2024 Supreme(Online)(KER) 31290

HIGH COURT OF KERALA
VIJU ABRAHAM, J
SRI. SHYLESAN T.S – Appellant
Versus
KERALA STATE POLLUTION CONTROL BOARD DISTRICT OFFICE, KOTTAYAM – Respondent
WP(C) 42572/2023



Pending legal proceedings do not preclude the renewal of quarrying consents unless an injunction is in place.

Headnote:

Quarrying - Renewing Consent - National Green Tribunal - Ext.P8 - The court held the pending proceedings before the National Green Tribunal do not bar the renewal of consent unless there's an injunctive order; set aside the rejection of renewal and mandated reconsideration in line with legal guidelines.

Fact of the Case:

The petitioner challenged the rejection of his quarrying consent renewal application by the first respondent, citing absence of injunctive orders from the National Green Tribunal despite ongoing proceedings regarding alleged violations of quarrying norms.

Issues: Whether the ongoing proceedings before the National Green Tribunal prevent the first respondent from renewing the petitioner’s quarrying consent application.

Ratio Decidendi: The court decided that pending proceedings do not automatically impede the renewal of consents unless there is a specific order restraining the authority from doing so.

Final Decision: The court set aside Ext.P8 and ordered reconsideration of the renewal application within one month.

JUDGEMENT

Petitioner has approached this Court challenging Ext.P8.

2. It is averred that the petitioner is a grantee of Ext.P1 quarrying lease with respect to an extent of 3.4260 hectares of land comprised in block no. 25, in re-survey nos.48/1(pt) and 48/2(pt), in Erumely North Village, Kanjirappally Taluk, Kottayam District. Petitioner submits that he is conducting quarrying operation after obtaining necessary clearance/consent/license from the other statutory authorities concerned, copies of which are produced as Exts.P2 and P4 to P6. By Ext.P7 petitioner has submitted an application for renewal of consent to operate before the 1st respondent and requisite fee was also paid as evident from Ext.P7(a). Thereafter petitioner has approached this Court filing W.P.(C) No.28218 of 2023 wherein Ext.P3 interim order was passed directing the respondents to consider the application by referring to the notification issued by the MoEF. But the said application has now been rejected by Ext.P8 stating that the application cannot be considered since O.A.No.44 of 2023 is pending before the National Green Tribunal, Principal Bench, New Delhi and that the application will be considered only after the final disposal of the Original Application by the Tribunal. It is contended by the petitioner that at the time of filing of the writ petition he has not been served with any copy of the proceedings before the National Green Tribunal pending as O.A.No.44 of 2023. Petitioner submits that since no interim orders have been passed by the Tribunal restraining the 1st respondent from renewing the consent to operate the quarry or restraining the petitioner from continuing with the quarrying operations, the stand taken by the 1st respondent in Ext.P8 is absolutely arbitrary and unjust.

3. The 2nd respondent entered appearance through counsel and filed a detailed counter affidavit mainly contending that the petitioner has conducted extensive quarrying operation without complying with the prescribed norms and guidelines and that the petitioner has extracted more quantity of mineral than what is permitted as per the quarrying lease issued to him. It is in the said circumstances that the 2nd respondent has approached the National Green Tribunal filing O.A.No.44 of 2023 and the Tribunal by Ext.R2C order dated 03.03.2023 constitute a committee to visit the premises to collect relevant information and submit a factual as well as action taken report. The 2nd respondent submits that pending consideration of the proceedings before the National Green Tribunal the application submitted by the petitioner for renewal of NOC cannot be considered. An additional counter affidavit has also been filed by the 2nd respondent stating various instances of violation committed by the petitioner which was tabulated as follows:

    It is further submitted that the petitioner was impleaded in the proceedings before the National Green Tribunal and has filed an application challenging the maintainability of the complaint.
DATEPARTICULARSPAYMENT
25/11/2020Royalty, Price and Fine for illegal extraction and removal of 43 MT of GBSRs.28,096/-/-
06/05/2022Royalty, Price and Fine for illegal extraction and removal of 52171 MTRs.38,56,312/-
18/05/2022Royalty, Price and Fine for illegal extraction and removal of 940 M3 [332 MT] of GBSRs.1,94,200/-
30/05/2023Royalty, Price and Fine for illegal extraction and removal of 108793 + 378272.9 MT of GBS [487065.9 MT]Rs.2,99,46,681/-
Total539569 MT [1527889.25 M3]

4. Learned counsel for the petitioner has filed a detailed reply to the counter affidavit preferred by the 2nd respondent wherein a contention was taken that the attempt of the 2nd respondent is only a blackmailing and pressure tactics for forcing the petitioner to purchase her ancestral home. Relying on Exts.P11 and P12 whatapp chats the petitioner would contend that he was even threatened that complaints will be filed and the account details of the 2nd respondent was also forwarded. To which the 2nd res