)
Through: Ms Radha Sharma, Adv. ( in CRM(M) No. 779/2024)
Mr. Sunil Sethi, Sr. Advocate With Mr. Paras Sharma, adv.(CRM (M) No. 116/2025)
Through: Mr. Raman Sharma , AAG With Ms. Saliqa Sheikh, Adv
CORAM: Hon’ble Mr. Justice Mohd. Yousuf Wani, Judge
(Mohd. Yousuf Wani)
Judge
Srinagar: 06.10.2026
“Ayaz”
Whether approved for reporting in law journal? Yes
Whether judgment is speaking ?Yes.
JUDGMENT
1. Through the medium of instant petitions having been filed in terms of the provisions of Section 528 of Bharatiya Nagarik Suraksha Sanhita, 2023 (BNSS for short), corresponding to Section 482 of the repealed Code of Criminal Procedure, 1973, (Code for short), the petitioners have thrown challenge to the order dated 13.08.2024 passed by the Court of learned Special Judge Anti-Corruption, Jammu (herein after referred to as ―Special Judge‖ for short), on the final closure report/ Ikhtitami, presented by the Anti-Corruption Bureau, (ACB) Jammu, bearing file number 361/Ikhtitami/2022 titled UT of J&K through Police Station ACB Jammu vs. Shri Manhar Gupta and others (four persons), whereby the learned Special Court rejected the said Final Closure Report/Ikhtitami, which had exonerated the accused public servants, namely: 1. Manhar Gupta, son of Late Sh. A. R Gupta, R/o 168, Sec-D Sainik Colony, Jammu, 2. Asgar Hussain, Late Sh Ghulam Mustafa Ishrat R/o Ishrat Manzil Kishtwar, 3. Tasaduq Hussain Sheikh S/o Sh. Gh. Mustafa Sheikh R/o Village Khalu, BPO Bharla Tehsil Bhaderwah District Doda, and 4. Umesh Perihar, son of Late Shri M. R Parihar, R/o F-53 Karan Nagar, Jammu, who had come to be associated in their official positions in the execution of SAUBHAGYA Scheme in Jammu Province, from any criminal liability and had only recommended departmental action, (D.A)against them for committing violations of the guidelines of the Scheme.
2. The facts of the case relevant for disposal of the instant petitions are that the Government of India launched a scheme, namely Pradhan Mantri Sehaj Bijli Har Ghar Yojna (SAUBHAGYA) in order to electrify each and every un-electrified household up to the last mile connectivity in both urban and Rural areas of J&K through on grid and off grid mode. That the objective of the scheme was to achieve universal household electrification by providing last mile connectivity and electricity connections to all households in rural and urban areas of erstwhile State of J&K.That aforesaid SAUBHAGYA scheme was approved by the Ministry of Power, Government of India on 11.10.2017 and 20.10.2017. That according to the operational guidelines issued for implementation of said scheme, Rural Electrification Corporation Ltd. (RECL), was nominated as Nodal Agency for implementation of the said scheme and beneficiaries under the said scheme were identified by using Socio Economic Caste Census (SECC) done in the year 2011. That SAUBHAGYA scheme was regarded as one of the most successful endeavours of Power Development Department. That it was the largest network expansion program ever happened in the history and was successfully accomplished within a definite and very limited time frame. That a coordinated approach involving various stakeholders and departments from the initial survey to the commissioning of projects, coupled with close monitoring by authorities at various levels and the immediate resolution of bottlenecks, were key attributes to Scheme's success. That being a public benefit scheme, the people remained associated with the Department throughout its implementation period. That the efforts of the departmental workforce, particularly those operating in remote and inaccessible areas were highly appreciated. That these workers provided connections to households that had been without electricity for the past 70 years. That additionally, in some regions, material such as poles and transformers had to be transported manually/head Load over distances of more than 20 km. That pictures documenting the execution of the scheme in the challenging terrains of J&K are available on record and have been featured in various Government of India magazines. That for ensuring last mile connectivity under the scheme, the public involvement was given top priority. That in this regard, various camps were regularly organized to facilitate the release of electricity connections right at the consumers' doorsteps. That the