IN THE HIGH COURT OF KERALA AT ERNAKULAM
ABDUL NASIR C.I. – Appellant
Versus
MR. PUNIL KUMAR – Respondent
Con.Case(C) 2031/2023



IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE MR.JUSTICE ANIL K. NARENDRAN &

THE HONOURABLE MRS.JUSTICE SOPHY THOMAS TH THURSDAY, THE 14 DAY OF SEPTEMBER 2023 / 23TH BHADRA, 1945 CON.CASE(C)NO.2031 OF 2023 FOR NON-COMPLIANCE OF THE JUDGMENT DATED 10.10.2022 IN W.P.(C)NO.31851 OF 2022 OF THE HIGH COURT OF KERALA PETITIONERS/PETITIONERS 1 AND 3:

1 ABDUL NASIR C.I., AGED 50 YEARS, S/O. IQBAL, NASEEMA MANZIL, CHALAKUNNU, VIDHYANAGAR P.O., KASARAGOD, PIN - 671123

2 NAMSHAD K.M., AGED 51 YEARS, S/O. LATE K.S.

MUHAMMED, MAK ASAD ROAD, NAINMARMOOLA, P.O.

VIDHYANAGAR, KASARAGOD DISTRICT, PIN - 671123 BY ADV K.K.MOHAMED RAVUF RESPONDENT/RESPONDENT:

MR. PUNIL KUMAR,(AGE AND FATHER’S NAME NOT KNOWN TO THE PETITIONERS) PROJECT DIRECTOR, NATIONAL HIGHWAY AUTHORITY OF INDIA, PROJECT IMPLEMENTATION UNIT, BUILDING NO. 46/3460, ’ZAHIRA’, NEAR DINESH AUDITORIUM, KANNUR, PIN -

670002 OTHER PRESENT:

SRI. MATHEW K. PHILIP, S.C., NHAI SMT. RASMI K.M., SR. G.P.

THIS CONTEMPT OF COURT CASE (CIVIL) HAVING COME UP FOR ADMISSION ON 14.09.2023, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:

JUDGMENT

Anil K. Narendran, J.

Petitioners 1 and 3 along with another have approached this Court in W.P.(C)No.31851 of 2022, seeking a writ of mandamus commanding the respondent, namely, the Project Director, National Highway Authority of India, Project Implementation Unit, Kannur to install traffic signals and lights on the National Highway- 66 at Nainmarmoola Junction for the smooth flow of vehicles through that junction. The petitioners have also sought for a writ of mandamus commanding the respondent to consider and pass orders on their representation dated 03.09.2022 (Ext.P2)

forthwith.

2. W.P.(C)No.31851 of 2022 was disposed of by Annexure

2 judgment dated 10.10.2022, whereby, the respondent was directed to consider and pass orders on the said representation dated 03.09.2022, if it was pending on the file, in accordance with law, within a period of six weeks from the date of receipt of a copy of that judgment. In the said judgment it was made clear that, if a personal hearing is required, it is left to the discretion of the respondent.

3. Now, the petitioners are before this Court in this Contempt case, invoking the provisions under Section 12 of the Contempt of Courts Act, 1971 and Article 215 of the Constitution of India, alleging willful disobedience of the directions contained in Annexure 2 judgment, by the respondent Project Director, who has issued Annexure A3 communication dated 23.11.2022 on the request made by the petitioners in their representation dated 03.09.2022. The stand taken in Annexure 3 has been reiterated in Annexure 5 communication dated 07.01.2023 issued by the respondent, in reply to Annexure 4 representation dated

19.12.2022 made by the 1st petitioner.

4. Annexure 3 communication dated 23.11.2022 of the respondent reads thus;

“It is intimated that, during construction of the project, the Traffic Diversion Plan and traffic signage arrangements shall be made by the concessionaire as per IRC:SP:55-2014 Traffic Management in Work Zones.

After construction of the project, the traffic signage and Road appurtenances as per IRC:67-2012 (Code and Practice for Road Signs) shall be installed by the concessionaire after getting the approval of Safety Consultant, NHAI and Road Safety Expert of Independent Engineer.”

5. Annexure 5 communication dated 07.01.2023 of the respondent reads thus;

“Regarding your request for the installation traffic signal, we have already informed the status after technical scrutiny vide our letter No.11115/NHAI/PIU-Kannur/2022/1091 dated

23.11.2022.

However, with reference to your remaining points, an underpass of 7mx3m is considered at KM53+440, Naimarmoola in change of scope which is under process and hope the same will suffice the requirements.”

6. Heard Sri. Mohamed Ravuf K.K., the learned counsel for the petitioners and Sri. Mathews K. Philip, the learned Standing Counsel for National Highway Authority of India.

7. The lear

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top