2024 Supreme(Online)(KER) 20725

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE MR. JUSTICE SATHISH NINAN

& THE HONOURABLE MR. JUSTICE JOHNSON JOHN MONDAY, THE 12TH DAY OF AUGUST 2024 / 21ST SRAVANA, 1946 RFA NO. 91 OF 2024 JUDGMENT DATED 11.04.2023 IN OS NO.41 OF 2020 OF SUB COURT,, KOTTARAKKARA APPELLANT/PLAINTIFF:

1 STATE OF KERALA REPRESENTED BY THE SECRETARY TO GOVERNMENT WATER RESOURCES DEPARTMENT, THIRUVANANTHAPURAM, PIN – 695 001.

2 SUPERINTENDING ENGINEER KALLADA IRRIGATION PROJECT (R.B) CIRCLE, KOTTARAKKARA , PIN – 691 531.

BY ADV. SRI. SUJITH MATHEW JOSE, SPL. GOVERNMENT PLEADER

(IRRIGATION)

RESPONDENT/DEFENDANT:

YOHANNAN ABRAHAM S/O, YOHANNAN, PADAPPU PARAYIL HOUSE,PATHANAPURAM TALUK, PIRAVANTHOOR VILLAGE ,PIRAVANTHOOR MURI, KOLLAM DISTRICT,, PIN – 689 696.

BY ADV. SRI. ABDUL LATHIEF T.M THIS REGULAR FIRST APPEAL HAVING COME UP FOR ADMISSION ON 07.08.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

SATHISH NINAN & JOHNSON JOHN, JJ.

--------------------------------------------------------- RFA No. 91 of 2024

--------------------------------------------------------- Dated this the 12th day of August, 2024

Important Points

The court affirmed that an unconstitutional act cannot impede arbitration proceedings, allowing plaintiffs to pursue their claims.

Subject

Civil Law - Contract Law

Act Referred

Headnote

Arbitration - Contractual Dispute - Order VII Rule 11(d) CPC - The court upheld the rejection of the plaint based on the unconstitutionality of the Act, 1998, allowing arbitration proceedings to continue.

Fact of the Case:

The plaintiffs filed a suit for money recovery after the defendant abandoned a contract under the Kallada Irrigation Project. The plaint was rejected under Order VII Rule 11(d) CPC, leading to an appeal.

Finding of the Court:

The court found no illegality in the rejection of the plaint as the Act, 1998 was declared unconstitutional, allowing the plaintiffs to proceed with arbitration.

Issues: Whether the rejection of the plaint under Order VII Rule 11(d) CPC is sustainable and whether the order for costs to the defendant should be interfered with.

Ratio Decidendi: The court concluded that the rejection of the plaint was justified due to the unconstitutionality of the Act, 1998, and the plaintiffs acted in good faith.

Final Decision: The appeal is disposed of with parties bearing their respective costs.

Advocates:
SRI. SUJITH MATHEW JOSE, SPL. GOVERNMENT PLEADER (IRRIGATION), SRI. ABDUL LATHIEF T.M

JUDGMENT

JOHNSON JOHN, J The appellants are the plaintiffs in a suit for realization of money.

2. The appeal is filed challenging the rejection of the plaint as per Order VII Rule 11(d) of the Code of Civil Procedure, 1908. The defendant —Contractor was engaged by the plaintiffs for execution of certain works under the Kallada Irrigation Project. But, the defendant abandoned the work after receiving the part bills and materials. Hence, the plaintiffs terminated the contract and initiated revenue recovery proceedings to realize the difference in the rearrangement of the work and the cost of the materials. The contract contained an arbitration clause. The revenue recovery proceedings were challenged before this Court by the Contractor and as per the judgment in W.A No. 2116 of 2000, it was ordered that the revenue recovery proceedings shall continue only after finalisation of arbitration proceedings. The State had in the meantime enacted the Kerala Revocation of Arbitration Clauses and Reopening of Awards Act, 1998 (‘Act, 1998’ for short) nullifying all arbitration clauses and awards in Government contracts. The validity of the Act, 1998 was challenged before this Court. This Court declared the Act, 1998 to be unconstitutional. Thereafter, the Honourable Supreme Court stayed the said order. But, subsequently, the Honourable Supreme Court upheld the judgment of this Court that the Act, 1998 is unconstitutional. The plaintiffs had filed the suit when the Honourable Supreme Court stayed the order of this Court declaring the Act,1998 as unconstitutional.

3. Heard the learned Special Government Pleader appearing for the appellants and the learned counsel for the respondent.

4. The points that arise for determination are the following:

1. Whether the rejction of the plaint as per Order VII Rule 11(d) CPC is legally sustainable?

2. Whether the order directing the plaintiffs to pay cost to the defendant warrants any interference?

Point No.1:

5. It is not in dispute that the Honourable Supreme Court upheld the judgment of this Court declaring the Act, 1998 to be unconstitutional. It is also not in dispute that the contract between the plaintiffs and the defendant contained an arbitration clause. It is in evidence that the plaintiff appointed arbitrators in view of the judgment in W.A No. 2116 of 2000 and since Act, 1998 is already declared as unconstitutional, the plaintiffs can only proceed with the arbitration proceedings as directed by this Court in W.A. No. 2116 of 2000. In that circumstance, we find no illegality in rejecting the plaint as per Order VII Rule 11(d) CPC by the trial court. The point is answered against the appellant.

Point No.2:

6. The learned counsel for the appellant pointed out that the trial court, apart from rejecting the plaint, also ordered that the defendant is entitled to the cost of the suit and that part of the decree is liable to be set aside, as the plaintiffs instituted the suit during the period when the Honourable Supreme Court stayed the order of this Court regarding the unconstitutionality of the Act, 1998.

7. Considering the facts and circumstance of the case, it cannot be held that the plaintiffs made any frivolous claim or instituted any vexatious proceedings without bona fides. Therefore, we find that the order in the impugned judgment directing the plaintiffs to pay the cost of the suit to the defendant can be set aside and the parties can be directed to bear their respective costs, and we do so.

The appeal is disposed as above.