SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(KAR) 4531

IN THE HIGH COURT OF KARNATAKA, DHARWAD BENCH
MR. JUSTICE ASHOK S. KINAGI, MR. JUSTICE UMESH M ADIGA, JJ
T.g. Shet – Appellant
Versus
Managing Director, N.w.k.r.t.c., Central Office – Respondent
REGULAR FIRST APPEAL NO. 100041 OF 2020 (MON)



Advocates:
Advocate Appeared:
For the Appellant : SRI. V.G BHAT, ADV
For the Respondent: SMT. VEENA HEGDE, ADV FOR R1, (ABSENT) SRI. SHIVAKUMAR S BADAWADAGI, ADV FOR R2 & R3

The court affirmed that a contractor must complete work as per contract terms to claim payment, and failure to do so negates entitlement to revised rates.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 8 and Section 11 - Contractual dispute - Plaintiff, a Class-I Contractor, sought recovery of Rs.1,56,61,745/- for construction work, claiming delays were due to defendants' actions - Defendants contended suit was barred by limitation and that plaintiff failed to complete work as per contract terms - Trial court dismissed the suit, ruling that plaintiff did not prove completion of work or entitlement to revised rates. (Paras 5, 10, 12, 28, 32)

(B) Limitation - The court found that the plaintiff's claims were filed within the limitation period as he was pursuing alternate remedies - The defendants' argument regarding delay was not upheld. (Paras 30, 31)

(C) Jurisdiction - The court addressed the issue of jurisdiction, confirming that the trial court had the authority to hear the case despite defendants' claims of non-joinder of necessary parties. (Paras 7, 10, 12)

Facts of the case:
The plaintiff entered into a contract for construction work but faced delays attributed to the defendants, leading to a claim for unpaid amounts. The defendants argued the suit was barred by limitation and that the plaintiff had not completed the work as per the contract.

Findings of Court:
The trial court found that the plaintiff failed to prove completion of work and dismissed the suit.

Issues: The main issues included whether the plaintiff completed the work, whether the defendants were liable for payment, and whether the suit was barred by limitation.

Ratio Decidendi: The court ruled that the plaintiff did not fulfill contractual obligations and thus was not entitled to the claimed amounts.

Result: Regular First Appeal is dismissed.

ORAL JUDGMENT

(PER: THE HON'BLE MR. JUSTICE ASHOK S. KINAGI)

This Regular First Appeal is filed by the appellant challenging the judgment and final decree dated 19.10.2019 passed in O.S.No.163/2013 by the learned III Additional Senior Civil Judge and JMFC at Hubballi.

2. For convenience, the parties are referred to based on their rankings before the trial Court. The appellant was the plaintiff and the respondents were the defendants.

3. Brief facts, leading rise to the filing of this regular first appeal, are as follows:

4. The plaintiff filed a suit against the defendants for the recovery of money of Rs.1,56,61,745/- along with the interest at the rate of 18% p.a. from 01.04.2013, till the realization of the suit.

5. It is the case of the plaintiff that he is the Class-I Contractor and undertakes the contract for the construction of Government buildings and other major works on a large scale. The plaintiff had entered into an agreement with defendant No.3 on 23.09.1999 for the estimated amount of Rs.1,24,15,000/-. Defendant No.1, after price negotiation with the plaintiff, had accepted the tender with defendant No.3, at the lowest price of Rs.1,43,05,803/-. It is contended that the plaintiff had agreed to the construction work of a divisional workshop at Bagalkot. The date of commencement of work was considered from 25.10.1999 and the defendants had granted 18 months of time for completion of the work. The plaintiff has to completed the entire project on 17.10.2002, as per the terms and conditions of the said agreement. It is further contended that after completion of the work, the defendants have failed to settle the claim amount as requested by the plaintiff. The plaintiff issued a legal notice dated 10.04.2004 to settle the claim amount, but the defendants did not heed the said request. Hence, the plaintiff had filed an Arbitration Case No.1/2005. After hearing both sides, the trial court, allowed the petition and referred the matter to the Arbitrator. The order of the trial Court was challenged by the defendants, before the Hon’ble High Court, in W.P.No.5653/2008. The writ petition was dismissed and the plaintiff was permitted to file a fresh petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act of 1996’ for short). Thereafter, the plaintiff filed a Civil Miscellaneous Petition in CMP No.208/2011 before this Court, and said petition was dismissed on the ground that the plaintiff is prosecuting the litigation in an alternative forum and accordingly, sought to compute the limitation. It is the case of the plaintiff that there is no delay in completion of work, but the defendants have dragged the matter for one or the other reasons, to avoid the settlement of the bill amount. The plaintiff, due to delays and default on the part of the defendants, was forced to execute certain works beyond the contract period and therefore, it is contended that the defendants are bound to pay the equitable revised rates with an interest, including the charges and security deposits. Hence, prays to decree the suit.

6. In pursuance of service of summons, defendants Nos.1 & 2 appeared before the trial court through counsels and as per the order dated 25.08.2014, defendant No.3 was impleaded and in pursuance of service of summons, he appeared before the Court. Defendant Nos.2 and 3 filed the written statements separately, and defendant No.1 filed a memo, adopting the written statement of defendant No.2.

7. Defendant No.2 filed a written statement, by denying the plaint averments. He contended that the suit of the plaintiff is bad for non-joinder of the necessary party, as defendant No.2 is no way concerned with the suit in hand. It is further contended that the plaintiff has entered into a contract with defendant No.3 on 23.09.1999, and the contract work was carried out at Bagalkot and hence, he has no right to file a suit within the territorial jurisdiction of the Civil Judge and JMFC at Hubballi.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top