2022 Supreme(Online)(Kar) 31338

IN THE HIGH COURT OF KARNATAKA AT BENGALURU

DATED THIS THE 31ST DAY OF MARCH, 2022

BEFORE

THE HON9BLE MR. JUSTICE E.S. INDIRESH

WRIT PETITION NO.4845 OF 2021 (GM-CPC)

BETWEEN

M/S. ABHIRAM INFRA PROJECTS PRIVATE LIMITED

A COMPANY INCORPORATED UNDER THE COMPANIES

ACT, 1956 AND HAVING ITS REGISTERED OFFICE AT

FLAT NO.1A/4, 8-2-618/2/2, R K RESIDENCY ROAD

NO.11, BANJARA HILLS, HYDERABAD-500 034.

(REPRESENTED BY ITS AUTHORISED REPRESENTATIVE

MR. SUNKARA VENKATA RAMANA REDDY)

...PETITIONER

(BY SRI SAMAKSH SOOD, ADVOCATE FOR

SR SUNDARA RAMAN M V, ADVOCATE)

AND

THE COMMISSIONER

KARNATAKA SLUM DEVELOPMENT BOARD

NO.55, ABHAYA COMPLEX

RISALDAR STREET, SHESHADRIPURAM

BENGALURU-560 020.

REPRESENTED BY THE COMMISSONER

&.RESPONDENT

(NOTICE TO RESPONDENT SERVED AND UNREPRESENTED)

THIS WRIT PETITION IS FILED UNDER ARTICLE 227 OF

CONSTITUTION OF INDIA PRAYING TO QUASH THE ORDER

DATED 18TH FEBRUARY, 2021 (ANNEXURE-A) PASSED IN

2

COMMERCIAL EXECUTION PETITION NO.3835 OF 2019 PASSED

BY THE LXXXV ADDITIONAL CITY CIVIL AND SESSIONS JUDGE,

BENGALURU AND ETC.,

THIS PETITION COMING ON FOR PRELIMINARY HEARING

8B9 GROUP THIS DAY, THE COURT MADE THE FOLLOWING:

This Writ Petition is filed by the Decree holder in Execution

No.3835 of 2019 on the file of LXXXV Additional City Civil and

Sessions Judge at Bangalore, allowing the memo dated 16th

January, 2020 filed by the judgment debtor.

2. Facts in nutshell are that, the petitioner had entered

into an agreement No.001/2011-12 dated 03rd August, 2011 for

execution of <Construction of Community Centres at thirteen

locations under Phase-2 and work at the identified slums in

Bengaluru City=. The total amount for the project was

Rs.6,41,58,238/- and the time stipulated to complete the project

was twelve months. However, for the reasons best known to the

parties, the project was not completed within the stipulated

period and as such the respondent herein refuted the claims

made by the petitioner on account of the delay in execution of

work and in that view of the matter the petitioner invoked

3

arbitration clause in the agreement dated 03rd August, 2011. A

Sole Arbitrator was appointed on 23rd October, 2017 for

adjudication of dispute between the parties. The Arbitral

Tribunal, by award dated 08th April, 2019, ordered that the

Decree holder/petitioner is entitled for Rs.63,97,750/- with

further simple interest at the rate of Rs.15.80% (SBI PLR + 2%)

from 09th April, 2016 till realisation. The counter claim filed by

the respondent was rejected by the learned Arbitrator.

Thereafter, the petitioner herein has filed Execution Petition

No.3835 of 2019 on the file of the trial Court to execute the

award made by the learned Arbitrator. In the Execution

Proceedings the judgment debtor filed Memos dated 16th

January, 2020 and 12th December, 2019; and the memo of

calculation filed by the Decree holder on 16th January, 2020.

The trial Court heard the learned counsel appearing for the

parties and allowed the memo dated 16th January, 2020 filed by

the judgment debtor/respondent and as such, modified the

award.

Feeling

aggrieved

by

the

same,

the

Decree

holder/petitioner herein has presented this petition.

4

3. Sri Samaksh Sood, learned counsel appearing for the

petitioner drew the attention of the Court to the award at

Annexure-B made by the learned Arbitrator and also Section 33

of the Arbitration and Conciliation Act, 1996 (for short,

hereinafter referred to as "Act=). He submitted that the

Executing Court has no jurisdiction to correct the award made by

the learned Arbitrator and therefore, he places reliance on the

judgment of the Hon'ble High Court of Delhi in the case of S.P.S.

RANA v. MTNL AND OTHERS decided on 14th January, 2010; in

the case of DO-IT COMPUTER JV A v. THE MUNICIPAL

CORPORATION OF GREATER MUMBAI reported in 2018 SCC

ONLINE Bom.1192; and in the case of UNION OF INDIA v.

POPULAR CONSTRUCTION COMPANY reported in (2001)8 SCC

470. Placing reliance on the above judgments, learned counsel

appearing for the petitioner submitted that neither the petitioner

nor the respondent have filed an application under Section 33 of

the Act and therefore the impugned order passed by the

Executing Court modifying the award requires interference in this

Writ Petition.

5

4. Respondents are served remained absent.

5. In the light of the submission made by the learned

counsel appearing for the petitioner I have carefully examined

the finding recorded by he trial Court in the impugned order

dated 18th February, 2021. Section 33 of the Act provides as

under:

<33. Correction and interpretation of award;

additional award.4

(1) Within thirty days from the receipt of the arbitral

award, unless another period of time has been agreed

upon by the parties4

(a) a party, with notice to the other party, may request

the arbitral tribunal to correct any computation errors,

any clerical or typographical errors or any other errors of

a similar nature occurring in the award;

(b) if so agreed by the parties, a party, with notice to the

other party, may request the arbitral tribunal to give an

interpretation of a specific point or part of the award.

(2) If the arbi

Click Here to Read the rest of this document