SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Kar) 20014

KARNATAKA HIGH COURT
HANCHATE SANJEEVKUMAR, J
SMT. SUNITA W/O MANOHAR NAGARAHALLI, REP. BY HER GPA HOLDER, CHANNAPPA S/O GUNDAPPA KARAMUDI – Appellant
Versus
KALAKAPPA S/O GUNDAPPA KARAMUDI – Respondent
MISCELLANEOUS FIRST APPEAL NO.105766 OF 2024 (CPC)



Advocates:
For the Appellants/Petitioners: SMT. PADMAJA S. TADAPATRI, FOR SRI K.L. PATIL
For the Respondents: SRI SHIVAPRASAD SHANTANAGOUDAR

A temporary injunction cannot be granted against infrastructure projects when the property owners have executed prior binding agreements.

Headnote:(A) Code of Civil Procedure, 1908 - Order 39 Rule 1 and 2 - Specific Relief Act, 1963 - Sections 20A and 41(ha) - Temporary injunction - The appeal questioned the dismissal of the temporary injunction application concerning the ancestral property - The plaintiff claimed a 1/3rd share - The trial court found that prior agreements executed by defendants No.1 and 2 with defendant No.3 for a wind power project negate the basis for the injunction - The court ruled that given the nature of the agreements and the legislative provisions, no injunction could be granted. (Paras 9, 11, 15)

(B) Temporary Injunction - The plaintiff cannot prevent the action affirmed by legal agreements involving third-party defendants when affording access for project initiation has been acknowledged. (Paras 8, 12, 14)

Table of Content
1. plaintiff's claim of share in ancestral property. (Para 4 , 5 , 6 , 7)
2. defendant's execution of agreements impacts plaintiff's claims. (Para 8)
3. legal agreements with defendant 3 outweigh the plaintiff's injunction request. (Para 9 , 10 , 11)

ORAL JUDGMENT (PER: THE HON'BLE MR. JUSTICE HANCHATE SANJEEVKUMAR) This appeal is filed by the plaintiff, questioning the order dated 22.10.2024, passed by the Senior Civil Judge and JMFC, Ron, in O.S.No.90/2024, on I.A.No.1 filed under Order 39 Rule 1 and 2 of CPC, thereby, the prayer for the relief of temporary injunction is dismissed.

2. Heard the arguments of learned counsels appearing for both the sides and perused the material placed before the Court.

3. For the purpose of convenience and easy reference, ranking of the parties is referred to as per their status before the trial Court.

4. The plaintiff has filed a suit for partition and separate possession by metes and bounds contending that the suit schedule properties are the ancestral and joint family properties by claiming 1/3rd share in all the suit schedule properties. The plaintiff is the daughter of defendants No.1 and 2.

5. Further, the plaintiff pleaded that the defendants No.1 and 2 have entered into agreement of sale dated 13.03.2023 in respect of 01 acre of land in Sy.No.158/3 out of total extent of 08 acres 13 guntas. Further, defendants No.1 and 2 have executed an agreement of lease for 03 acres 25 guntas in the said land. Therefore, pleaded that when the plaintiff is having inherent right of share of 1/3rd in the suit schedule properties, therefore, filed a suit for partition and also filed an application for temporary injunction in respect of land bearing Sy.No.158/3 not to change the nature of land.

6. Though initially the trial Court has granted an ex-parte order of temporary injunction, but subsequently upon hearing both the parties, the trial Court has dismissed I.A.No.1 and an ex-parte order of injunction granted was vacated. Being aggrieved by this, the plaintiff has preferred the present appeal.

7. The grounds urged and the learned counsel for plaintiff submitted that all the suit schedule properties including Sy.No.158/3 are ancestral and joint family properties. Whatever agreement of sale between defendant No.1 and 2 with defendant No.3 as also agreement for lease executed by defendants No.1 and 2 in favour of defendant No.3 is not binding on the share of plaintiff. Therefore, submitted that if defendant No.3 is going to install the project, then it would decline the valuable right of other properties more particularly the portion of the land bearing Sy.No.158/3 which cause deprivation of legitimate right of the plaintiff. Therefore, prays for grant of order of temporary injunction.

8. On the other hand, learned counsel for respondent/defendant No.3 submitted that defendants No.1 and 2 after understanding that defendant No.3 is going to install wind power project on the land bearing Sy.No.158/3 to the extent of 04 acres 25 guntas and accordingly an agreement of sale was executed in respect of 01 acre of land and agreement of lease was executed for remaining 03 acres 25 guntas of land. Therefore, further submitted that the Government of Karnataka has given permission to defendant No.3 for installation of wind power project and accordingly agreement of sale and agreement of lease were executed and when this being the fact, when the plaintiff is claiming 1/3rd share in the other properties, and the land as per lease agreement is only a small extent and for this the entire project cannot be prevented. Also submitted that in clause (8) and (9) of agreement of sale, defendants No.1 and 2 being vendors have specifically agreed for carrying out necessary sketch, soil testing, topography work and rerouting before making installation of the power project and now the plaintiff cannot file application for injunction prohibiting defendant No.3 to carryout the project. Further submitted that as per Section

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top