SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(KAR) 7758

HIGH COURT OF KARNATAKA
HON'BLE MRS. JUSTICE ANU SIVARAMAN - J, HON'BLE MR. JUSTICE VIJAYKUMAR A. PATIL - J
M/S. S.V. ENTERPRISES ENGINEERS AND CONTRACTORS – Appellant
Versus
THE CHIEF SECRETARY GOVERNMENT OF KARNATAKA – Respondent
WA 1086 of 2021



Petitioner Advocates:SHIVARUDRAPPA SHETKAR ,Respondent Advocate:

The court clarified that claims regarding unpaid contract amounts should be considered despite procedural disputes.

Headnote:The appeal challenges an order denying a writ for payment under Karnataka High Court Act, 1961. The appellant asserted completion of work and claimed unpaid dues, which were admitted by respondents. The core issue, being whether the claim is payable, was resolved in favor of the appellant. The appeal is allowed requiring the respondents to process the dues expeditiously.

Table of Content
1. claim for payment acknowledged as valid. (Para 3 , 4)
2. dispute relates solely to the amount payable. (Para 5 , 6 , 7)
3. court orders processing of payment claims promptly. (Para 8)

ORAL JUDGMENT

(PER: HON'BLE MRS. JUSTICE ANU SIVARAMAN)

We have heard the learned counsel appearing on either side.

2. This writ appeal is filed by the writ petitioner challenging as against the order of the learned Single Judge dismissing the writ petition filed by the petitioner.

3. Learned counsel for the appellant submits that the prayer in the writ petition was for a consideration of the legal notices/representations preferred by the petitioner at Annexure - K and Annexure - K1 and to take appropriate steps to make payment to the petitioner. Learned Single Judge has non-suited the appellant on the ground that the matter is one of contract and that since the valid contract determines the rights and obligations of the parties, a writ petitioner seeking a writ of mandamus would not be maintainable.

4. Learned counsel for the appellant submits that there is absolutely no factual dispute between the parties and the respondents have also admitted that works had been completed by the appellant and the amounts are due. It is submitted that in the above circumstances, the dismissal of the writ petition was completely unwarranted.

5. Learned counsel appearing for respondents No.3 to

6 submits that there was two contracts for the conduct of work by the appellant as claimed by the appellant. It is further submitted that the estimated work was for an amount of Rs.82,81,000/- for one work and Rs.25,60,000/- for other work. The works were commenced on 20.12.2006 and 08.06.2006, respectively and were actually completed by the appellant on 10.08.2007 and 15.11.2006. It is submitted that as regards the first work, the appellant was liable to be paid only Rs.62,47,692.50/- as per the actual measurements taken at the time of completion of the said work in the presence of the appellant. Out of which, the appellant had already been paid Rs.57,60,405.20 and hence, due amount is only Rs.4,87,287.74/-. With regard to the second work, it is submitted that though the estimated cost was Rs.25,60,000/- after the completion of the work, it was found that the appellant was liable to be paid only Rs.23,21,145.95/- as per the actual measurements taken after completion of the work in the presence of the appellant. It is further stated that as per the payment register, the appellant has already been paid Rs.21,57,230.10/- and the amount due is only Rs.1,63,915.85. It is therefore contended that the amount due is much lower than what has been claimed by the appellant.

6. Having considered the contentions advanced, we notice that it is an admitted case that two works as claimed by the appellant in the writ petition had actually being carried out by the writ petitioner and that amounts are due to be paid to the writ petitioner as claimed by him.

7. Learned counsel for the appellant submits that the details of the amounts claimed are available in Annexures-K and K1 and that the claim is liable to be considered in accordance with law, which was the only prayer sought for by the appellant in the writ petition.

8. Having considered the contentions advanced, we are of the opinion that the question as to the amount actually payable is the only dispute between the parties and in the absence of any specific dispute with regard to the works done by the appellant, the claim raised by the appellant is liable to be considered by the respondents. In the above view of the matter, this appeal is allowed. There will be a direction to the 5th respondent to take up Annexures - K and K1 and any further representation that the petitioner may wish to submit before the 5th respondent and to consider and pass orders on the same, after hearing the petitioner within four weeks. The amounts found due to be payable to the petitioner shall be paid with interest if any, as provided in the contract.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top