SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Online)(KER) 30355

HIGH COURT OF KERALA
M.R.ANITHA, J
M/S. SHWAS HOMES PRIVATE LTD., REPRESENTED BY MANAGING DIRECTOR MR.SREENI PARAMESWARAN – Appellant
Versus
M/S. MOON WATERS OWNERS ASSOCIATION REPRESENTED BY ITS SECRETARY MR.MADHAVAN UNNI – Respondent
MSA 4 2023



Advocates:
S.S.ARAVIND, P.B.KRISHNAN, SREEVALSAKRISHNAN P K, R. LEKSHMI NARAYANAN

Suo moto proceedings by K-RERA regarding project registration are permissible under the Act; prior orders do not constitute a barrier to reconsideration based on new evidence.

Headnote:

Real Estate - Project Registration - [Real Estate (Regulation and Development) Act, 2016] - Sections [3, 4(2)(c), 34, 35, 36, 37] - The court interpreted the provisions to conclude that the authority has the discretion to initiate suo moto proceedings regarding project registration, emphasizing that prior orders do not preclude reconsideration unless new facts emerge. It affirmed the findings of registrability for the project based on compliance with designated legal frameworks.

Fact of the Case:

The case involves appeals against a judgment regarding the registration status of the Aqua City real estate project under the Real Estate (Regulation and Development) Act. The Kerala Real Estate Regulatory Authority (K-RERA) had issued interim and final orders on the project's registrability, which were contested by the promoters based on prior occupancy and completion certifications.

Finding of the Court:

The court found that K-RERA correctly initialed suo moto proceedings for project registration and that its interim orders merged with later final orders. The earlier order from K-RERA could not prohibit consideration of the project's status given evolving circumstances.

Issues: The main issues revolve around K-RERA's authority to initiate suo moto registration proceedings, the impact of earlier orders on registrability decisions, and whether sufficient grounds existed to substantiate project registration compliance.

Ratio Decidendi: The court held that previous K-RERA orders do not limit the authority's ability to reconsider project registration, especially when new or additional evidence is brought forth, subject to discretion under the respective sections of the Act.

Final Decision: The appeals are allowed, setting aside the Tribunal's annulment of K-RERA's order and directing fresh consideration of the case.

JUDGMENT

Dated this the 29th day of May, 2023 The above MSAs were filed against the common judgment in REFA Nos.17, 18, 27 & 30 of 2022 of the Kerala State Real Estate Appellate Tribunal, Ernakulam.

2. Heard both sides.

3. M.S.A. No.1/2023 admitted on the following substantial questions of law:

(a) Whether section 3 the Real Estate regulation and Development Act, 2016 contemplates registration when the completion of the project and issue of occupancy certificate under the relevant local law with reference to a period long before the Act?

(b) Whether standalone project means and has to be reckoned along with the sanction plan, lay out, agreement of construction advertisement of the project?

(c) Whether the certification of occupancy issued by the statutory authority can be brushed aside and ignored and required to be that complying with the Real Estate regulation and Development Act, 2016?

(d) Whether registration of the project can be directed when sanction plan, layout plan etc has expired and no declaration as contemplated under Section 4 (2)(i) could be obtained for want no new constructions being commenced or advertised and when already substantial units have been sold out years back?

(e) Whether an inquiry under section 35 is mandatory before considering and adjudicating the question as to whether a project is ongoing or not for the purpose of registration? (f) Whether interim order survives and is binding for other proceedings before the same forum in the same subject matter, when final order is pronounced?

(g) Is the finding that the whole Acquacity township project is registrable under section 3 the Real Estate regulation and Development Act, 2016 is correct?

4. M.S.A. Nos.4 & 6 of 2023 admitted on the following substantial questions of law:

1. Whether order dated 28.04.2021 preclude K-RERA from reconsidering the question of registration of the project in the final stage?

2. Whether there is any illegality in initiating suo moto proceedings by K-RERA regarding the registration of the project, after the proceedings initiated against the appellant/promoter in the complaints and passing of order dated 28.04.2021?

5. When the appeals came up for hearing, the learned counsel for the appellants would submit that MSA Nos.4 & 6 of 2023 arouse out of the suo moto proceedings initiated by the Kerala Real Estate Regulatory Authority (in short ‘K-RERA’). While disposing the common judgment in REFA Nos.17, 18, 27 & 30 of 2022 of the Kerala Real Estate Appellate Tribunal (in short ‘the Tribunal’) found that K- RERA has no power to review its earlier order dated 28.04.2021 and hence, the suo moto order dated 21.12.2021 is without authority and is non-est in the eye of law and it has no legal effect or consequence. Hence, no argument was advanced in MSA Nos.4 & 6 of 2023 which in turn arouse out of the order in REFA Nos.17/2022 and

18/2022.

6. In REFA No.27/2022 appellants are the promoters and the respondents 1 & 2 are the associations in a tower by name Moon Waters Association and Aqua City Palm Bay Villas Owners Residence Association and respondent Nos.3 and 4 are two allotees in Moon Waters in the township called ‘Aqua City’. Three complaints 115, 116, 117 of 2020 were filed seeking registration of Aqua City township project comprising ten apartment towers and 68 Villas and other reliefs before K-RERA. K-RERA passed two interim orders issuing show cause notices to the promoters for not registering the projects on 07.11.2020 and 30.11.2020 respectively. Against which W.P.(C) No.27217/2020 was filed and this Court directed K-RERA to consider the question of maintainability of complaints and competency of complainants on hearing both sides. Thereafter, an interim order was passed on 28.04.2021 to the effect that the entire project is registrable under Section 3 of the Real Estate (Regulation and development) Act, 2016 (in short ‘the Act’). The question of maintainability was found in favour of the respondents. Against which the appellants filed

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top