2023 Supreme(Online)(Kar) 34241
KARNATAKA HIGH COURT
M. NAGAPRASANNA, J
THE SCHOOL DEVELOPMENT AND MONITORING COMMITTEE – Appellant
Versus
THE STATE OF KARNATAKA – Respondent
WRIT PETITION No.21595 OF 2022 (GM – RES)
Important Points
Subject
Educational Law - Right to Education
Act Referred
Constitution of India: Article 21-A
Headnote
(B) State's Duty - Obligation to ensure infrastructure and effective machinery for the implementation of the right to education guaranteed under Article 21-A - Failure of state officials exemplifies red-tapism and apathy. (Paras 11, 12)
Facts of the case:
The school was established by the community 35 years ago, leading to its closure due to demolition for highway widening. Compensation awarded but not utilized for rebuilding the school despite attempts. (Paras 2, 3, 4)
Findings of Court:
The State has failed in its duty towards children's right to education by delaying construction despite budgetary availability, necessitating immediate action for compliance. (Paras 18, 19)
Issues: Evaluation of the State's accountability in ensuring the right to education and the Committee’s locus standi in the petition. (Paras 15, 16)
Ratio Decidendi: The right of children under Article 21-A must be prioritized over bureaucratic processes; the State's delay is unjustifiable given the resources available for rebuilding. (Paras 12, 19)
Result: Writ Petition allowed mandating immediate actions for construction of the school by defined timeline.
For the Appellants/Petitioners: SRI PRAKASH M.H.
For the Respondents: SMT.SHWETHA KRISHNAPPA, SRI B.J.SOMAYAJI
| Table of Content |
|---|
| 1. petition for rebuilding a school post-demolition due to highway construction. (Para 2 , 3 , 4 , 5 , 6 , 8) |
| 2. state's responsibility towards ensuring children's right to education. (Para 7 , 12 , 13) |
| 3. court mandates immediate action for construction of school. (Para 11 , 19 , 20) |
ORDER
The petitioner/School Development and Monitoring Committee (‘the Committee’ for short) of the Government Lower Primary School, Agaralingana Doddi, Maddur Taluk is before this Court seeking a direction by issue of a writ in the nature of mandamus directing respondents 1, 3 and 4 to take immediate action for initiation of process of identification of land and re- building of the Government School in Agaralingana Doddi, Maddur Taluk on consideration of representation submitted by the Committee.
2. Heard Sri M.H. Prakash, learned counsel appearing for the petitioner, Smt. Shwetha Krishnappa, learned Additional Government Advocate for respondents 1 to 5 and Smt. B.J.Somayaji, learned counsel appearing for respondent No.6.
3. Brief facts leading to the filing of the present petition, as borne out from the pleadings, are as follows:-
The school at Agaralingana Doddi, Maddur Taluk was established 35 years ago in a small area in the village and the present Committee is the School Development and Monitoring Committee of the Lower Primary School. As and when the strength of students would increase, the need for expanding the school with required infrastructure also increased. Many members in the Village then volunteered and donated 10 guntas of land in favour of the State only for the purpose of building the School at Agaralingana Doddi. Later the Government transferred entire records into the name of the school. The Government school then came within the jurisdiction of the Gram Panchayat as it was in the vicinity of Agaralingana Doddi Gram Panchyat. The State then constructed two rooms, a kitchen and toilet both for boys and girls in the area that was donated by the members of the village and established a new building in the said area. From 2003 upto 2018 the school was functioning in its full swing. 25 students, both boys and girls were studying in the said school from first to fifth standard.
4. In the year 2016 the National Highways Authority of India undertakes a project of widening and upgrading Bangalore – Mysore Highway, NH-275 into a ten-lane road. The land in which the school was established was also notified for acquisition as 732 sq. mts. of the school area was sought to be acquired which led to demolition of entire school building. The National Highways Authority assessed the compensation to the building as also for the land and awarded a compensation of `66,95,098. On assessment of compensation present Committee then makes a representation to the 4th respondent for utilization of compensation amount for purchasing an alternative land for construction of a new school building as the amount was more than sufficient for such construction. The said communication comes about on 03-01-2020, now close to three years. The Committee and the Head Master of the School again collectively requested the 2nd respondent/Deputy Commissioner, Mandya District to take immediate action in this regard. The said representation was submitted by the Committee and the Head Master of the School on 13-01-2020, which is also three years old.
5. On 01-02-2020 the 3rd respondent/Deputy Director of Public Instructions (‘DDPI’ for short) communicated to the 4th respondent/Block Education Officer (‘BEO’ for short) to submit required documents to his office for steps to be taken for construction/reconstruction of the school building. All the documents were submitted on 28-05-2020. Again on 03-06-2020 the Committee through the Head Master represented to the 4th respondent/BEO to take alternative steps for the purpose of conducting classes in view of demolition of the school building. The Government did not identify any land in the vicinity. The members of the vill