IN THE HIGH COURT OF KERALA AT ERNAKULAM
ZIYAD RAHMAN A.A.TH, J
MARYMATHA INFRASTRUCTURE PVT. LTD – Appellant
Versus
THE STATE OF KERALA – Respondent
| Table of Content |
|---|
| 1. petitioner challenges applicability of a government order on contract. (Para 1 , 2 , 3) |
| 2. respondents assert variations in agreement alter pre-existing rates. (Para 4 , 6 , 7 , 8) |
| 3. court notes non-retrospective nature of government order paramount to litigated issue. (Para 9 , 10 , 11) |
| 4. court directs representation to government for reconsideration based on findings. (Para 12) |
JUDGMENT
This writ petition is submitted by a works contractor, who was entrusted with the work of “Construction of Hospital Block Buildings in Government Medical College, Palakkad” and Ext.P2 is the agreement executed in this regard, between the petitioner and the respondents 2 and 3 on 30.01.2017. Exhibits P3, P3(A) and P3(B) are the supplemental agreements executed between the petitioner and the said respondents, on 7.1.2021, 12.8.2022 and 28.1.2023 respectively.
2. The grievance highlighted by the petitioner in this writ petition pertains to the fixation of the rate for the works, in respect of additional works carried out by the petitioner based on Ext.P3 series supplemental agreements. According to the petitioner, the rates for such additional works and the supplies made, were reckoned
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.