2021 Supreme(Online)(KER) 37815

HIGH COURT OF KERALA
N. NAGARESH, J
K.S.SHIJU – Appellant
Versus
CHENKAL GRAMA PANCHAYATH – Respondent
WP(C) NO. 19973 OF 2020 | WP(C) NO. 13949 OF 2021 | WP(C) NO. 14390 OF 2021



Advocates:
For the Appellants/Petitioners: B.S.SWATHI KUMAR, ANITHA RAVINDRAN, HARISANKAR N UNNI, SARANGADHARAN P, SHUROOKA.P.K.
For the Respondents: R.T.PRADEEP, S.MOHAMMED AL RAFI, M.BINDUDAS, K.C.HARISH, GOVT. PLEADER, MANU RAJ

The Grama Panchayat holds primary responsibility under the MGNREG Act for project execution and must prioritize public interest over personal interests of individuals in key positions.

Headnote:The petitioner challenges the construction of a bridge under the MGNREGS, claiming it benefits only one individual while reducing canal width, adversely affecting public interest. The court finds significant issues regarding public benefit and directs the District Collector to intervene and decide on project continuance. 'The decisions of the Grama Panchayat... ought to be given due weightage.' The court orders the District Collector to finalize the decisions within two weeks to uphold public interest.

Table of Content
1. challenging a construction under public project regulations. (Para 2 , 3 , 5)
2. dispute over potential legal encroachment of public canal. (Para 6 , 8 , 10)
3. court seeks public interest assessment by authority. (Para 14 , 15 , 16)
4. entrusting oversight responsibility to district collector. (Para 20 , 21)

JUDGMENT

~ ~ ~ ~ ~ ~ ~ ~ ~

Dated this the 6th day of August, 2021

[W.P.(C) Nos.19973/2020, 13949/2021 & 14390/2021]

All the three writ petitions have been filed by the same petitioner, related to same set of facts and cause of action and hence are heard together and being disposed of by a common judgment.

2. The petitioner is a resident of Chenkal Grama Panchayat in Thiruvananthapuram District. The petitioner is aggrieved by the construction of a new bridge and approach road under the Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS), which construction, according to the petitioner, is beneficial only to one influential individual and is being carried out reducing the width of an existing public canal.

3. In W.P.(C) No.19973/2020, the petitioner seeks to direct the respondents to comply with Ext.P7 communication of the Block Programme Officer directing the Panchayat to stop the work. In W.P.(C) No.13949/2021, the petitioner seeks to declare that Ext.P9 communication of the Joint Programme Co-ordinator directing to resume the said work, as illegal. In W.P.(C) No.14390/2021, the petitioner prays for a declaration that respondents 2 to 7 are legally bound to implement Ext.P11 decision of the 1st respondent–Grama Panchayat and stop the work forthwith.

4. The respondents and exhibits marked in these writ petitions are referred to as they are arrayed/marked in W.P. (C) No.14390/2021.

5. In brief, the case of the petitioner is that he is a resident of 1st respondent–Chenkal Grama Panchayat and that the 5th respondent, who is a Panchayat Contractor, has property near the petitioner’s house. Their properties are near Vandichira Canal. A bund of the said Vandichira Canal has now developed as a pathway. The Canal originally had a width of 18 metres and due to encroachments from time to time, the width available now is hardly 7 metres. There is a concrete bridge across the Canal through which two-wheelers and three-wheelers ply. The canal is the source of irrigation water.

6. In the year 2016, the 5th respondent started to encroach upon the Canal making constructions by filling up the sides of the Canal. The petitioner filed O.S. No.730/2019 and the Munsiff Court, Neyyattinkara passed Ext.P2 injunction order restraining the 5th respondent from trespassing into Plaint A Schedule property. Later, the 5th respondent prevailed upon the 1st respondent and managed to get the work of construction of retaining walls on the side of the Canal and construction of a bridge, in the MGNREG Scheme. He obtained the contract for supply of materials for the said work. In the pretext of construction of retaining wall, the 5th respondent is encroaching the Canal reducing its width, for widening the pathway.

7. The petitioner preferred complaints. The 2nd respondent-Joint Programme Co-ordinator and the 3rd respondent-Block Programme Officer made enquiries and found that the entire work is illegal and issued Ext.P6 Stop Memo. The 3rd respondent-Block Programme Officer issued Ext.P7 Stop Memo. However, the 5th respondent, with the active connivance of the 7th respondent-Secretary to Panchayat, proceeded with the work. The petitioner thereupon filed W.P.(C) No.19973/2020. This Court passed Ext.P8 interim order directing the Panchayat to give effect to Ext.P7 Stop Memo. The 2nd respondent-Joint Programme Co-ordinator, however, issued Ext.P9 communication to the 3rd respondent-Block Programme Officer directing resumption of the work. The petitioner thereupon filed W.P.(C) No.13949/2021. This Court passed Ext.P10 interim order restraining the respondents from reducing the width of the Canal.

8. The petitioner contends that the work of con