2025 Supreme(Online)(Ker) 52788
IN THE HIGH COURT OF KERALA AT ERNAKULAM
K. NATARAJAN, J
PREMALATHA – Appellant
Versus
MAHEEN – Respondent
OP(C) NO. 2355 OF 2025 | OP(C) 2357/2025
Important Points
Subject
Civil Law - Appellate Procedure
Headnote
(C) NO. 2355 OF 2025 and OP
(C) 2357/2025, where the petitioner seeks directions for a timely resolution of pending appeals AS No.15/2019 and AS No.18/2019. The court acknowledges the request for an extension from the Sub Court and mandates a three-month timeframe for resolution. Both petitions are thus disposed with directions to the Sub Court to comply accordingly.
Result: The Sub Court is directed to dispose of the appeals within 3 months.
For the Appellants/Petitioners: SRI.G.P.SHINOD, SRI.GOVIND PADMANAABHAN, SHRI.AJIT G ANJARLEKAR, SHRI.ATUL MATHEWS, SMT.GAYATHRI S.B.
For the Respondents: Not specified
| Table of Content |
|---|
| 1. filing for expediting the case (Para 1 , 2) |
| 2. judicial instruction for timely resolution (Para 3) |
COMMON JUDGMENT
(Dated this the 14th day of November, 2025)
Both these petitions are filed by the petitioner/1st respondent for issuing direction to the Sub Court, Nedumangad to dispose of the appeals, AS No.15/2019 and AS No.18/2019 in a time bound manner.
2. A report has been received from the concerned court and the concerned court requested 3 months time to dispose of the appeals.
3. Considering the facts and circumstances of the case and the report of the concerned court, it is necessary to issue direction to the court concerned.
Accordingly, both original petitions are disposed of with a direction to the Sub Court, Nedumangad to dispose of the appeals, AS No.15/2019 and AS No.18/2019 within 3 months from the date of receipt of copy of the judgment.