SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Kar) 33839

IN THE HIGH COURT OF KARNATAKA
N/A, N/A
Karnataka Industrial Area Development Authority – Appellant
Versus
N/A – Respondent
Intra-Court Appeal | W.P No.146875/2020



Advocates:
For the Appellants/Petitioners: Sri.Basavaraj Sabarad, Smt.Sharmila Patil
For the Respondents: Sri.Prashant.F.Goudar

The court clarified that a party cannot be treated as abandoning a project due to delays in acquiring land by the authority responsible, highlighting the entitlement to a refund under specific circumstances.

Headnote:(A) Karnataka High Court Act, 1961 - Section 4 - Agreement dated 02.05.2011 - Land acquisition process - Petitioner seeks refund of deposited amount due to delay in acquisition process - Legal entitlement of the KIADB to forfeit sums upon project abandonment clarified - Court held petitioner did not abandon but sought refund due to KIADB’s delay. (Paras 10, 22, 24)

(B) Writ Jurisdiction - Entitlement of refund and interest - Court examined that learned single Judge was correct in finding KIADB responsible for delay in land acquisition and hence liable for refund with interest. (Paras 10, 24)

Facts of the case:
The petitioner aimed to set up a sugar factory, received approvals, deposited funds, but KIADB failed to complete the acquisition process, leading to requests for a refund.

Findings of Court:
Petitioner entitled to a refund of Rs.27,81,240/- plus interest due to KIADB's delay in land acquisition.

Issues: Primary issue is whether the order of the learned single Judge was erroneous given the circumstances of delay in acquisition process.

Ratio Decidendi: Court affirmed that the petitioner’s delays in requesting refunds were due to KIADB’s inaction in the land acquisition process.

Result: Partial allowance of appeal, directing the refund.

Table of Content
1. appellant's entitlement to seek refund due to delay in land acquisition. (Para 1 , 6 , 18)
2. clarification on kiadb's forfeiture rights under agreements and circular. (Para 2 , 19 , 22)
3. court's finding on the kiadb's breach of obligations. (Para 10 , 24)

1. The present intra - Court appeal is filed under S.4 of the Karnataka High Court Act , 1961 (Hereinafter referred to as the ' Act of 1961'), by the appellant No.1 / Karnataka Industrial Area Development Authority, challenging the order dated 15.09.2021, passed in W.P No.146875/2020, by the learned single Judge, whereunder the learned single Judge has allowed the writ petition filed by respondent No.1 / petitioner.

2. The parties will be referred to as per their ranking before the Tribunal, for the sake of convenience.

3. The factual matrix in brief leading to the present appeal are that the petitioner intended to setup a sugar factory at Devlapurhatti village, Raibhag taluk, Belagavi district and pursuant to the request made by the petitioner, the Government of Karnataka (Hereinafter referred to as the 'GOK'), vide order dated 29.04.2010, granted in principle approval to the project proposal of the petitioner company to setup a 2500 TCD Sugar plant with 12 MW Cogen at Devlapurhatti village of Raibag taluk in Belagavi district. The G.O.K undertook to acquire an extent of 158 acres of land situated in Devlapurhatti village and allotted the same to petitioner through Karnataka Industrial Areas Development Board (Hereinafter referred to as the 'KIADB').

4. The petitioner also obtained an Industrial Entrepreneur Memorandum (Hereinafter referred to as the 'IEM') as required under the Sugarcane (control) (Amendment) O.2006 and also furnished a performance bank guarantee of Rs.1 crore to the Chief Director (Sugars), New Delhi on 23.07.2010, in pursuance of which, the Union Secretary, passed an order dated 15.12.2010, taking the proposed sugar factory of petitioner on record as a new sugar factory.

5. On 02.05.2012, the petitioner entered into an agreement with the KIADB for the purpose of making available land an extent of 158.06 acres situated across several survey numbers in Devlapurhatti village, Raibhag Taluk, Belagavi district, for the purpose of setting up of the said sugar factory. As per the terms and conditions of the said agreement, the petitioner deposited a sum of Rs.1,39,06,200/- on 20.04.2012 being 40% of the tentative amount quoted and intimated the same to the KIADB vide letter dated 23.04.2012. As per the terms and conditions of the agreement, the KIADB was required to take necessary steps to acquire the said land and thereafter, transfer its right, title and interest and possession in favour of petitioner and issue allotment letter.

6. The IEM dated 06.07.2010 was valid only for a period of two years and petitioner sought for extension of the same. Vide order dated 23.07.2012, the IEM was extended by a period of six months and vide order dated 15.01.2013, it was further extended up to 05.07.2013. The petitioner was informed that in the event the petitioner does not take effective steps by 05.07.2013 and commence commercial production on or before 05.07.2015, the performance guarantee furnished by the petitioner would stand forfeited.

7. Since the KIADB did not take requisite steps to acquire the land and handover possession, the petitioner submitted a representation dated 03.09.2014, to the Chief Director (Sugar), New Delhi, requesting for exclusion of time taken for completing the acquisition of land, while computing the time limit for implementation of the IEM. The petitioner also issued a letter dated 29.01.2015 to the KIADB requesting them to expedite the process of land acquisition. On 04.02.2015, the Directorate of Sugar, issued a show cause notice to the petitioner as to why action should not be taken against the petitioner for non - implementing the IEM, to which, the petitioner sent a detailed reply on 06.04.2015.

8. The Special Land Acquisiti

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top