SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1994 Supreme(Online)(Ker) 175

KERALA HIGH COURT
Not Mentioned, Not Mentioned
Regional Science Centre v. Varghese K. Pulayath And Co.
O.S. No. 910 of 1992 | I.A. No. 5930 of 1992 | C.M.A.



A bank guarantee is an independent contract, and courts will not interfere with its execution unless there are exceptional circumstances such as fraud or irretrievable injustice.

Headnote:(A) Bank Guarantees - Principles governing their invocation - The court held that an injunction restraining performance of a bank guarantee is only permissible in exceptional circumstances such as fraud or irretrievable injustice - Citing established cases such as United Commercial Bank v. Bank of India and R.D. Harbottle v. National Westminster Bank Ltd. - The court emphasized the independent nature of bank guarantees, underlining that they should not be interfered with lightly. (Paras 10, 14, 15, 44, 46)

(B) Injunctions - Grant of - The court ruled that the basis for granting an injunction must show a prima facie case of irretrievable injustice, which was not evident in this case - Noting the lack of sufficient justification for the court's earlier ruling on injunction. (Paras 8, 16, 46)

(C) Legal Obligations of Banks - A bank's duty under a bank guarantee is absolute in nature - Determining factors include strict compliance with the terms of the guarantee without reference to the underlying contract or disputes therein. (Paras 19, 25, 41)

1. Defendants 2 and 3 are the appellants. The suit was one for injunction restraining the first defendant from encashing or parting with any amount under Bank Guarantee Nos. 31/30 dated 9-1-1991 and 31/23 dated 20-10-1990 furnished to the second and third defendants pursuant to the demand of the third defendant in his letter dated 2-11-1992 and for an order of injunction restraining the second and third defendants and their officers from pressing the demand for encashing the Bank guarantees or recovering any loss without a fiat from a competent court. Plaintiff filed I. A. No. 5930 of 1992 for an order of temporary injunction restraining the first defendant - Bank from parting with any amount under Bank Guarantee Nos. 31/30 dated 9-1-1991 and 31/23 dated 20-10-1990 issued by the first defendant, to the third defendant, pending disposal of the suit. In this I.A. defendants 2 and 3 were parties. The Court below passed an ad interim order of temporary "injunction against encashing BG" (Bank Guarantee) and also ordered "Inj. & Notice".

2. This order of interim injunction was made absolute by the impugned order in this appeal. Now, facts:

3. For the purpose of construing buildings for the Regional Science Centre at Kozhikode, first appellant invited tenders. The estimated cost of the work was Rs. 55 lakhs. Time for carrying out the work was 12 months from the date of issue of letter of intent with an additional period of three months for piling work. Plaintiff was one of the tenderers pursuant to the invitation for tenders. Plaintiffs tender was accepted. By Ext. B 36, an agreement was executed between the plaintiff and the National Council of Science Museum through the second defendant on 4-1-1991. Ext. A2 is. the notice inviting tenders. One of the conditions in the notice is that the tenderers should furnish, among others, an earnest money deposit amounting to Rs.1,10,000/- in cash/Bank Draft/Bank Guarantee Bond from a nationalised Bank. By Ext. A1, letter of intent plaintiff had to execute an agreement on a stamp paper, avail mobilisation advance of 10% of the tender amount on furnishing bank guarantee recoverable from running bills at the rate of 10%. Ext. A3 is the Bank Guarantee furnished by the plaintiff pursuant to Ext. A1 letter of Intent and Ext. A4 is the Bank Guarantee furnished by the plaintiff pursuant to Ext. A2 notice inviting tenders.

4. The construction work carried on by the plaintiff was found to be not up to the expectation of defendants 2 and 3. Ext. B33 letter dated 11th October, 1992 was issued to the plaintiff informing him that the plaintiff has neither the capacity nor the infrastructure to complete the work and therefore, the stipulation of the contract provision would have to be operated upon. The third defendant, by Ext. B2 letter dated 2-1-1992 (addressed to the first defendant) invoked the two Bank Guarantees Exts. A3 and A4 and demanded the Bank, the amounts due under the Bank Guarantee.

5. The Bank did not reply to Ext. B1 and so, a reminder was sent on 18-11-1992. In Ext. B1 (a) it was pointed out that more than a fortnight has elapsed after the request made in Ext. B1 invoking the Bank Guarantee No. 31/30 dated 9-1-1991 extended upto 9-1-1993 and 31/23 dated 20-10-1990 extended upto 20-1-1993 respectively, amounting to Rs. 6,28,746/- and that they have neither received the requisite Demand Draft nor any official communication. Further, it was noted that the matter is urgent and so, the bank was asked to forward the necessary crossed demand draft drawn in favour of the National Council of Science Museums, payable at Calcutta immediately in terms of the subject Bank Guarantees.

6. The Bank informed defendants 2 and 3 that the plaintiff has filed a suit O.S. No. 910 of 1992 and in I.A. No., 5930/92, an order of injunction was passed by the court on 10-4-1992 restraining the Bank from encashing the Bank guarantee. It is stated that the appellants-defendants 2 and 3 came to know about the impugned order w



















































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top