SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Online)(Ker) 77983

IN THE HIGH COURT OF KERALA AT ERNAKULAM
P.V.KUNHIKRISHNAN, J
KAIKKARA CONSTRUCTION COMPANY – Appellant
Versus
STATE OF KERALA – Respondent
WP(C) NO. 31363 OF 2009 | WP(C) NO. 4856 OF 2019



Advocates:
For the Appellants/Petitioners: SRI.K.BABU THOMAS, SMT.MARYKUTTY BABU
For the Respondents: STATE ATTORNEY SRI.K.V.SOHAN, STATE ATTORNEY SRI.K.V.MANOJ KUMAR, SR.GP

A claim for unliquidated damages does not create a debt until the liability is established through judicial adjudication, and one party cannot unilaterally determine breach or damage without agreement from the other.

Headnote:(A) Breach of Contract - Principles of unilateral assessment of damages - State's right to recover damages from contractors cannot be assessed unilaterally when there is a dispute. The court emphasized the necessity of independent adjudication for disputes about breach of contract (Paragraphs 7-27).

(B) Writ Jurisdiction - This court will exercise jurisdiction to prevent unilateral actions void of due process.

(C) Damage Assessment - Claim for unliquidated damages does not give rise to a pecuniary obligation until adjudicated and assessed by a court or authority (Paragraphs 11-12).

Facts of the case:
The petitioner was engaged in constructing a Fisheries Harbour and contested unilateral damage claims imposed by the State without adjudication. The petitioner sought quashing of decisions imposing fines and termination of the contract for delays purportedly caused by the State’s actions.

Findings of Court:
The court ruled the State's unilateral decisions were invalid as they violated principles established in previous case law asserting that both breaches and damages must be established through proper judicial processes.

Issues: The principal issue revolved around the validity of unilateral assessments of damages by the State in the face of contractual disputes.

Ratio Decidendi: The court articulated that the State, like any contracting party, cannot determine damages unilaterally when such determination is contested by the other party; it must seek judicial resolution.

Result: Writ petition allowed; unilateral damage claims and related orders quashed.

Table of Content
1. state contract obligations and damages. (Para 1 , 2 , 3)
2. court's view on adjudication necessity. (Para 9 , 10 , 11)
3. unilateral damage assessment principles. (Para 18 , 19 , 20)
4. writ petitions' outcomes and legal redress. (Para 22 , 27)

COMMON JUDGMENT

It is a settled position that the unliquidated damages do not give rise to debt especially when the same is disputed until the liability is adjudicated and damages assessed by a decree or order of a court or by any other adjudicatory authority. One party to a contract cannot unilaterally assess the damages. But in these cases, the state challenges this proposition based on certain decisions of the apex court. Since these two writ petitions are connected, I am disposing of these two writ petitions by a common judgment. I will first narrate the facts in WP(C) No.31363 of 2009.

2. The petitioner was awarded the construction work of break waters in connection with the Ponnani Fisheries Harbour Project of the State Government. As per the terms of the agreement entered into by the petitioner with the Government in connection with the execution of work referred above, the petitioner ought to have completed the work on or before 31.3.2007. The case of the petitioner is that due to various reasons attributable exclusively to the respondents, the work could not be completed in full within the time stipulated. For completing the remaining part of the work, a minimum period of seven months further was required at that point of time. Hence, the petitioner on 7.2.2007 submitted an application for an extension of time. It is the case of the petitioner that since the reason for non-completion of the work was not attributable to the petitioner, the Harbour Engineering Department under which the work was executed recommended to the Government that time sought for by the petitioner can be granted. Consequently, based on Ext P1 Government Order,the Government allowed the request for extension of time but imposed a fine @ Rs.21,956/- per day for completion of the remaining part of the work. It is the case of the petitioner that the fine imposed by the Government as per Ext P1 order was approximately 1 crore and the same was even far above the anticipated profit of the petitioner. Hence, the petitioner again approached the Government to modify Ext P1 order and to permit them to complete the work without a fine. Subsequently, Ext P2 Government Order was passed based on the direction in Ext P3 judgment of this court.

3. Thereafter, it is the case of the petitioner that the 1st respondent illegally directed to terminate the contract by Ext P2 order. The termination of the contract effected by the 2nd respondent on 29.4.2005 at the risk and cost denying unconditional extension of time sought from 1.4.2007 to 31.12.2007. The respondents issued a notice inviting tenders for the balance work. Pursuant to Ext P3 judgment, the Government conducted a hearing on the issue of termination of the contract and in the course of the hearing, the petitioner contended that they had not committed any breach of the terms of the contract. It is the case of the petitioner that without considering the contentions of the petitioner, the Government restored its earlier decision as per Ext P4. Since a substantial amount is due to the petitioner, the petitioner decided to file a suit, and a Section 80 Civil Procedure Code notice was issued as evident by Ext P5. The Government sends a reply as per Ext P6. Thereafter, the petitioner was taking steps to file the suit. At that stage, the petitioner received Ext P7 notice from the 4th respondent stating that the petitioner is liable to pay a sum of Rs.4,34,12,105/- to the Government in connection with the rearranging of the work referred to above and directing them to pay the same to the Government. The petitioner sent Ext P8 reply. In Ext P8, the petitioner also stated that Government cannot determine the issue as to who has committed the breach of the terms of

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top