SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Ker) 58954

IN THE HIGH COURT OF KERALA AT ERNAKULAM
P.M.MANOJ, J
K.DINESH KUMAR – Appellant
Versus
THE DISTRICT COLLECTOR, PALAKKAD – Respondent
WP(C) NO. 25165 OF 2017 | WP(C) No. 19242 of 2017



Advocates:
For the Appellants/Petitioners: Dr.George Abraham
For the Respondents: Government Pleader, Sri.Ajit Joy, SC, Kerala State Electricity Board Limited, Sri.Aneesh James

The Court mandates reassessment of pole usage and adherence to statutory requirements before Revenue Recovery proceedings can proceed.

Headnote:This judgment concerns the petitions under WP

(C) No. 25165 and WP

(C) No. 19242 of 2017 regarding a demand for pole rentals based on unauthorized use. The petitioner challenged the district's assessments and Revenue Recovery proceedings initiated against him for unauthorized pole usage. The Court recognized the contractual basis of the dispute and indicated the need for a reassessment of the actual poles utilized, emphasizing adherence to legal standards and the principles of natural justice. The final direction settled the ongoing Revenue Recovery proceedings while allowing for potential reassessment based on established legal protocols.

Table of Content
1. unauthorized use of poles leads to assessment of rental charges. (Para 1 , 2)
2. revenue recovery initiated due to unpaid fees despite partial compliance. (Para 4 , 5)
3. dispute over actual pole usage and rentals charged. (Para 7 , 8)
4. petitioner contends charge legality and procedural adherence. (Para 9 , 10)
5. court emphasizes contractual obligations and authority verification. (Para 11 , 12 , 13 , 14)
6. reassessment directive to ensure natural justice. (Para 15)

JUDGMENT

The petitioner operates a cable TV network in and around Shornur and Ottappalam areas. The issue in WP(C) No.19242 of 2017 concerns a demand raised by the 3rd respondent regarding the unauthorized use of electric poles for stringing cables. Following a failure to remit the demanded amount, Revenue Recovery proceedings were initiated, which are now under challenge in both writ petitions.

2. In this regard, the petitioner entered into agreements with the 3rd respondent, as evidenced by Exhibits P1 to P3. Based on these agreements, the 3rd respondent sanctioned the use of 238 electric poles. The petitioner admits to utilizing an additional 144 poles and has submitted a representation regarding this matter. However, the 3rd respondent—allegedly ignoring the Assistant Engineer’s report—determined that the petitioner had used 347 poles between the years 2011-12 and 2016-17.

3. Accordingly, a sum of ₹6,71,185/- was assessed via Ext.P4.

Aggrieved by this, the petitioner submitted a representation and challenged the order before this Court. Following the dismissal of that challenge, the petitioner preferred an appeal, which was disposed of via the judgment in Ext.P6. In that judgment, the Court directed the 3rd respondent to determine the exact number of unauthorized poles for which rental charges were due. This assessment was to be conducted by the respondent or an authorized officer, with due notice to the appellant. Based on the findings, the respondents were permitted to raise a demand, which the appellant was to satisfy within a stipulated timeframe. Consequently, an inspection was conducted, which revealed that the petitioner had erected new poles for cable TV routing without maintaining the statutory clearance from electric lines. While the respondent directed the petitioner to clear the resulting arrears, the petitioner has raised an objection to these findings.

4. Subsequently, a further inspection conducted in the presence of the petitioner’s representative revealed that 538 electric poles under the Shornur Section were being utilized for routing cables. It was also found that the petitioner had erected independent iron poles without maintaining the required statutory clearance from the electric lines. The petitioner thereafter remitted ₹75,000/- as an ad-hoc payment under protest toward the pole rentals. Under Ext.P14, it was clarified that of the 538 poles utilized, 304 were unauthorized (excluding the 234 sanctioned posts). The petitioner was directed to submit further clarifications, if any, before 10.04.2017, however, no response was received. Consequently, after credit was given for previous payments totalling ₹97,798/-, the petitioner was directed to remit the remaining balance of ₹3,33,141/- by 31.05.2017 to avoid Revenue Recovery (RR)

proceedings.

5. The petitioner was further informed that information obtained under the Right to Information Act revealed absence of permission from the Shornur Municipality and a failure to maintain requisite statutory clearances. Despite being cautioned that they would be held liable for any accidents arising from these violations, the petitioner did not respond. This led to the demand raised via the invoice dated 08.05.2017, which is challenged herein. Following the failure to remit the said amount, RR proceedings were initiated, which are currently under challenge in WP(C) No. 25165 of 2017.

6. The petitioner’s primary contention is that he utilized only

382 electric poles in total. Of these, 238 are

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top