2024 Supreme(Online)(KER) 2651

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE MR. JUSTICE RAJA VIJAYARAGHAVAN V TH TUESDAY, THE 27 DAY OF FEBRUARY 2024 / 8TH PHALGUNA, 1945 WP(C) NO. 43990 OF 2023 PETITIONER:

M/S. SHIVALAYA CONSTRUCTION COMPANY PVT LTD PLOT NO. 137, AVATAR ENCLAVE, PASCHIM VIHAR, NEW DELHI, HAVING BRANCH OFFICE HOUSE NO. 488, MAPPLE HOMES, THRIPRAYAR, KIZHAKKENADA, PERINJGOTTUKARA P.O, EDATHURUTHY, THRISSUR REPRESENTED BY ITS LAISON OFFICER, CHANDRAMOHAN, AGED 43 YEARS, S/O CHINAYA, KULATHOOPPUZHA, KOLLAM, PIN - 680565 BY ADV MANOJ P.KUNJACHAN RESPONDENTS:

1 THE DISTRICT POLICE CHIEF OFFICE OF THE DISTRICT POLICE CHIEF, PALAKKAD, PIN - 678001

2 STATION HOUSE OFFICER CHALISSERY POLICE STATION, PALAKKAD DISTRICT, PIN - 679536

3 GEOLOGIST DEPARTMENT OF MINING AND GEOLOGY, SULTANPETU, PALAKKAD DISTRICT, PIN - 678001

4 NATIONAL HIGHWAY AUTHORITY OF INDIA MINISTRY OF ROAD TRANSPORT AND HIGHWAYS, G 5&6, SECTOR 10, DWARAKA, NEW DELHI 110075 REPRESENTED BY THE PROJECT DIRECTOR, NHAI, VII/511B, NEITHELI-MAVELIPURAM ROAD, KAKKANAD, KERALA, PIN - 682030

5 RAHEED THANGAL S/O KUNJIKOYA, MANATHPARAMBIL HOUSE, CHATHANNOOR P O, PERINGODE VIA, PALAKKAD DISTRICT, PIN - 675535

6 SULAIMAN K P S/O SIDHI, KOCHUPARAMBIL HOUSE, CHAZHIYATTIRI P O, PERINGODE, PALAKKAD, PIN - 679535

7 MANIKANDAN L V FATHERS NAME NOT KNOWN, KOZHIKKUNNU COLONY, THICHUR P O, THRISSUR DISTRICT, PIN - 680585 BY ADV. BABU S. NAIR SRI P. M. SHAMEER, GP, SRI B. G. BIDAN CHANDRAN, SC FOR NATIONAL HIGHWAY AUTHORITY OF INDIA THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON

27.02.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

JUDGMENT

M/s. Shivalaya Construction Company Limited has been granted the contract to undertake 6 laning works of the National Highway from Talikkulam to Kodungallur Section on Hybrid Annuity mode under Bharathmala Pariyojana. According to the petitioner, in order to carry out the work as ordered under Ext.P1, they require a large quantity of red earth. To satiate the demand for earth for filling, they approached the 3rd respondent and secured Exts.P2 and P3 permits for the extraction of red earth. It is submitted that to ensure that no damage is caused to the road, the petitioner has submitted Ext.P4 undertaking as well. They contend that when the work was started, the party respondents, along with certain others, obstructed the construction work. Aggrieved by the same, repeated representations were submitted before respondents 1 and 2. The grievance of the petitioner is that no action has been taken yet. It is on these assertions that this writ petition is filed seeking the following reliefs:-

“i. To issue a writ of mandamus or any other appropriate writ, order or direction directing the respondents 1&2 to alford effective, timely and meaningful police protection to the petitioner, his workers, machinery and vehicles using for extraction of ordinary earth and construction activity from the 99.99 ares in Sy.No. 275/lA3-30 of Thirumittakkode II village of Pattambi Taluk of Palakkad District.as against respondents 5 to 7 and their henchmen.

ii. To declare that respondents 5 to 7 and their henchmen have no right or authority to cause obstructions and hindrances while extracting the ordinary earth from the property mentioned in Ext, P2 and Ext. P3.”

2. A counter affidavit has been submitted by respondents 5, 6, and 7, alleging that the petitioner has been engaging in the extraction of ordinary earth in contravention of previously granted permits. They assert that the petitioner has excavated a significant quantity of earth exceeding the permitted limit, further alleging that this excess earth is being transported, causing damage to the road infrastructure. Citing photographic evidence in Ext.R5(a) series, the respondents contend that continued excavation poses an imminent risk of landslides in the area. Additionally, it is stated that the Secretary of the Grama Panchayat has formally requested the geologist to inspect the property and take necessary action in response to the observed violations. Moreover, it is highlighted that the petitioner, purportedly acting under the interim order issued by this Court, continues to remove large quantities of earth unabated. Furthermore, the respondents state that a criminal case has been registered at Thalassery Police Station as Crime No. 952/2023, and investigations are underway.

3. A reply affidavit is filed by the petitioner, denying the contentions raised in the counter affidavit. It is stated that based on the complaint, the Geologist had blocked the portal for e-pass and had visited the site. It is further stated that the Geologist had, after inspecting the site, found out that the petitioner was acting in strict compliance with the directions and had cleared the portal for e-pass. It is further stated that the petitioner has already submitted Ext.P4 undertaking before the Panchyat that he shall repair the road if any damage is caused. Finally, it is stated that the contract that has been granted is time-bound, and if any delay is caused, it would result in a huge loss to the State as well.

4. The learned Government Pleader submits that initially, two permits were given to the petitioner. On receipt of complaints, an inquiry was conducted, and it was decided to carry out a Geo Physical study. It is stated that only after conducting the study can it be determined whether the petitioner is removing excess earth or not. It is further submitted that the Geologist has inspected the site and found that the petitioner is acting strictly in accordance with the permits issued.

5. I have heard Sri. M

1
2
3
4
5
6
7
8
9
10
11