SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Ker) 13364

2025 KER 36356
IN THE HIGH COURT OF KERALA AT ERNAKULAM
AMIT RAWAL, MURALEE KRISHNA S., JJ.
Kothamangalam Municipality - Appellant
Versus
P.P. Ajithkumar - Respondent
W.A. No. 520 of 2024
Decided On : 28-05-2025
Advocate Appeared : 
For the Appellants : D. Kishore, Joice George, Tom E. Jacob
For the Respondents : Deepu Lal Mohan, T.K. Vipindas

Advocates:
D.KISHORE, SHRI.JOICE GEORGE, SC, KOTHAMANGALAM MUNICIPALITY, TOM E. JACOB, DEEPU LAL MOHAN, SR.GOVERNMENT PLEADER SRI T K VIPINDAS

Emergency provisions under Section 15(4) of the Kerala Municipality Act allow a Chairperson to authorize urgent work without prior council approval, ensuring public safety.

Headnote:

(A) Kerala Municipality Act, 1994 - Section 15(4) - Writ appeal against judgment regarding payment for additional work - Contractor executed extra work under emergency powers granted by Chairperson - Municipality failed to approve actions taken, but contractor not penalized for this - Court held that emergency provisions allow for immediate action without prior council approval. (Paras 2, 3, 9, 10)

(B) Emergency Powers - Chairperson's discretion under Section 15(4) allows for urgent work execution without prior council approval, ensuring public safety. (Paras 8, 9)

Facts of the case:
The contractor was engaged for construction work but faced delays due to unforeseen circumstances, leading to additional excavation and blasting work authorized by the Chairperson. The Municipality later refused payment for this work.

Findings of Court:
The contractor is entitled to payment for additional work performed under the Chairperson's emergency authorization, and the Municipality must consider his representation for payment.

Issues: Whether the contractor is entitled to payment for additional work executed under emergency powers without prior council approval.

Ratio Decidendi: The court ruled that the contractor's actions were justified under the emergency provisions of the Municipality Act, and he should not be penalized for the Chairperson's failure to report to the council.

Result: Writ appeal disposed of with directions for the Municipality to consider the contractor's representation.

JUDGMENT :

MURALEE KRISHNA, J.

1. This is an appeal filed under Section 5(i) of the Kerala High Court Act, 1958, by respondents 1 and 2 in W.P. (C) No. 30648 of 2012 against the judgment of the learned Single Judge dated 29.02.2024 in the writ petition.

2. The 1st respondent herein is a PWD contractor, who successfully secured the construction work of the first Phase of ‘Kothamangalam Municipal Bus Stand’ from the 1st appellant Municipality, by quoting the lowest rate and subsequently by reducing it on negotiation. Accordingly, Ext.P1 agreement dated 09.03.2009 was entered into between the 1st respondent and the Municipality. According to the 1st respondent, the work could not be commenced immediately after the execution of Ext.P1 agreement due to reasons beyond his control. The initial work, such as the excavation of soil, was done under the supervision of the Assistant Engineer of the 1st appellant. At that time, it was found that against the total quantity of 660 M3 earth work excavation specified in the schedule to the agreement, around 13000 M of earth work excavation had to be done. Similarly, it was found that since hard rock was noticed beneath the soil, around 5000 M3 of rock blasting had to be done at the site. The Assistant Engineer reported this to the Municipal Engineer, who in turn reported the same to the 2nd appellant Secretary and subsequently, the matter was placed before the Chairperson of the 1st appellant Municipality. The then Chairperson of the 1st appellant Municipality granted sanction for carrying out earth work excavation of 13900 M3 and medium rock blasting of 1900 M3 by the 1st respondent as extra items by invoking the emergency power conferred on him under Section 15 (4) of the Kerala Municipality Act, 1994 (the ‘Municipality Act’ in short).

2.1. According to the 1st respondent, he immediately commenced the said additional works and carried on earth excavation of 12417 M3 and medium rock blasting of 1894 M3 at the site. Meanwhile, the Municipality entrusted the removal of hard rock from the site to third parties. At that juncture, the Department of Mining and Geology directed the Municipality to stop the quarrying work and to remit an amount of Rs.21,000/- towards royalty and fine for the granite quarried. In spite of repeated requests by the 1st respondent, the Municipality did not take any steps to recommence the work. Meanwhile, the contract period for completion of the work expired on 09.03.2010. Though the 1st respondent submitted Ext.P7 request, dated 07.07.2011 to the 2nd appellant to take appropriate steps for re-commencing the work after extending the period of contract or to relieve him of the subject work after paying the amount due to him, no response was followed. Hence, the 1st respondent approached this Court by filing W.P. (C) No. 29403 of 2011, which was disposed of by Ext.P8 judgement dated 11.11.2011, directing the 2nd appellant to consider and pass orders on Ext.P7 request within a time frame. Thereafter, as per Ext.P13 resolution dated 13.09.2012 of the Municipal Council, the 1st respondent was decided to be relieved from the work. It was further resolved by the Council not to grant payment to the 1st respondent for execution of the aforesaid two extra items of work and also resolved to recover from him the cost of earth that was removed from the site. Hence, the 1st respondent filed the writ petition seeking the following reliefs:

“(i) To issue of Writ of Certiorari or other appropriate writ, order or direction calling for the records leading to Ext.P13 and quash the same to the extent it resolves not to grant payment to the Petitioner for the execution of the two extra items of work in question and also to recover from the Petitioner the cost of the earth that was removed from the site at 2007 schedule of rates.

(ii) To declare that since the Petitioner has executed the two extra items of work in question on the basis of the sanction granted by the Chairperson of the 1st Responde

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top