2022 Supreme(Online)(Kar) 31338
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
DATED THIS THE 31ST DAY OF MARCH, 2022
BEFORE
THE HON9BLE MR. JUSTICE E.S. INDIRESH
WRIT PETITION NO.4845 OF 2021 (GM-CPC)
BETWEEN
M/S. ABHIRAM INFRA PROJECTS PRIVATE LIMITED
A COMPANY INCORPORATED UNDER THE COMPANIES
ACT, 1956 AND HAVING ITS REGISTERED OFFICE AT
FLAT NO.1A/4, 8-2-618/2/2, R K RESIDENCY ROAD
NO.11, BANJARA HILLS, HYDERABAD-500 034.
(REPRESENTED BY ITS AUTHORISED REPRESENTATIVE
MR. SUNKARA VENKATA RAMANA REDDY)
...PETITIONER
(BY SRI SAMAKSH SOOD, ADVOCATE FOR
SR SUNDARA RAMAN M V, ADVOCATE)
AND
THE COMMISSIONER
KARNATAKA SLUM DEVELOPMENT BOARD
NO.55, ABHAYA COMPLEX
RISALDAR STREET, SHESHADRIPURAM
BENGALURU-560 020.
REPRESENTED BY THE COMMISSONER
&.RESPONDENT
(NOTICE TO RESPONDENT SERVED AND UNREPRESENTED)
THIS WRIT PETITION IS FILED UNDER ARTICLE 227 OF
CONSTITUTION OF INDIA PRAYING TO QUASH THE ORDER
DATED 18TH FEBRUARY, 2021 (ANNEXURE-A) PASSED IN
2
COMMERCIAL EXECUTION PETITION NO.3835 OF 2019 PASSED
BY THE LXXXV ADDITIONAL CITY CIVIL AND SESSIONS JUDGE,
BENGALURU AND ETC.,
THIS PETITION COMING ON FOR PRELIMINARY HEARING
8B9 GROUP THIS DAY, THE COURT MADE THE FOLLOWING:
This Writ Petition is filed by the Decree holder in Execution
No.3835 of 2019 on the file of LXXXV Additional City Civil and
Sessions Judge at Bangalore, allowing the memo dated 16th
January, 2020 filed by the judgment debtor.
2. Facts in nutshell are that, the petitioner had entered
into an agreement No.001/2011-12 dated 03rd August, 2011 for
execution of <Construction of Community Centres at thirteen
locations under Phase-2 and work at the identified slums in
Bengaluru City=. The total amount for the project was
Rs.6,41,58,238/- and the time stipulated to complete the project
was twelve months. However, for the reasons best known to the
parties, the project was not completed within the stipulated
period and as such the respondent herein refuted the claims
made by the petitioner on account of the delay in execution of
work and in that view of the matter the petitioner invoked
3
arbitration clause in the agreement dated 03rd August, 2011. A
Sole Arbitrator was appointed on 23rd October, 2017 for
adjudication of dispute between the parties. The Arbitral
Tribunal, by award dated 08th April, 2019, ordered that the
Decree holder/petitioner is entitled for Rs.63,97,750/- with
further simple interest at the rate of Rs.15.80% (SBI PLR + 2%)
from 09th April, 2016 till realisation. The counter claim filed by
the respondent was rejected by the learned Arbitrator.
Thereafter, the petitioner herein has filed Execution Petition
No.3835 of 2019 on the file of the trial Court to execute the
award made by the learned Arbitrator. In the Execution
Proceedings the judgment debtor filed Memos dated 16th
January, 2020 and 12th December, 2019; and the memo of
calculation filed by the Decree holder on 16th January, 2020.
The trial Court heard the learned counsel appearing for the
parties and allowed the memo dated 16th January, 2020 filed by
the judgment debtor/respondent and as such, modified the
award.
Feeling
aggrieved
by
the
same,
the
Decree
holder/petitioner herein has presented this petition.
4
3. Sri Samaksh Sood, learned counsel appearing for the
petitioner drew the attention of the Court to the award at
Annexure-B made by the learned Arbitrator and also Section 33
of the Arbitration and Conciliation Act, 1996 (for short,
hereinafter referred to as "Act=). He submitted that the
Executing Court has no jurisdiction to correct the award made by
the learned Arbitrator and therefore, he places reliance on the
judgment of the Hon'ble High Court of Delhi in the case of S.P.S.
RANA v. MTNL AND OTHERS decided on 14th January, 2010; in
the case of DO-IT COMPUTER JV A v. THE MUNICIPAL
CORPORATION OF GREATER MUMBAI reported in 2018 SCC
ONLINE Bom.1192; and in the case of UNION OF INDIA v.
POPULAR CONSTRUCTION COMPANY reported in (2001)8 SCC
470. Placing reliance on the above judgments, learned counsel
appearing for the petitioner submitted that neither the petitioner
nor the respondent have filed an application under Section 33 of
the Act and therefore the impugned order passed by the
Executing Court modifying the award requires interference in this
Writ Petition.
5
4. Respondents are served remained absent.
5. In the light of the submission made by the learned
counsel appearing for the petitioner I have carefully examined
the finding recorded by he trial Court in the impugned order
dated 18th February, 2021. Section 33 of the Act provides as
under:
<33. Correction and interpretation of award;
additional award.4
(1) Within thirty days from the receipt of the arbitral
award, unless another period of time has been agreed
upon by the parties4
(a) a party, with notice to the other party, may request
the arbitral tribunal to correct any computation errors,
any clerical or typographical errors or any other errors of
a similar nature occurring in the award;
(b) if so agreed by the parties, a party, with notice to the
other party, may request the arbitral tribunal to give an
interpretation of a specific point or part of the award.
(2) If the arbi