2024 Supreme(Online)(KER) 39679

IN THE HIGH COURT OF KERALA AT ERNAKULAM


PRESENT


THE HONOURABLE MR.JUSTICE V.G.ARUN


MONDAY, THE 28TH DAY OF OCTOBER 2024 / 6TH KARTHIKA, 1946


WP(C) NO. 34070 OF 2024


PETITIONER:


M/S CHICAGO CONSTRUCTIONS INTERNATIONAL PRIVATE LIMITED


REPRESENTED BY ITS MANAGING DIRECTOR, S.MOHANA KUMAR,


AGED 60 YEARS, SON OF SADASIVAN, HAVING ITS REGISTERED


OFFICE AT TC 22/2703, CHITIRA LANE, KOCHAR ROAD,


SASTHAMANGALAM, THIRUVANANTHAPURAM, PIN - 695010


BY ADVS.


N.KRISHNA PRASAD


P.SHANES METHAR


A.MOHAMMED FAIZAL


ARJUN P.V.


HARKISH SREETHU V.S.


PUSHPARAJ.K.P


RESPONDENTS:


1 KERALA WATER AUTHORITY


REP. BY ITS MANAGING DIRECTOR, JALA BHAVAN,


VELLAYAMBALAM, THIRUVANTHAPURAM, PIN - 695033


2 THE CHIEF ENGINEER (SOUTHERN REGION)


KERALA WATER AUTHORITY, JALA BHAVAN, VELLAYAMBALAM,


THIRUVANTHAPURAM, PIN - 695033


3 THE SUPERINTENDING ENGINEER


OFFICE OF THE SUPERINTENDING ENGINEER, P.H. CIRCLE,


KERALA WATER AUTHORITY, OBSERVATORY HILLS,


THIRUVANANTHAPURAM., PIN - 695033


4 THE EXECUTIVE ENGINEER


OFFICE OF THE EXECUTIVE ENGINEER, WATER SUPPLY


DIVISION, KERALA WATER AUTHORITY, VISWABHARATHY ROAD,


ALUNMOODU, NEYYATINKARA, THIRUVANANTHAPURAM, PIN - 695121


SRI .V.V. JOSHY SC FOR KWA.


THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 28.10.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:


Sd/-


V.G.ARUN


JUDGE


SSK/28/10


APPENDIX OF WP(C) 34070/2024


PETITIONER EXHIBITS


Exhibit P1 TRUE COPY OF THE RELEVANT EXTRACT OF THE NOTICE INVITING TENDER (VOLUME NO.1 AND VOLUME MO.2) WITH DUE DATE 10.1.2022


Exhibit P2 TRUE COPY OF THE SELECTION NOTICE ISSUED BY THE 3RD RESPONDENT DATED 11.3.2022


Exhibit P3 TRUE COPY OF THE ACCEPTED SCHEDULE ISSUED BY THE 3RD RESPONDENT


Exhibit P4 TRUE COPY OF THE AGREEMENT NO.34/2021-22 DATED 23.3.2022 WITH THE 2ND RESPONDENT.


Exhibit P5 TRUE COPY OF THE CC 8TH AND PART BILL ALONG WITH THE CALCULATION PARTICULARS


TRUE COPY


P.A. TO JUDGE

JUDGMENT

Dated this the 28th day of October, 2024

The petitioner, an A class Contractor under the Kerala Water Authority, has been entrusted with the work "Jal Jeevan Mission-2023-24 Thiruvananthapuram District-Kottukal Grama Panchayath-Supplying Laying, Testing & Commissioning of pipe line extension and providing Functional house hold tap connections". During the course of such work, the petitioner had to carry out excess items of work, for which the petitioner has requested to prepare a revised estimate. The petitioner's 8th part bill is pending payment and the prayer in this writ petition is to direct the respondents to complete preparation of the revised estimate in respect of the excess quantities and extra items as reflected in Exhibit P5 calculation, so as to facilitate payment along with the amounts due to the petitioner as per Exhibit P5 part bill.

2. Learned counsel for the petitioner submitted that the delay in preparation of the revised estimate will result in the petitioner losing his seniority with respect to payment of bills and the practice of the Water Authority is to prepare the revised estimate only after the entire work is over. It is contended that as per Clause 1601.1.6 of the PWD Manual, a revised estimate is to be prepared immediately after completion of the extra item of work.

3. Learned Standing Counsel for the Water Authority submits that the process of preparation of revised estimate will take some time and the petitioner cannot insist that the revised estimate should be prepared and included for payment along with the pending bills.

4. Having heard the learned Counsel on either side, this Court is of the opinion that, any undue delay in preparation of the revised estimate would have an adverse impact on the petitioner's seniority and runs contrary to the mandate of Clause 1601.1.6 of the PWD Manual.The writ petition is hence disposed of, directing respondents 2 to 4 to prepare the revised estimate with respect to the subject work within three months of receipt of a copy of this judgment.