IN THE HIGH COURT OF KERALA AT ERNAKULAM
MOHAMMED NIAS C.P., J
M.J.MATHEW S/O. OUSEPH(DIED), MEDAPALLIL HOUSE, CHAKKITTAPPARA, KOYILANDY, KOZHIKODE – Appellant
Versus
THE PROJECT DIRECTOR, J.B.I.C. WATER SUPPLY PROJECT KERALA WATER AUTHORITY – Respondent
WP(C) NO. 10037 OF 2014



Important Points

Parties are bound by agreements outlining assessment protocols for damages, and expert evaluations are needed to substantiate claims.

Subject

Civil Law - Writ Petition

Headnote

(1) The petitioners claimed damages for their properties allegedly affected by the construction activities of Kerala Water Authority, governed by Ext.P1 agreement mandating compensation based on expert assessments. (2) The court addressed claims regarding inadequate compensation, establishing liability based on expert reports and past inspections. The court upheld the validity of prior evaluations and findings relevant to damages. (3) The court concluded that the petitioners' claims were unsubstantiated, affirming the previous orders dismissing the writ petition.

Advocates:
For the Appellants/Petitioners: K.MOHANAKANNAN, A.R.PRAVITHA, H.PRAVEEN, D.S.THUSHARA
For the Respondents: SRI.GEORGE MATHEW, SC, KERALA WATER AUTHORITY, SHRI.P.BENJAMIN PAUL, SC, KERALA WATER AUTHORITY, SRI.JOSHY THANNICKAMATTOM, GOVERNMENT PLEADER, P.M.JOHNY

Table of Content
1. property owners allege damages due to water supply project. (Para 1 , 2)
2. court reviews prior settlements and expert assessments. (Para 3 , 4 , 5)
3. respondents contest claims citing oversight and expert conclusions. (Para 6 , 7)
4. court affirms the validity of government assessments. (Para 8 , 9 , 10)

JUDGMENT

The petitioners are owners of the properties, who alleged that their building had been damaged due to the unscientific use of machines and explosives for the purpose of laying pipes by the Kerala Water Authority (KWA). The petitioners had earlier filed OS No.5 of 2009 before the Munsiff Court, Perambra, during the pendency of which, Ext.P1 agreement was entered into between the petitioners and the Project Director, JBIC, Water Supply Project, KWA, agreeing that the damages caused to the building will be assessed by the District Collector through the expert authorities and as per such valuation market rates will be paid to them.

2. Petitioners allege that in violation of Ext.P1 agreement only the Assistant Executive Engineer of the Public Works Department inspected the premises and is stated to have made a valuation statement, according to which Exts.P2, P3, and P4 cheques amounting to Rs.44,942/-, 46,862/- and 60,611/- were issued. The petitioner says that the amount so granted was meagre and they ascertained the value by taking the services of a valuer who was also a consulting engineer, who gave Exts.P5 to P7 reports stating that 40% damage has been caused to the building of the first petitioner, 90% as far as the second petitioner and 60% as far as the third petitioner is concerned. The value of the houses the petitioners were assessed at Rs.60,00,000/-, Rs.1,00,000/- and Rs.15,00,000/-. The petitioners state that only less than 5% of the actual loss has been paid, and therefore they filed a representation, Ext.P8 to get an assessment by a competent committee.

3. WP(C)No.4305 of 2013 was also filed for a direction to the first respondent to pay amounts in terms of Ext.P1 and which is valued in Exts.P3 to P5 reports. This Court by Ext.P11 judgment, directed the 4th respondent to pass appropriate orders on the representations. Accordingly, Ext.P12 dated 31.01.2014 was passed, which accepted the report of the joint inspection conducted on 18.12.2013 by the Deputy Collector (LA), Assistant Executive Engineer, Sub Division, Koyilandi, and rejected the request of the petitioners to enhance the amount. Challenging Ext.P12, and with a prayer to pay the amounts in terms of Ext.P1 as valued in Exts.P3, P4, and P5, this writ petition is filed.

4. A counter affidavit has been filed on behalf of the third respondent stating that the State Government, in order to find a solution to the water scarcity of Kozhikode Corporation and 13 adjoining villages, had adopted a new scheme by the name Kerala Water Supply Project. Japan Bank for International Corporation (JICA) sanctioned a loan and the project was implemented in five contract packages. The project, estimated at a cost of Rs.804 crores was to be beneficial to 13 lakh people upto the year 2036. This project was implemented by the Kerala Water Authority and M/s.Tokyo Engineering Consultant Consortium Ltd., Japan (TECC), was the Design and Construction Supervision Consultant of the project. The area where the petitioners' properties are situated falls in one of the five packages, package II (II A & II B), covering the laying of the transmission main from Peruvannamuzhy to Kadalundi.

5. The allegation that the damages were caused to the properties of the petitioners due to the indiscriminate breaking of granite was denied. It is stated that the excavation works and laying of MS piles were carried out by the contractor M/s.L&T under the expert supervision of the consultant M/s. TECC. Controlled/protected blasting was done for the purpose of removing hard rocks found on the route for the purpose of creating 2.45 meters wide and 3.00 meter deep wide trenches for laying

1
2
3
4
5
6
7
8
9
10
11