SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Kar) 8238

IN THE HIGH COURT OF KARNATAKA AT BENGALURU
Vibhu Bakhru, CJ, C.M. Poonacha, J
THE CHIEF ENGINEER (ELE) – Appellant
Versus
SRI L S SHIVARAMAIAH – Respondent
WA No. 642 of 2025|W.P. No. 10651/2017|MISCL. No. 114/2006



Advocates:
For the Appellants/Petitioners: H.V. Devaraju
For the Respondents: Kishan G.S.

A claim for compensation for damages caused by electricity line installation is not barred by limitation if the authority fails to prove that notice of compensation was served or payment was made, particularly when the claimant's knowledge is triggered by payments to neighboring landowners.

Headnote:The matter pertains to a claim for compensation under Section 19 of the Indian Electricity Act, 1910, and Sections 10 and 16 of the Indian Telegraph Act, 1885, following the removal of 80 mango trees to facilitate the installation of electricity lines. The lower court awarded compensation, which was subsequently challenged on the grounds of limitation. The court found that the authority failed to produce evidence of serving a notice of compensation or making the actual payment to the claimant. The primary issue was whether the claim was barred by limitation under the Limitation Act, 1963, given that the lines were installed in 1996 but the petition was filed in 2006. The court reasoned that the limitation period is not triggered until the claimant is notified of the compensation; since the claimant only became aware of the entitlement when neighboring landowners were paid in 2006, the petition was timely. The present appeal is dismissed both on the ground of delay and on the merits.

Table of Content
1. background of the compensation claim for tree removal and the dispute over the limitation period. (Para 1 , 2 , 3 , 4)
2. the burden of proof lies on the authority to show that notice of compensation was served or payment was made. (Para 5 , 6 , 7 , 8 , 9)
3. limitation does not bar a claim if the claimant only becomes aware of the entitlement through payments to others in the absence of official notice. (Para 10 , 11 , 12)
4. condonation of delay requires a credible and detailed explanation; failure to provide such leads to dismissal. (Para 13 , 14 , 15 , 16)

Digitally signed by SRIDEVI S

2ND FLOOR

Location: High Court of Karnataka

WRIT APPEAL NO. 642 OF 2025 (GM-KEB)

THIS WRIT APPEAL FILED UNDER SECTION 4 OF THE KARNATAKA HIGH COURT ACT PRAYING TO SET ASIDE THE ORDER, DATED 06.06.2024 PASSED IN W.P. No.10651/2017 BY THE LEARNED SINGLE JUDGE AND CONSEQUENTLY ALLOW THE WRIT PETITION BY QUASHING THE JUDGMENT AND AWARD, DATED 30.01.2016 PASSED IN MISCL.No.114/2006 ON THE 1ST ADDITIONAL DISTRICT AND SESSION JUDGE, AT TUMAKURU AND DISMISS THE CLAIM PETITION IN THE INTEREST OF JUSTICE.

THIS APPEAL, COMING ON FOR PRELIMINARY HEARING, THIS DAY, JUDGMENT WAS DELIVERED THEREIN AS UNDER:

CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE and HON'BLE MR. JUSTICE C.M. POONACHA

ORAL JUDGMENT

(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)

1. The appellants, officials of Karnataka Power Transmission Corporation Limited (hereafter, 'KPTCL'), have filed the present appeal impugning an order dated 06.06.2024 passed by the learned Single Judge of this Court in W.P.No.10651/2017 (GM-KEB).

2. The appellants had preferred the said petition assailing an order dated 30.01.2016 passed by the learned I Additional District and Sessions Judge, Tumakuru [District Court], in Miscellaneous Petition No.114/2006. The said petition was filed by the respondent claiming compensation of an amount of `8,20,000/- for the damages suffered on account of the removal of 80 mango trees. KPTCL had removed the said trees to lay electricity lines on the respondent's land.

3. The respondent's claim was based on the assertion that each mango tree would yield `500. This was contested by the KPTCL. During the proceedings before the learned District Court, KPTCL also raised the issue of limitation. It claimed that the electric lines were drawn in the year 1996. However, the respondent had filed the petition under Section 19 of the Indian Electricity Act, 1910 [Electricity Act], read with Sections 10 and 16 of the Indian Telegraph Act, 1885 [Telegraph Act] in the year 2006. However, no such grounds were raised in the written statement/statement of objections filed by the KPTCL. The said contention was advanced orally at the hearing.

4. The respondent contested KPTCL’s contention that his claim was barred under the Limitation Act, 1963. The respondent claimed that he had never received a notice intimating the compensation fixed for the loss caused, and he continued to await the same. However, in the year 2006, compensation was disbursed to the owners of the neighbouring lands, and therefore, he issued a legal notice to the KPTCL demanding the compensation due. Although, the KPTCL received the notice, it did not respond to the same.

Therefore, the respondent had filed the petition before the learned District Court.

5. The parties led their evidence, and the learned District Court found that the KPTCL was unable to refute the respondent's claim that he had not received any notice of compensation. Although the KPTCL claimed to have paid compensation to the respondent, there is no evidence to establish the same. We may note that the KPTCL has not produced any evidence to show that the compensation has been paid either before the learned Single Judge or in the present appeal.

6. It is not disputed that 400 KV overhead electric transmission lines had been pulled over the land of the respondent, and he wa

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top