SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Kar) 12208

THE HIGH COURT OF KARNATAKA
M. Nagaprasanna, J
Dundappa Malladad – Appellant
Versus
Special Land Acquisition Officer, Karnataka State Highway Authority Project – Respondent
WRIT PETITION No.104133 OF 2025 (LA-RES) | Writ Petition No.104127 OF 2025 (LA-RES)



Advocates:
For the Appellants/Petitioners: Archana A. Magadum
For the Respondents: Girija S. Hiremath

When land acquisition authorities take possession of property, they are statutorily liable to pay interest on the compensation awarded for the period of delay until payment, regardless of whether the final compensation amount was determined or revised through subsequent judicial intervention.

Headnote:(A) Karnataka Highways Act, 1964 - Sections 15 and 19 - Land Acquisition Act, 1894 - Section 34 - Compensation - Payment of interest on delayed compensation - Right to interest from date of possession or agreement - When the amount of compensation is not paid or deposited on or before taking possession of the land, the authority is liable to pay interest under Section 34 of the Land Acquisition Act, 1894. (Paras 3.3, 9, 10)

(B) Writ Jurisdiction - Scope of relief - Judicial intervention against rejection of interest claim - Where acquisition proceeds are delayed due to procedural errors in notification later corrected by court, the entitlement to interest relates back to the initial date of dispossession, and the Authority cannot deny interest simply because payment was made pursuant to a court order. (Paras 6, 11)

Facts of the case:
The petitioners entered into an agreement regarding the acquisition of their land for infrastructure projects. Possession was taken by the authorities in 2014. A subsequent notification under the regional highways legislation reduced the extent of the acquired land, which was later challenged. A coordinate Bench of the High Court directed re-determination of compensation. The authorities paid the enhanced compensation but rejected the petitioners' claim for interest on the delayed payment, prompting the current petitions.

Findings of Court:
The court held that the authorities took possession of the land upon the execution of the agreement in 2014. The subsequent correction of the acquisition extent by the court merely rectified an error, but the deprivation of the property occurred from the initial date. The authorities are legally bound to pay interest for the period of delay under statutory provisions for land acquisition.

Issues: Whether the petitioners are entitled to interest on the compensation amount for the interregnum between the date of possession/agreement and the date of actual payment of compensation, despite the compensation being paid pursuant to a court-directed re-determination.

Ratio Decidendi: Where possession of land is taken by the authorities, the obligation to pay interest on compensation is a statutory mandate. The act of correcting an erroneous acquisition notification does not absolve the state from liability for interest, as the owner remained deprived of the land and its benefits from the date of the original agreement and taking of possession.

Result: Petitions allowed in part; endorsements denying interest quashed; petitioners declared entitled to interest from the date of possession till payment.

Table of Content
1. factual history regarding land acquisition, agreement execution, and re-determination of compensation. (Para 1 , 2 , 3 , 7 , 8)
2. precedents establishing entitlement to interest or damages on delayed compensation payments. (Para 4 , 5 , 6)
3. legal obligation to pay interest on delayed compensation under the land acquisition act. (Para 9 , 10 , 11 , 12)

THESE WRIT PETITIONS HAVING BEEN HEARD AND RESERVED FOR ORDERS, COMING ON FOR PRONOUNCEMENT THIS DAY, THE COURT MADE THE FOLLOWING:-

CORAM: THE HON'BLE MR JUSTICE M.NAGAPRASANNA

CAV ORDER

Both these petitions rank a common string of relief viz., denial of interest on payment of compensation for the period between the date of agreement between the petitioners and the Karnataka State Highways Authorities and, till the date of payment of compensation.

2. Heard Smt. Archana A. Magadum, learned counsel appearing for the petitioners and Smt. Girija S. Hiremath, learned High Court Government Pleader appearing for the respondents.

3. For the sake of convenience, the facts obtaining in Writ Petition No.104133 of 2025 would be narrated:

3.1. The petitioners are the joint owners of non-agricultural land in R.S.No.128/3B situate at Gadag measuring 2 acres 20 guntas. A notification comes to be issued under Section 15 of the Karnataka Highways Act, 1964 (hereinafter referred to as ‘the Act’ for short) notifying the lands of the petitioners to an extent of 16 guntas 08 annas out of 2 acres 20 guntas. The 1st respondent/Special Land Acquisition Officer acquires the notified land and the Chief Project Officer of the Project Implementation Unit of the Karnataka State Highways Development Project fixes the market value of the acquired land at ₹874/- per sq. ft. The market value of the petitioner’s land is subsequently enhanced to ₹1,093/- per sq. ft. on the score that it is a commercial land. In furtherance of the notification under Section 15 of the Act, the petitioners enter into an agreement with the Land Acquisition Officer accepting the market value so determined on 18-11-2014. Three years thereafter, a notification comes to be issued under Section 19 of the Act. The petitioner’s land which was found to be acquired as 16 guntas 8 annas out of 2 acres 20 guntas was now reduced to 10 guntas and the remaining 6 guntas 8 annas is shown as Government road. Pursuant to the said notification under Section 19 of the Act, on 26-08-2019, an award is passed for the land acquired through the preliminary and the amended notification maintaining the acquisition as found in the notification under Section 19.

3.2. On 30-08-2019, the 1st respondent/Special Land Acquisition Officer deposits the award amount to the bank account of the petitioners only to the extent of 10 guntas out of 16 guntas 8 annas. The petitioners then submit a representation seeking compensation for the remaining extent, as it was acquired pursuant to the notification under Section 15 and the land was neither usable by the petitioners nor salable, as agreement was entered into accepting the market price on 18-11-2014. When the representation went unheeded, the petitioners were before the Court in two writ petitions viz., W.P.No.147609 of 2020 c/w 147610 of 2020 seeking a direction to re-determine the compensation. The writ petitions come to be disposed of by a common order dated 11-01-2024 directing the respondents to re-determine the compensation, taking into account the revised market value of the subject land, which at that point in time was ₹1093/- per sq. ft. as against ₹874/- per sq. ft. determined in the year 2014.

3.3. A consent award comes to be passed on 06-06-2024 pursuant to the direction issued by the coordinate Bench of this Court and accordingly, the difference in compensation amount of ₹3,97,66,603/- was directed to be paid to the petitioners. The petitioners now claim that they are entitled for interest on such delayed payment, from the date of agreement till the date of grant of compensation. An endorse

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top