SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Ker) 58512

IN THE HIGH COURT OF KERALA AT ERNAKULAM
ZIYAD RAHMAN A.A.TH, J
P.C. Thankachan – Appellant
Versus
State of Kerala – Respondent
WP(C) NO. 20594 OF 2024



Advocates:
For the Appellants/Petitioners: Shri.BLAZE K.JOSE, Shri.NIKHIL SANJAY, Smt.TREESA ROSE, Smt.AIRINE JOBY
For the Respondents: Shri.ARUN AJAY SHANKAR

The court emphasized that public authority's arbitrary termination of a contract without following due procedures violates principles of fairness and justness, meriting judicial intervention.

Headnote:(A) Contractual Law - Terms of Contract - Termination due to delay - The decision to terminate the contract is not compliant with enabling clauses of the contract and may be seen as arbitrary and unreasonable, considering that the petitioner was willing to complete the work if the respondents provided necessary cooperation. (Para 6, 12, 18, and 30)

(B) Jurisdiction of High Court under Article 226 - Judicial Review - The High Court can interfere in contracts involving public authorities if actions are arbitrary or unreasonable, reflecting a significant shift in legal interpretation. The Supreme Court's observations regarding public authorities' obligations are essential for contract sanctity. (Para 22, 56, and 65)

Facts of the case:
The petitioner, an A Class contractor, was engaged for road improvement works but faced delays caused by external factors such as shifting utility lines. The contract was terminated before completion time despite the petitioner's willingness to comply, leading to arbitrariness allegations.

Findings of Court:
The court found that the termination was premature and not justified under contract terms. The contract's termination was upheld, but without penal consequences on the petitioner.

Issues: The primary issues were whether the requisite conditions for contract termination were met and the extent of arbitrariness in the actions of the public authority.

Ratio Decidendi: The court ruled that the termination of contract prior to the expiry without justifiable grounds constitutes unfairness and can be challenged under Article 226. The presumption of arbitrariness lies with the procedures followed by the public authority.

Result: Writ petition allowed in part; termination upheld but without imposing liability.

Table of Content
1. dispute arises from contract performance delays. (Para 2 , 3 , 4)
2. arguments presented on contract justification. (Para 10 , 11)
3. discussion on arbitrariness and unreasonable actions. (Para 12 , 26 , 30)
4. judicial review enables challenge of public authority decisions. (Para 22 , 24)
5. writ petition results in partial allowance. (Para 31)

JUDGMENT

The petitioner is an A Class contractor under the Public Works Department. The dispute involved in this writ petition pertains to the order of termination of the contract entered into between the petitioner and the 2nd respondent, at the risk and cost of the petitioner, before the expiry of the contract.

2. The facts that led to the filing of this writ petition are as follows; As per Ext.P1 agreement, the petitioner entered into a contract with the 2nd respondent, based on the tender notification published by the said respondent, for carrying out the work of improvement to Thamarachal - Malayidamthuruthu Road by providing BM and BC from chainage 2/950 to 5/000 - General Civil Work. Ext.P1 was executed on 26.10.2022 and consequently, the site was handed over to petitioner on 05.11.2022. As per the terms of contract, the petitioner was supposed to complete the work within nine months i.e., on or before, 04.08.2023. According to the petitioner, the work mainly included widening of the road from 3.8 meters width to 5.5 meters width by providing Granular Sub Base (GSB) and then Wet Mix Macadam (WMM) to be laid for the entire road and later Bitumen Macadam (BM) 5 centimeter and Bitumen Concrete (BC) 5 centimeters. Drainage facilities were to be provided by constructing M20 side wall drain of 15 cm thickness. Culverts along the road for cross drainage. Already existing damaged culverts were to be reconstructed.

3. The case of the petitioner is that, for carrying out the said works, shifting of utility lines such as, Kerala Water Authority pipelines, telephone cables, some electric posts and transformers were necessary. Since the shifting of such facilities was beyond the scope of the work entrusted to the petitioner, the petitioner approached the authorities to facilitate the same, but there was delay in carrying out the same, at the instance of the respondents. It is also pointed out that, in such circumstances, the petitioner remitted an amount of ₹1,28,283/- to the KSEB, towards the expenses for shifting the electric poles, as evidenced by Ext.P4. Thereafter, when he was proceeding with works, certain communications were issued by the respondents, alleging that the petitioner is not carrying out the work as per the time schedule submitted by the petitioner in this regard. According to the petitioner, the said communications were at the instance of local MLA.

4. Ultimately, in the meeting convened by the Superintendent Engineer, the 2nd respondent, on 22.06.2023, after discussing the matter, a decision was taken by the 2nd respondent, terminating the contract of the petitioner, at his risk and cost. It is to be noted that, Ext.P6 decision was taken on 22.06.2023, whereas the time to complete the work was till 04.08.2023. Consequent to the decision taken as per Ext.P6, Ext.P8 order was passed terminating the contract at the risk and cost of the petitioner and it was also intimated that, the amount to be payable by the petitioner towards the damages shall be fixed in due course and would be intimated to the petitioner.

5. Ext.P8 was challenged by the petitioner, by filing W.P(C) No.21705/2023 and this Court, as per Ext.P10 judgment, disposed of the writ petition, by setting aside Ext.P8 on the ground that, the decision taken therein was without giving the petitioner an opportunity for being heard. The relevant observations in this regard is extracted below:-

6. Normally, when a contract is terminated at the risk and cost of a contractor, he ought to be given an opportunity of being heard and of furnishing his views against such action. This is particularly, where the petitio

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top